09-27-10 SCCITEM 3_1
SPECIAL CITY COUNCIL MEETING
MONDAY, SEPTEMBER 27, 2010
OTSEGO CITY HALL
6:30 PM
1. Mayor Stockamp will call the meeting to order.
Mayor Stockamp called the meeting to order at 6:30 PM.
Roll Call: Mayor Jessica Stockamp; Councilmembers: Vern Heidner, Dan Scharber and
Doug Schroeder. Councilmember Tom Darkenwald arrived at 6:55 PM.
Staff: Mike Robertson, City Administrator; Tami Loff, City Clerk; Gary Groen, Finance
Director; Daniel Licht, City Planner; Ron Wagner, City Engineer; Andy MacArthur, City
Attorney.
2. I- 4 AH 37 Improvement.
The City Council reviewed a draft response letter to the city of Albertville.
CM Heidner questioned Albertville's response regarding the access on CSAH 19
and that we are asking for stuff not in accordance with the Wright County
Transportation Plan. City Planner Licht said it is to do with spacing requirements.
City Engineer Wagner felt we were in compliance with county spacing
requirements.CM Scharber said he feels the interchange will benefit Monticello
Township as well. CM Heidner said he would like to see a traffic count with the
mall. Mayor Stockamp asked if we received any information on funding options
from the City of Albertville. City Administrator Robertson said no.
City Attorney MacArthur said he is having a hard time finding funding options
legally. He spoke with Mary Ippel and she mentioned possibly Street
Reconstruction Bonds. CM Scharber asked if we should change our offer to
$185,000 until they can prove how we can legally fund more. CM Darkenwald
said he is not sure why we need to write a three page response letter. CM
Heidner said the city's response needs to be on record. CM Darkenwald
questioned if the 1/8 maintenance and operation costs for traffic signals really
needs to be included in the letter. CM Heidner said he feels residents should
know our reasoning.
CM Heidner motioned to approve letter. Seconded by CM Schroeder.
CM Darkenwald said he is against sending a response. CM Scharber agreed. City
Council agreed to have staff review letter.
CM Heidner retracted his motion. Seconded by CM Schroeder.
3. Any other items.
No items.
4. Adjourn.
CM Scharber motioned to adjourn. Seconded by CM Darkenwald. All in
favor. Motion carried. Adjourned at 7:05 PM.
ATTEST:
Tam! Loff, City Clerk
Mayor Jessica Stockamp
Motion By CM Darkenwald, Seconded by CM Schroeder to provide funding to the
Proposed I-94/CSAH 19 Phase 1 interchange project as follows:
1. Otsego will participate in funding for the 1-94/CSAH 19 Interchange Phase
One Project up to $400,000.00 or 3.6 percent of the total project cost,
whichever is less. The $400,000.00 contribution is based upon the engineer's
estimate for the project and is the maximum that the City will contribute. In
the event that the bid for the project is below that estimate, Otsego's
contribution will be reduced and pro -rated at the same percentage as its
contribution to the unfunded portions of the overall project.
2. The funding mechanism for Otsego's contribution shall involve payment to
Albertville and/or Wright County one or both of which are expected tted to issue
financing bonds for the Phase 1 project or other structure and on a schedule
as approved by the Otsego City Council. If Otsego is to make payments to
Albertville and/or Wright County for the repayment of bonds, the payment
shall be at the lowest interest rate for which debt has been issued for the
project or loans acquired.
3. Otsego has determined to contribute to the Project on the front end even
though the benefit to Otsego, if any, would attach to Phase Two of the
Project which would establish a more efficient route to the east. The above
mentioned contribution is based upon Albertville's assurance that it will
proceed in good faith to complete Phase Two of the Project and have it
completed within three years from the date of this Agreement. Based upon
Otsego's contribution to Phase 1 of the project Albertville agrees that no
contribution from Otsego is expected for phase 2 of the Project. Otsego
would support any applications for funding from other sources.
4. Albertville has requested Otsego's contribution to this Project even though
the portion of the Project that is actually within Otsego's jurisdiction is
extremely small. Otsego is making the above contribution based upon
potential limited future benefit to Otsego, in the spirit of cooperation
between the Cities and based upon the specific representations of Albertville
that they will actively cooperate with future projects within the City of
Otsego. In order to make the contribution Otsego needs to receive the
following consideration from Albertville:
a. Albertville will take action within six (6) months of an agreement
signed between the parties to include in its Comprehensive Plan and
official controls guidance to acquire needed right of way for a Kadler
Avenue Interchange at no cost to Otsego so that sufficient right-of-
way is acquired by either the platting process, official mapping or
otherwise by Albertville within the City of Albertville for the Kadler
Avenue Interchange Project.
b. Wright County, Albertville and Otsego will agree to allowed full and
limited right-in/right-out intersection locations for the future build out
of CSAH 19 between I-94 and 75"' Street and along 7& Street from
Maciver Avenue to 77t' Street.
C. Albertville agrees that Otsego's contribution to the Phase i project
relieves Otsego of any responsibility for the cost of traffic signals that
were installed by Albertville at the existing west bound exit from I-94
at CSAH 37 as Otsego was not asked for any contribution when the
traffic signal was installed.