Item 1. W WWTF 60% Design Progress ReportCouncil Study Session: West WWTF –60% Design Presented by: Advanced Engineering and Environmental Services, Inc. (AE2S) November 2021 West WWTF: Schedule •Preliminary Design January-June 2021 •MBR Pre-Procurement April 2021 •60% Design July-Nov 2021 •90% Design Nov 2021 –Feb 2022 •Final Design March-April 2022 •Bidding May 2022 •Construction Initiation June 2022 •Substantial Completion November 2023 •Final Completion December 2023 West WWTF / Project Quick Facts •Original Design/Construction: 2003/2004 •REC Capacity (flow based) –Current: 3,428 –Post-Project:8,057 –Ultimate Buildout: 24,000 •Treatment Type –Current: Bio-P Oxidation Ditch –Proposed: Full BNR Membrane BioReactor Odor Mitigation Area / Building Current Future (2023) Pretreatment GAC New GAC Fine Screen Building (New)N/A New GAC Pre-Aeration Tanks Covered Covered (New Tanks) WAS Thickening Indoors Indoors (no change) Aerobic Digestion GAC GAC (no change) Solids Storage Tank Remain Empty Remain Empty TWAS Loading Outdoors Indoors, Only Bottom Fill Noise Mitigation Area / Building Current Future (2023) Pretreatment Odor Fan Fence Sound Enclosure FSB Odor Fan (New)N/A Sound Enclosure Digester Odor Fan Sound Enclosure Sound Enclosure OxDitch Motors No Mitigation Decommissioned Existing Digester Blowers Indoors Indoors (no change) Process Blowers (New)N/A Indoors Membrane Blowers (New)N/A Indoors Effluent Aeration N/A Passive Aeration Funding Overview •State Revolving Fund (SRF) •PPL Score Improvement = Fundable Range •Green Project Reserve (GPR) •Point Source Implementation Grant (PSIG) •“Community Project Funding” •Federal Infrastructure Bill •SRF Capitalization, Specific Funding Regulatory / Permitting •NPDES Permit Re-issuance (main permit) –Preliminary Effluent Limits –Chloride Variance –Anti-Degradation Study –Environmental Assessment Worksheet •General stormwater, etc SITE LAYOUT West WWTF: Rendering PRETREATMENT BUILDINGS SECONDARY BIOLOGICAL TREATMENT Membrane Treatment Building Administration Building Administration Building Costs and Phasing DESCRIPTION WEST LIQUID PHASE 1 (WL1) Sept. 2020 WEST LIQUID PHASE 1 (WL1) 30% DESIGN WEST LIQUID PHASE 1 (WL1) 60% DESIGN Mobilization $1,402,000 $2,073,000 $2,071,574 Site Work $1,247,000 $1,738,000 $2,880,000 Influent Pump System $300,000 $226,000 $50,000 Preliminary Treatment Building $1,404,000 $1,077,000 $1,003,890 Fine Screen Building $2,565,000 $3,578,715 Convert Existing OD to Anaerobic Selector $348,000 Secondary Biological Treatment (SBT)$5,691,000 $6,197,550 Blower Building (BB)$1,050,000 $1,240,980 Membrane Treatment Building (MBT)$9,325,000 $5,500,000 $7,947,825 Tertiary Treatment Building (UV)$271,631 $412,000 $115,000 Effluent Aeration $546,000 $438,000 $201,260 Administration Building $1,650,000 $2,237,000 $2,802,795 PTB Biofilter Odor Control $312,592 Electrical $2,311,000 $2,550,000 Mechanical $1,232,000 $1,833,500 Instrumentation and Controls $1,078,000 $1,100,000 SUBTOTAL $21,427,233 $28,490,500 $28,089,589 Construction Contingencies $2,678,000 $2,849,000 $2,808,959 Undeveloped Construction Details $1,607,000 CONSTRUCTION SUBTOTAL $25,712,223 $31,339,500 $30,898,548 Engineering, Legal, Admin $4,371,000 $4,600,000 $4,600,000 OPINION OF PROBABLE COST $30,080,000 $35,940,000 $35,498,548 2021 (7.5% ENR Adjustment)$32,336,000 $35,940,000 $35,498,548 2022 (Additional 3% to Spring 2022)$33,306,000 $37,018,000 $36,563,505 COST DIFFERENCE $0 $3,712,000 $3,257,505 Potential GPR Grant ~$700,000 Costs and Phasing •Phasing Options Project Area Potential Modification Potential Cost Reduction Savings Influent Pump System Reduction in improvements for PH1 $182,700 Deferred Cost Secondary Biological Treatment (SBT)Reduce to two trains for PH1 $1,948,800 Deferred Cost Tertiary Treatment Building (UV)Alternate UV option $60,900 Reduced Cost Effluent Aeration Alternate EA option $304,500 Reduced Cost Administration Building For Discussion TBD Deferred Cost Total $2,496,900 Solar Array •Summary –electricity is too inexpensive ($0.0593/kwh plus demand) •Requires high assumed YoY electrical rate increases •East Facility –Xcel program pays back higher rate for solar incentive ($0.06/kwh “bonus”) Solar Array ($200,000) ($150,000) ($100,000) ($50,000) $0 $50,000 $120,000 $140,000 $160,000 $180,000 $200,000 $220,000 $240,000 $260,000 $280,000 Net Cumulative Cash Flow at the end of 20-year period“Profit” at End of 20-year period Given Electric Rate Increase and Initial Capital Cost 2.43%3.50%5.00% QUESTIONS? Otsego City Council Update WEST WWTF DESIGN •Construction Costs -Uncertain •Concrete •Materials WEST WWTF DESIGN -COSTS •ENR CCI –Construction Inflation •Building Cost Index –10.4% (12-mo) •Construction Cost Index –5.2% (12-mo) •“Composite” –7.5% (is that enough??) June 2021 Water/Wastewater Bids* Engineer's Estimate Low Bid +/- Northern MN (2 projects)$ 34,800,000 $ 44,246,508 Over 27% Central MN $ 5,000,000 $ 5,974,000 Over 19% Southern MN $ 22,000,000 $ 26,765,800 Over 22% *data courtesy of RLCG SOLIDS BUILDING –MODEL/RENDERING PROCESS FLOW DIAGRAM