ITEM 3.4D Streets Project 18-01OtSTY F(/ 0 MINN65OTA ! 7 DEPARTMENT INFORMATION Request for City Council Action ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: ` Public Works City Engineer Wagner November 26, 2018 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.4D (1 I[o7k MEETS: THE CITY OF,OTSEGO: ARE YOU SEEKING' APPROVAL OF'A CONTRACT? Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. BACKGROUND/J USTIFICATION: Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. SUPPORTING DOCUMENTS ATTACHED: Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: Staff recommends approval of Pay Estimate #3 (Final) in the amount of $6,702.42 for the 2018 Street Maintenance Project, City Project No. 18-01 to Pearson Bros, Inc. ARE YOU SEEKING' APPROVAL OF'A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/J USTIFICATION: The 2018 Street Maintenance Project has been completed. Pay Estimate #3 is for $6,702.42. Total Construction Cost is $381,237.60, which is 99.97% of the original bid of $381,332.68. SUPPORTING DOCUMENTS ATTACHED: • Final Payment (PE #3) POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE ITTO APPEAR IN THE MINUTES: Motion to approve Pay Estimate #3 (Final) to Pearson Bros, Inc. in the amount of $6,702.42 for the 2018 Street Maintenance Project, City Project No. 18-01. BUDGET INFORMATION FUNDING: BUDGETED: Fund #201- Pavement Management I Yes FINAL PAYMENT CITY OF OTSEGO 2018 Street Maintenance Project City Project # 18-01 November 20, 2018 Honorable Mayor & City Council City of Otsego 13400 90th Street NE Otsego, MN 55330 RE: 2018 Otsego Street Maintenance Project Contractor: Pearson Brothers, Inc. ContractAmount: $381,341.58 Award Date: March 12, 2018 Completion Date: Sepember 15, 2018 Dear Honorable Mayor and Council Members: The following work has been completed on the above -referenced project by Pearson Brothers, Inc. ITEM NO. ITEM DESCRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNIT PRICE CONTRACT AMOUNT USED TO DATE EXTENSION 1 BITUMINOUS MATERIAL FOR FOG SEAL - CSS -1H DILUTED 32,877 GAL $0.89 $ 29,260.53 26,900 $ 23,941.00 2 BITUMINOUS MATERIAL FOR SEAL COAT (CRS -2P) 58,425 GAL $2.55 $ 148,983.75 62,114 $ 158,390.70 3 SEAL COAT AGGREGATE (FA -2) 278,214 SY $0.49 $ 136,324.86 270,061 $ 132,329.89 4 TRAFFIC CONTROL 1 LS $43,000.00 $ 43,000.00 1 $ 43,000.00 Total Bid Schedule "A" $ 357,669.14 $ 357,661.59 ITEM NO. ITEM DESCRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNIT PRICE CONTRACTUSED AMOUNT TO DATE EXTENSION 5 PAVEMENT MESSAGE (ARROW) - PAINT 102 EACH $ 21.00 $ 2,142.00 107 $ 2,247.00 6 PAVEMENT MESSAGE - PAINT 4 EACH $ 79.00 $ 316.00 8 $ 632.00 7 4" DOUBLE SOLID LINE YELLOW - PAINT 74,891 LF $ 0.10 $ 7,489.10 5,305 $ 530.50 8 4" BROKEN YELLOW - PAINT 1,686 LF $ 0.07 $ 118.02 1,651 $ 115.57 9 4" SOLID LINE YELLOW - PAINT 10,181 LF $ 0.04 $ 407.24 151,522 $ 6,060.88 10 4" SOLID LINE WHITE - PAINT 135,554 LF $ 0.05 $ 6,777.70 143,572 $ 7,178.60 11 4" BROKEN LINE WHITE - PAINT 1,536 LF $ 0.10 $ 153.60 221 $ 22.10 12 12" SOLID LINE WHITE - PAINT 1,240 LF $ 1.00 $ 1,240.00 640 $ 640.00 13 24" SOLID LINE WHITE - PAINT 764 LF $ 2.30 $ 1,757.20 774 $ 1,760.20 14 24" SOLID LINE YELLOW - PAINT 185 LF $ 2.00 $ 370.00 64 $ 128.00 15 CROSSWALK MARKING (3'X6' BLOCKS) - PAINT 2,934 SF $ 1.02 $ 2,992.68 4,158 $ 4,241.16 Total Bid Schedule "B" $ 23,763.64 Bid Schedule "A" Bid Schedule"B" TOTAL ALL BID SCHEDULES TOTAL WORK COMPLETED TO DATE LESS PAY ESTIMATE #1 LESS PAY ESTIMATE #2 WE RECOMMEND PAYMENT OF Please verify the amount of previous payments, and the receipt of the following items prior to making payment. 1. Certificate of claims payment (lien waiver), 2. Affidavit of payment of States taxes (MN Stale TAX Form IC 134), 3. Letter of consent from surety firm. APPROVALS: CONTRACTOR: PEARSON BROTHERS, INC. Certification by Contractor: I certify that all items and amounts are correct for the work completed to date. ENGINEER: HAKANSON ANDERSON ASSOCIATES, INC. Certification by Engineer: We recommend payment for work and quantities as shown. Title: Date OWNER: CITY OF OTSEGO Title: 07387-2018 SMP PE.xisx PE - 1 $ 367,569.14 $ 23,763.64 $ 381,332.68 $ 23,676.01 $ 357,661.59 $ 23,576.01 $ 381,237.60 $ 381,237.60 $ 338,163.73 $ 36,381.45 $ 6,702.42