ITEM 3.11A Pay Estimate #6 Municipal Builders40 ots 7e F O MINN1aoTA g DEPARTMENT INFORMATION Request for City Council Action ORIGINATING DEPARTMENT REQUESTOR: " 'MEETING DATE: Public Works City Engineer Wagner October 26, 2020 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.11 (A) STRATEGIC VISION MEETS: THE CITY, OF_OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff recommends City Council approval of Pay Estimate #6 (Final) to Municipal Builders, Inc. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: All work has been completed to the satisfaction of City staff and Well #9 is now in use. The contractor has submitted Operation and Maintenance Manuals and submitted all required IC134's, lien waivers and consent of surety. Final construction cost is $582,600.12. Total contract amount of the project including change order #1 and minor work orders #1-3 was $606,204.12. SUPPORTING DOCUMENTS ATTACHED: 0 Pay Estimate #6 (Final) POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to approve Pay Estimate #6 (Final) in the amount of $29,130.01 to Municipal Builders, Inc., for work completed on the Well #9 and Pumphouse #1 Improvements, City Project No. 20-04. BUDGET INFORMATION FUNDING: BUDGETED: Fund 601- Water Utility Yes PAY ESTIMATE #6 CITY OF OTSEGO Well #9 and Pumphouse #1 Improvement Project October 18, 2020 Honorable Mayor & City Council City of Otsego 13400 901h Street NE OlaegD, MN 05330 RE: Wet q9 and Pumphouse #1 Improvement Project Contractor. Municipal Builders, Inc. Award Dale: Mar 24, 2020 Compleaoa Date: July 9, 2020 Dear Honorable Mayor and Council Members: The following work has been completed on the abova-referenced project by Municipal Builders, Inc. ITEM No, ITEM DESCRIPYION ESTIMATED QUANTITY UNIT CONTRACT UNrTPRICE CONTRACT AMOUNT USEDTO DATE EXTENSION 1 Mobilization 1 Ls $27,000,00 $27,00a.0a 1.00 $27,000.00 2 Remove Watermaln Prossum Volvo Manhole 1 EA $1,200.00 $1200.00 0.00 $o.a0 3 Removal & Disposal ofEIs"Antenna, Trunsfarmer, Elecidcal Meter 1 LS $1,150.00 $1,160.00 0.00 $0,0o 4 Cut Off and Dispose Existing Abandoned Wall Pips 1 Ls $11500.00 $1,500.00 0.37 $555,00 5 Abandon Dialing ill Pipe lnplece and Cap at Main i LS $11800,00 $1,600.00 1,00 $1,800,00 e hMll 81lurnimuis Surface(1.8'Thlok) 14 SY $30.00 $420,00 0.00 $0.00 7 SaWno Bituminous Pavement (Full Depth) 40 LF $316g $140.00 40.00 $140.00 8 Remove ultundnaus Pevamanl 3S SY $8.00 $280.00 35,00 $280.00 9 Remove Chain Link Fare 120 LF $10.00 $1200.00 0.00 $0,00 10 salvage Aggregate Saso Close 6 28 CY $1200 $330.00 28.00 $338.00 11 Sllaaredkw i La $2,560.00 $2,500.00 1.e0 $2,600.00 12 Class 5 Aggregate Basa 122 TON 1 $28100 $3,4181Og 110.00 $3.332.00 13 Type SP 12.5 Non Weadno Cou sa Mixture, (2,8) 66 TON $t45.00 $9,670.00 64.00 59,260,U0 14 Concrete Pad wish conduits (a' Thick) 48 SP $80,00 $2,880.00 46,00 $2,860.00 is Install Oollards(CRY Supplied) 4. FA $400,00 $1,600.00 4.00 $1,600.00 18 C*nnadTaE"agwatarmah 1 LS $1,200.00 111200.00 1Aa $1200.0a 17 Install l0'Os10 Valve and Box 1 LS $3,800,00 $3,800.00 1A0 $3,800.00 18 Ductile iron FdUngs 295 LOS KOO $1,710.00 286.001 S1,7f0,00 1S 10' Wetermala Ductile Iron CL 52 120 LF $13T.001 $16,440.001 120.00 $16,440,00 20 Ma Cleanup, EslebpsbmentTurfend Controft Erosion 1 LS I $3,500,00 $3,500.00 1.00 $3,500.00 21 Teating (P(ewuro and Bacteria) 1 I LS 1 $750.001 $760.00 1= I $750,00 Total Bid Schedule "A7 $82,392.00 $77,103,00 ITEM NO, ITEMOESCRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNIT PRICE CONTRACT AMOUNT USEDTO I OATR EXTENSION 22 Dill& Drive 24' Casing 60 LF slosm $151800.00 81.00 $15.705.00 23 Dill23' Open Hot* 253 LF $165.00 $41,746.00 168.00 $27,720.00 24 Fumish&Insta9181 cwhg 255 LF $9540 $24,220,00 249.00 $23,055,00 25 Finnish &Install Grout 20 CY $650.00 $131000.00 20.00 $13,000.00 28 Drift 17' Open Hula 83 LF $125.00 $10,376.00 78,00 $9,600,00 27 Plumb and Alignment 1 LS $500,00 $500.00 1.00 $500.0o 28 Furnish, Install and Ram*va Development Equipment 1 LS $3,500.00 $3,600.001 1.00 $3,6D0,00 29 Well cevel*pment s0 FIRS $395A0 423,700,001 00.00 $23,700.00 30 Haul Stand5tone Away 25 CY $14,00 $350.00 0.00 30.00 31 Furnish and Install Wet Sciaon&Gravel Pack 75 LF $325.00 $24,376.00 80.00 $23,000.00 32 PRless/Wepter 1 LS $84,500.00 $84,500,00 1.00 $64,500.00 33 Discharge piping 10, Us 250 LF S6A0 $1,600.00 290.00 $i,600,00 34 Dlsohargo Too on its' caeing, Flgo Cop 1 LS 4825.00 $82$.00 1.00 $025,00 35 JFUIWsh and Install 12S HP Pump and Motor i Ls $69252,00 369,252.00 1.00 $89,252.00 38 Furnish, Install end Remove Test Pump Equipment Y LS $0,600.00 $8,600.00 1.00 $a,500,00 37 Test pumping 200 KW&ISO HP Pump 50 HRS $195.00 $9,750.00 33.00 $8,435.00 38 Water Analysts STD Me nu WM Radkmucrdidds 1 LS $1,850.80 $1,850.00 1.00 $1'650.00 39 Data Logger For Test Pump Rocordmg 1 EA $326.o0 $326.00 1.00 $325.00 40 Video Log i L3 $1,400.00 $1,400.00 1.00 $IA00.00 41 Gamma We 1 LS $1,80D,00 $1,e00.0n 1.00 $11900,00 42 O&M manual/Wall Report 1 LS $176.00 $176.00 1.00 $176,00 Total BId 8ohedu10"W $335,247.00 4317,932.00 PAY ESTIMATE #5 CITY OF OTSEGO Well #9 and Pumphouse #1 Improvement Project REM NO. ITEM DESCRIPTION ESTIMATED QUANTITY UNIT 0 NTRAOT 1 UNITPRICE CONTRACT AMOUNT USEDTO DATE EXTEN8ION 43. Remove Existing Pumphouse Pipe and Appiurtaaances i LS $4,000.00 $4,000.00 1.00 $4.00D,00 44 Furnish and Install Ductile Iron Plea and APpurtenancm 1 LS $20,000,00 $20.000.00 1.00 $20.00.00 45 Im1a08'Badgar Ma9 Meter (Cgy sOppllad) 2 FA $400.00 $000.00 2.00 $6000 46 Painting Ardor Repaint All Ductile Iron Pipe I LS $3,000,00 01000,00 1.00 $3.000.00 47 Testing (Pressure and Bacteria) 1 LS S1,000.00 $1,000.00 0.00 $0,00 Total Old Schedule`C" $28,800.00 $27,800.00 ITEM NO. ITEM DRACRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNITPRICE CONTRACT AMOUNT USED TO DATE EXTENSION 48 Control Panolw/VFD and Coabols+tnsbuments 1 LS $00,W0.Q0 $60,000.00 1.00 $80,000,60 49 Panel Disconnect SW 1 LS 45,980.00 $5,960,00 11.00 45'"0.00 60 Generator Receptacle i LS $1,933,00 $1,933.00 1,00 $1,933.00 51 Electrical Mob, Circulhy, and lnsbd# miss. 1 LS $8,110.00 $5,110,00 1.00 46,110.00 52 Furnish and lnalali Antenna Pole 1 LS $1,800.00 $1,600,00 1.00 $11800,00 b3 ElecMcalMdn OpOA Feeder In Conduct 176 LF $51.00 $8.025.00 175.00 $8,925,00 Total Bid Schedule "D" $100,728.00 $106,728,00 Total Bid Sohoduis - Minor Work Order#1 $4,759,61 $4,756.61 Bid Schedula - Minor Work Order 92 fTEM. ESTIMATED NO, ITEMDESCRIPTION QUANTITY UNIT CONTRACT UNITPRICE CONTRACT AMOUNT USED TO DATE I EXTENSION 1 Dawatedngetnon- oteblewalermain connec8onln Ctim 42d8ch I 1 LS $7.9w.001 $7,980.001 1.001 $7,880,00 Total Bid Schedula- Minor Work Ordar#2 $7,960.00 $1,080.00 Old Schedule • Minor Work Ord.rO ITEM No, ITEM DESCRIPTION ESTIMATED CVANTIIY UNIT CONTRACT UNITPRICE CONTRACT AMOUNT USED TO DATE EXTENSION 1 110, gate valve 1 EA $6,090,001 S6,M.001 1.00 1 $6,090.00 Total Bid Schedule -Minor Work Order#3 $6,0$0,00 $6,090.00 ITEM NO, ITEM DESCRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNIT PRICE CONTRACT AMOUNT USEDTO DATE EXTENSION 1 Wall#2 Line Double Check Valve Assembly 1 LS $ 0,556.66 $10.656.66 1.00 $10,558,88 2 We11#9 Lino Double Chock Valve Assembly 1 LS $10.556,66 $10.556,06 I= $10,656,BB 3 Wall#6 Lino Double Chock Valve Assembly 1 LS $131097.29 $13.097.20 1.00 $13,09729 Total Bid Schedule -Change Order#1 $34,210.61 $34,230,61 Tolai Bid Schedule "A" $82,392.00 $77,103.00 Total BidSohedute"B" $335,247.00 $317.932.00 Total Bid Schadule"C" $28,500.00 $27,600.00 Total BidBchoduto"D" $106,728,00 $108,728.00 TOTAL BID SUMMARY $563,167.00 $529,663.00 Total Minor WorkOrdar#1 -$4,766.61 $4,756.51 Total Minor Work order#2 $7,980.00 $7,9BO,00 Total Minor Work Order#3 $8,090,00 $0,090.00 Total Change Order#1 $34,210.81 $34,210.61 TOTAL APPROVED PROJECT $806,204,12 $682,600.12 TOTAL WORK COMPLETED TO DATE $582,800.12 LESS Pay Estimate 111: $24,226.00 LESS Pay Estimate 92t $41,11$,70 LESS Pay Estin ate#3; $123,830.60 LESS pay Estimate 04: $246,810.45 LESS Pay Estimate, 051 $118,410.40 WE RECOMMEND PAYMENT OF: 129,130.01 PAY ESTIMATE #6 CIT`! OF OTSEGO Well #9 and Pumphouse 41 Improvement Project Please verify the amount of previous payments, and the receipt of the following Items prior to malting payment. 1. Certirioate o(clatms payment (Iten waiver). 2. Affidavit of payment of stele taxes (MN Slate Tax Form IC 134). APPROVALS: CONTRACTpFjI MUNICIP BOIL ERS, INC. CertiH i aelo , artify ,aLall Ite nd amounts are correct for the wo* wmpleled to date, Signed: 0 C-'C3G'�' Tttie: ATAwk Data ENGINEER; NAKANSONANDERSONAS C ,INC, Certification e m d Ill for work and quantities as shown. Slgned:_6ralG�!L� - Title: iF r Orwy • Date G— L�FOZ C7 OWNER; CITY OFOTSEGO / Tula: Date