4.1 Walesch Estates & O'Day Acres Street Renewal Project
Request for
City Council Action
DEPARTMENT INFORMATION
ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE:
Public Works City Engineer Wagner March 14, 2022
PRESENTER(s) REVIEWED BY: ITEM #:
City Engineer Wagner City Administrator/Finance Director Flaherty 4.1 – Street Renewal
Improvement Hearing
STRATEGIC VISION
MEETS: THE CITY OF OTSEGO:
Is a strong organization that is committed to leading the community through innovative
communication.
X Has proactively expanded infrastructure to responsibly provide core services.
Is committed to delivery of quality emergency service responsive to community needs and
expectations in a cost-effective manner.
Is a social community with diverse housing, service options, and employment opportunities.
Is a distinctive, connected community known for its beauty and natural surroundings.
AGENDA ITEM DETAILS
RECOMMENDATION:
City staff recommends the City Council conduct the Public Improvement Hearing for the Walesch Estates
and O’Day Acres Street Renewal improvement and approve a resolution ordering plans and specifications.
ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED?
No Yes – Will be held on March 14, 2022.
BACKGROUND/JUSTIFICATION:
Each year the City Engineer and Street Operations Manager review and score the entire existing street
infrastructure. Based on this review, the Capital Improvement Plan (CIP) is developed. This plan includes
street renewal projects prioritized towards the street infrastructure in the worst condition. For 2022, the
recommended project are the streets within Walesch Estates and O’Day Acres.
The streets within Walesch Estates (1st and 2nd Additions) and O’Day Acres are paved. All original streets
consisted of 3 ½” of bituminous over approximately 6” of class 5. Streets in Walesch Estates vary from 18’ to
22’ wide with ditches, while O’Day Acres is approximately 29’ to 30’ with bituminous curb. The pavement
is experiencing extensive block and thermal cracking as well as some alligator cracking and scabbing due to
its age.
The existing street surfaces in Walesch Estates and O’Day Acres have PCI (Pavement Condition Index) Ratings
of 33 and 45 respectively, both well below the average in the City of Otsego. Typically, pavements with PCI
Ratings 50 and lower are in their final stages of useful life and will need to be reconstructed or overlaid in
the very near future.
In addition to reclaiming and paving the streets, existing centerline culverts will be replaced as necessary.
Some existing ditches will also be regraded to provide better drainage.
City Council authorized the preparation of a Feasibility Study to determine what needs to be completed to
remedy the issues, determine a cost estimate and allocate costs. An open house was held March 10th to
provide residents a less formal opportunity to review the project and discuss the project with the design
team. A public hearing is being held to present the study to the residents. The City Council will hear resident’s
comments or concerns regarding the possibility of continuing toward a project and with regard to the
potential for assessments in accordance with MN State Statue 429 and City Policy.
After the public hearing is closed, the City Council will determine whether to move forward with the project
by considering approval of a resolution authorizing preparation of plans and specifications. If approved, the
plans and specifications will be considered for approval by the City Council at a future meeting, where staff
would be seeking authorization to bid the project.
The total estimated project cost is $991,711 and is proposed to be funded using approximately 12%
assessments and 88% City funds. The CIP estimate was $895,304.33.
SUPPORTING DOCUMENTS ATTACHED:
• Feasibility Report
• Resolution 2022-26
POSSIBLE MOTION
PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES:
Motion to approve Resolution 2022-26 Ordering Preparation of Plans and Specifications for the 2022 Street
Renewal Improvement of Streets within Walesch Estates and O’Day Acres.
BUDGET INFORMATION
FUNDING: BUDGETED:
Fund 201 – Pavement Management
Yes
FEASIBILITY REPORT
FOR
2022 OTSEGO STREET RENEWAL PROJECT
WALESCH ESTATES & O’DAY ACRES
PROPOSED STREET RECONSTRUCTION
CITY OF OTSEGO, MINNESOTA
FEBRUARY 2022
Prepared by:
3601 Thurston Avenue
Anoka, MN 55303
Telephone: 763-427-5860
I hereby certify that this plan, specification or report was prepared by me or under my
direct supervision and that I am a duly Licensed Professional Engineer under State of
Minnesota Statutes Sections 326.02 to 326.16.
26052 February 14, 2022
Ron J. Wagner, P.E. Reg. No. Date
TABLE OF CONTENTS
TITLE SHEET
TABLE OF CONTENTS
I. INTRODUCTION ....................................................................................... 1
II. PROPOSED PROJECT ............................................................................ 5
III. INITIATION ................................................................................................ 6
IV. FEASIBILITY ............................................................................................. 6
V. RIGHT-OF-WAY / EASEMENTS ............................................................... 7
VI. PERMITS .................................................................................................. 7
VII. COMPLETION ........................................................................................... 7
VIII. PRELIMINARY PROJECT SCHEDULE .................................................... 7
IX. ESTIMATED PROJECT COST ................................................................. 7
X. PROPOSED FUNDING ............................................................................. 8
XI. ESTIMATED ASSESSMENT ..................................................................... 9
XII. CONCLUSION AND RECOMMENDATION .............................................. 9
EXHIBITS
LOCATION MAP .................................................................................................. A
PROPOSED STREET SECTION ......................................................................... B
ENGINEERS ESTIMATE .................................................................................... C
BENEFITING PROPERTIES LIST ....................................................................... D
BENEFITING PROPERTIES MAP ....................................................................... E
1
I. INTRODUCTION
The purpose of this Feasibility Report is to present the City of Otsego with
a preliminary examination of municipal street improvements for streets within the
Walesch Estates & O’Day Acres subdivision in Otsego, Minnesota.
Project Location Map
The report discusses the proposed scope of improvements, preliminary
cost estimates, and a project schedule. The report has been prepared in
compliance with Minnesota State Statutes 429 for projects resulting in special
assessments.
2
Walesch Estates was constructed in 1978 and overlaid in 1999. The
conditions of the streets within Walesch Estates have deteriorated to a point that
a full depth reclaim is recommended. The existing streets were constructed with
ditches and culverts to provide drainage. The cost and time associated with
patching necessary to maintain the streets is increasing and becoming
substantial.
O’Day Acres was constructed in 1994. The conditions of the streets within
O’Day Acres have deteriorated to a point that a full depth reclaim and
reconstructing with new concrete curb and gutter is recommended. The existing
streets were constructed with a bituminous curb and minimal storm sewer. The
cost and time associated with patching necessary to maintain the streets is also
increasing and becoming substantial.
The existing street surfaces within Walesch Estates have a PCI
(Pavement Condition Index) Rating of 33 and O’Day Acres have a PCI Rating of
45, which is well below the average in the City of Otsego. Typically, pavements
with PCI Ratings of 50 or less are in their final stages of useful life and will need
to be reconstructed or overlaid in the very near future.
3
4
The Walesch Estates & O’Day Acres streets have been included on the
Street Renewal plan and included in the Capital Improvement Plans (CIP) for
several years. Due to this, the City Council authorized a Feasibility Report be
completed to determine costs and potential sources of funding.
PCI RATING MAP – 2022
The original streets in Walesch Estates were constructed with 3½” of
bituminous over 6” of class 5 gravel with ditches and culverts to provide
drainage. The streets are 18-22’ wide. A seal coat was applied in 2005. The
original pavement is 44 years old now with an overlay 23 years ago. At this time
the streets are experiencing extensive block and thermal cracking and the edges
are experiencing alligator cracking. Therefore, it is recommended to reconstruct
the streets at this time.
The original streets in O’Day Acres were constructed with 3½” of
bituminous over 6” of class 5 gravel with bituminous curb and approximately 29’-
30’ wide. A seal coat was applied in 2005. The original pavement is 28 years
old now. Normally an overlay would be recommended at this time, but with the
adjacent larger project receiving a reconstruct, this short stretch would be better
served to be reconstructed as well. In addition, the City would like to eliminate
asphalt curbing as concrete curbing is advised.
5
II. PROPOSED PROJECT
The proposed street improvement project consists of improving streets
within Walesch Estates and O’Day Acres, specifically 82nd Street NE, 81st Street
NE, 79th Street NE, 78th Street NE, O’Day Ave NE, Ochoa Ave NE, O’Brian Ave
NE, and O’Day Circle NE. Proposed improvement work includes full depth
reclaim; evaluating existing center line culverts and storm sewer and replacing as
needed; shaping and compaction of the reclaimed material; regrading
problematic ditches, and lessening the most sever ditch slopes; placement of
3½” of bituminous in two lifts; and placing gravel shouldering, restoring with a
topsoil, seeding, and hydro-mulching. The proposed street typical section within
Walesch Estates would be constructed to a standard width of 10’ paved lanes
with 1’ grave shoulders. This is not in conformance with any current City
Standard but the cost for upgrading existing rural streets to current City standard
would be exorbitant. O’Day Circle typical section will be reconstructed to current
standard of 28’ wide with concrete curb and gutter and will be in general
conformance with the current City urban standard.
In general, the street will stay at its existing elevation. Existing bituminous
driveways will be milled approximately 2’-5’ back from the edge of the road and
match the street elevation. Where necessary, concrete driveways will be saw cut
at a joint and replaced to match the new street bituminous elevation. All other
gravel driveway will have gravel material added to match the new bituminous.
Walesch Estates Typical Section
6
O’Day Acres Typical Section
Surface water within the project area will be conveyed via the ditch and
culvert system. Center line culverts will be inspected and replaced if they are in
poor condition or are corrugated metal pipes. O’Day Acres bituminous curb will
be replaced with concrete curb and gutter. The exiting storm sewer at the north
end of the cul-de-sac will be inspected and rehabbed if necessary.
III. INITIATION
The feasibility report was initiated by the City Council due to the PCI
ratings in accordance with the city’s policy regarding streets renewal program.
IV. FEASIBILITY
The project necessary, cost effective, and feasible from an engineering
standpoint. The value of existing housing is positively benefited by accessing a
bituminous paved street in good condition. It can be accomplished as proposed,
and need not be constructed in conjunction with any other project. The City and
the persons assessed should review the project for benefit to determine the
economic feasibility of the proposed improvements.
7
V. RIGHT-OF-WAY / EASEMENTS
The existing streets and proposed street improvements are located within
the existing 66 and 60-foot-wide right-of-way.
VI. PERMITS
No permits would be required to accomplish the work.
VII. COMPLETION
This project is proposed to be completed during the 2022 construction
season.
VIII. PRELIMINARY PROJECT SCHEDULE
The preliminary project schedule for the 2022 Otsego Street Renewal
Project:
Table I
City of Otsego
Streets within Walesch Estates & O’Day Acres
Preliminary Project Schedule for 2022
1. City Council Receives Feasibility Report and Schedules
Public Hearing and Orders Plans and Specs February 14
2. Open House Meeting with Residents TBD
3. City Council Holds Public Hearing for Improvement Project March 14
4. City Council Approves Plans and Specifications and City
Council Approves and Authorizes to Advertise for Bid April 11
5. Open Bids May 3
6. City Council Considers Award of Contract or Discontinues
Process May 9
7. If Awarded, Contractor Completes Construction August
8. City Council Holds Assessment Hearing and Adopts
Assessment Roll TBD
IX. ESTIMATED PROJECT COST
Included in this report (Exhibit C) is a detailed estimate of construction
costs for the street improvements. The estimated total project cost is $991,711.
8
The costs herein are estimates only and are not guaranteed prices. The
quantities are estimates also. The contractor will be paid only for work
completed. The cost estimates are based on unit prices from previous similar
projects costs and projected for current inflation.
X. PROPOSED FUNDING
The funding for this project is expected to be provided by two sources, the
City of Otsego and the benefiting property owners.
The benefiting property owners are proposed to be assessed $114,660 or
$1,092 per lot and the City would provide the remaining estimated at $877,051.
Map of Benefiting Properties
9
XI. ESTIMATED ASSESSMENT
The per unit method of assessment was used due to all the benefiting
properties being single family homes and use the street in much the same
manner. The latest assessment policy for street reconstructs such as this project
is to assess at 20% of the project cost, but not to exceed $1,092 per lot or
benefiting property. 20% of project cost would set the assessment at $1,888.97
per benefitting property, therefore, assessments were capped at $1,092 per
benefitting property. The percentage proposed to be assessed on this project
amounts to 11.6%. See Exhibit D for the Benefiting Property Assessment
Summary.
XII. CONCLUSION AND RECOMMENDATION
This report analyzed the feasibility of improving streets within the Walesch
Estates & O’Day Acres subdivisions. The proposed improvements are
necessary, cost effective and feasible from a technical and engineering stand-
point, and benefit the properties proposed as shown on Exhibit E. The project
can be efficiently completed as a stand-alone project.
The project is proposed to be funded by assessing the benefiting
properties as well as receiving funds from the City of Otsego.
EXHIBIT A
HakansonAnderson
EXHIBIT B
HakansonAnderson
HakansonAnderson
EXHIBIT C
City of Otsego
2022 Street Reconstruction Project
Walesch Estates
PRELIMINARY ENGINEER'S COST ESTIMATE
Bid Schedule "A" - Reclaim and Remove 4" off Top
Item
No. Spec. Ref Description
Estimated
Quantity Unit Unit Price
Total Estimated
Extension
2021.501 Mobilization 1 LS $39,350.00 39,350.00$
2104.503 Remove Sewer Pipe (Storm)550 LF $12.54 6,897.00$
2104.504 Remove Bituminous Pavement (Driveways)545 SY $7.78 4,240.10$
2104.504 Remove Concrete Pavement (Driveways)50 SY $17.29 864.50$
2104.513 Sawing Bituminous Pavement (Full Depth)1320 LF $2.42 3,194.40$
2104.513 Sawing Concrete Pavement (Full Depth)185 LF $5.03 930.55$
2104.603 Relocate Sprinkler System 1 LS $20,000.00 20,000.00$
2105.603 Special Ditch Grading 1430 LF $8.87 12,684.10$
2105.607 Haul & Stockpile Excess Material (LV) (Excess Reclaim to City Hall)4824 CY $18.00 86,832.00$
2106.507 Excavation - Common (EV)0 CY $8.70 -$
2211.501 Aggregate Base Class 5 (Driveways)87 TON $32.91 2,863.17$
2211.506 Salvage Aggregate Reclaim and Respread Onsite (EV)0 CY $12.72 -$
2215.501 Full Depth Reclamation (P)33033 SY $1.69 55,825.77$
2232.501 Mill Bituminous Surface (1.5")106 SY $17.17 1,820.02$
2357.502 Bituminous Material For Tack Coat 1564 GAL $2.98 4,660.72$
2360.501 Type Sp 9.5 Wearing Course Mixture (2,B) Driveways 128 TON $140.83 18,026.24$
2360.501 Type Sp 9.5 Wearing Course Mixture (2,B)2728 TON $75.20 205,145.60$
2360.502 Type Sp 12.5 Non Wear Course Mixture (2,C) 3637 TON $72.41 263,355.17$
2506.502 Adjust Concrete Structures to New Finish Grades 1 EACH $550.00 550.00$
2531.503 Concrete Curb & Gutter Surrmountable 848 LF $15.96 13,534.08$
2531.504 6" Concrete (Ped Ramps and Driveways)1109 SF $7.93 8,794.37$
2540.602 Salvage and Relocate Mail Box Support 11 EA $123.84 1,362.24$
2563.601 Traffic Control 1 LS $2,235.78 2,235.78$
2573.530 Culvert Inlet Protection 28 EA $172.11 4,819.08$
2574.525 Pulverized Topsoil Borrow (Lv)0 CY $49.10 -$
2575.555 Turf Establishment (Hydro Seed) 1.60 AC $8,475.26 13,560.42$
$771,545.31
Bid Schedule "B" - Storm Sewer
Item Spec. Ref Description Estimated Unit Unit Price Total Estimated
2501.503 15" HDPE Pipe Culvert (driveway)185 LF $42.90 $7,936.50
2501.503 15" RC Pipe Culvert 525 LF $77.61 $40,745.25
2503.541 15" RC Pipe Sewer Design 3006 Cl V (All Depths)112 LF $55.35 $6,199.20
Total - Bid Schedule "B"$54,880.95
Total - Bid Schedule "A" - Streets $771,545
Total - Bid Schedule "B" - Strom Sewer $54,881
TOTAL CONSTRUCTION COST $826,426
$165,285
TOTAL ESTIMATED PROJECT COST $991,711
Total - Bid Schedule "A"
20 % Administration, Legal, & Engineering
S:\Municipal\AOTSEGO\392 CIP_Renewals\2022\A-PRELIMINARY DESIGN\1-FEASIBILITY\OT392-2022 EngEst_Feasibililty.xlsx Page 1 of 1
EXHIBIT D
City of Otsego
2022 Street Reconstruction Project
Walesch Estates O'Day Acres
Assessment Roll
Map # PARCEL ID TAXPAYER NAME PROPERTY ADDRESS CITY, STATE, ZIP
PROPOSED
ASSESSMENT
1 118037005050 DONALD F GOTH 7761 O'BRIAN AVE NE OTSEGO, MN 55330 $1,092.00
2 118037005030 CHRISTA A PALMER 7821 O'BRIAN AVE NE OTSEGO, MN 55330 $1,092.00
3 118037005020 DENIS BARANYUK 7849 O'BRIAN AVE NE OTSEGO, MN 55330 $1,092.00
4 118037005010 CALVIN & CORDELIA KARN 7879 O'BRIAN AVE NE OTSEGO, MN 55330 $1,092.00
5 118037004010 STANLEY A LINDRUD 14083 78TH ST NE OTSEGO, MN 55330 $1,092.00
6 118037004020 LANCE & MICHELLE LUBBERS 14107 78TH ST NE OTSEGO, MN 55330 $1,092.00
7 118037004021 AARON GOODMAN 14167 78TH ST NE OTSEGO, MN 55330 $1,092.00
8 118037004050 CARL G PAUMEN 14195 78TH ST NE OTSEGO, MN 55330 $1,092.00
9 118037004060 GREGORY & MARY PAUMEN 14223 78TH ST NE OTSEGO, MN 55330 $1,092.00
10 118037004070 JOHN T & SUNNY J NORFOLK 14253 78TH ST NE OTSEGO, MN 55330 $1,092.00
11 118037004080 BRYAN JOSEPH MULLIGAN JR & BRANDON NORFOLK 14281 78TH ST NE OTSEGO, MN 55330 $1,092.00
12 118037004090 VLADIMIR ZASTAVSKIY & VALENTINA ZASTAVSKAYA 14311 78TH ST NE OTSEGO, MN 55330 $1,092.00
13 118037004100 ROMAN ZASTAVSKIY 14339 78TH ST NE OTSEGO, MN 55330 $1,092.00
14 118037004110 RICHARD A & MARGARET BURNEY 14367 78TH ST NE OTSEGO, MN 55330 $1,092.00
15 118037004120 GERALD R & JUDITH MOSSAK 14395 78TH ST NE OTSEGO, MN 55330 $1,092.00
16 118037004130 BROOKE MARIE MOORE 14423 78TH ST NE OTSEGO, MN 55330 $1,092.00
17 118037004140 PAUL R & ASHLEY L NOLDEN 14453 78TH ST NE OTSEGO, MN 55330 $1,092.00
18 118056001080 JODI A & CAROL J EENHUIS 7830 O'DAY CIR NE OTSEGO, MN 55330 $1,092.00
19 118056001070 GREGORY P & JULIE L SYKORA 7860 O'DAY CIR NE OTSEGO, MN 55330 $1,092.00
20 118056001060 ROBERT D & KERRY A PLAYLE 7890 O'DAY CIR NE OTSEGO, MN 55330 $1,092.00
21 118056001050 MARK B & SHELBY L THORSTED 7857 O'DAY CIR NE OTSEGO, MN 55330 $1,092.00
22 118056001040 JOANN R & DANIEL D MATTERN 7827 O'DAY CIR NE OTSEGO, MN 55330 $1,092.00
23 118037002090 WESTERN DRYWALL SERVICES 14376 78TH ST NE OTSEGO, MN 55330 $1,092.00
24 118037002080 THOMAS S HOUDEK 7864 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
25 118037002070 STEVEN G & FAYE YOUNG 7888 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
26 118037002060 DONALD B JR & ADA M DITTBERNER 7908 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
27 118037002050 LUKE J LENNEMAN & EMILY F TSCHIDA 7928 ODAY AVE NE OTSEGO, MN 55330 $1,092.00
28 118037002040 JOSEPH L SR & KATHLEEN M WARNER 7942 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
29 118037002030 ANDREW J & MELISSA M PAULSON 7958 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
30 118037002020 JAMES & DELORES STEVENS 7972 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
31 118037002010 JOHN W & VIRGINIA M BREIWICK 7984 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
32 118037003120 JEFFREY & RAYNA MEYER 14320 78TH ST NE OTSEGO, MN 55330 $1,092.00
33 118037003130 SCOTT E & MELANIE J GRUPA 14266 78TH ST NE OTSEGO, MN 55330 $1,092.00
34 118037003140 JESSE DAHLHEIMER 14238 78TH ST NE OTSEGO, MN 55330 $1,092.00
35 118037003150 AARTHUR LINDHOLM 14208 78TH ST NE OTSEGO, MN 55330 $1,092.00
36 118037003160 JEROME M & SUSAN M KOWALCZYK 14182 78TH ST NE OTSEGO, MN 55330 $1,092.00
37 118037003170 TONY KAUNZNER & TAMMY GILBERT 14146 78TH ST NE OTSEGO, MN 55330 $1,092.00
38 118037003180 AUSTIN COPSEY 14084 78TH ST NE OTSEGO, MN 55330 $1,092.00
39 118037003010 WILLIAM HAUGLID & ANITA HAUGLID 7894 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
40 118037003020 THOMAS L & MICHELE M SWITZER 7900 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
41 118037003030 DILLON SCHULLO 7914 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
42 118037003040 REINHARD J & MARY A KARST 7928 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
43 118037003050 MICHAEL KISNER 7944 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
44 118037003060 THOMAS & PATRICIA DAVISON 7964 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
45 118037003070 JAMES F & JENNIFER G STEVENS 7953 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
46 118037003080 BRENT R SWANSON 7939 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
47 118037003090 RICHARD A & BARBARA MEYER 7923 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
48 118037003100 VICKIE CAMPBELL 7901 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
49 118037003110 SCOTT L & JANEE L ADAMSON 7867 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
50 118056001010 TIMOTHY LANDRUS JR & SAMANTHA LANDRUS 14483 81ST ST NE OTSEGO, MN 55330 $1,092.00
51 118056001020 STACY A & DANIEL D FLOODMAN 14453 81ST ST NE OTSEGO, MN 55330 $1,092.00
52 118056001030 WILLIAM & TAMARA DWINNELL 14423 81ST ST NE OTSEGO, MN 55330 $1,092.00
53 118036003070 CHRISTOPHER LEE & RICHARD LEE 14403 81ST ST NE OTSEGO, MN 55330 $1,092.00
54 118036003060 KENNETH L JR & SHARON SUITTER 14379 81ST ST NE OTSEGO, MN 55330 $1,092.00
Page 1 of 2
City of Otsego
2022 Street Reconstruction Project
Walesch Estates O'Day Acres
Assessment Roll
Map # PARCEL ID TAXPAYER NAME PROPERTY ADDRESS CITY, STATE, ZIP
PROPOSED
ASSESSMENT
55 118036003050 PATRICIA H MOSENG 14353 81ST ST NE OTSEGO, MN 55330 $1,092.00
56 118036003040 PATRICIA H MOSENG 14319 81ST ST NE OTSEGO, MN 55330 $1,092.00
57 118036003030 SHIRLEY A ALLEN 14293 81ST ST NE OTSEGO, MN 55330 $1,092.00
58 118036003020 PAVEL TESLARU 14263 81ST ST NE OTSEGO, MN 55330 $1,092.00
59 118036003010 ROGER D & JOAN I KLUVER 14221 81ST ST NE OTSEGO, MN 55330 $1,092.00
60 118036002010 WILLIAM R DABY 8114 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
61 118036002020 SANDRA I MCCHESNEY 8144 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
62 118036002030 DESTINY PROPERTIES LLC 14295 82ND ST NE OTSEGO, MN 55330 $1,092.00
63 118036002040 CYNTHIA LORGE 14325 82ND ST NE OTSEGO, MN 55330 $1,092.00
64 118036002050 TYLER SMITH & ALYXIS LUNDSTROM 14355 82ND ST NE OTSEGO, MN 55330 $1,092.00
65 118036002060 TYLER SMITH 8143 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
66 118036002070 RICHARD J & JOY K HARTFIEL 8105 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
67 118036002080 DANIEL JOHN ROMINSKI & SAMANTHA ROMINSKI 8063 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
68 118036002090 CALEB JOSHUA BROWN & COURTNEY LEE BROWN 8031 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
69 118036002100 DONALD D FALAAS JR 14330 81ST ST NE OTSEGO, MN 55330 $1,092.00
70 118036002110 MARK M STENZEL 14305 81ST ST NE OTSEGO, MN 55330 $1,092.00
71 118036002120 CHAD & JILL ERICKSON 14276 81ST ST NE OTSEGO, MN 55330 $1,092.00
72 118036001140 ALEXEI V LOGHINOV & ZINAIDA D LOGHINOVA 14480 81ST ST NE OTSEGO, MN 55330 $1,092.00
73 118036001130 DANIEL S WOODY 14448 81ST ST NE OTSEGO, MN 55330 $1,092.00
74 118036001120 JAMIE C FOSS 8026 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
75 118036001110 STEPHAN G FRITZ 8060 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
76 118036001100 GREGORY J & JOY M MAHER 8086 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
77 118036001090 ALEKSANDR & EMILIYA GOLOVATYY 8112 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
78 118036001080 CHRISTOPHER EASTMAN 8136 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
79 118036001070 SHIREL A PAULICK 8160 O'DAY AVE NE OTSEGO, MN 55330 $1,092.00
80 118036001040 JEFF RICE 14367 82ND ST NE OTSEGO, MN 55330 $1,092.00
81 118036001030 SHAWN T & TIA M OLSON 14348 82ND ST NE OTSEGO, MN 55330 $1,092.00
82 118036001020 JOSEPH A & REBECCA L GOSIAK 14320 82ND ST NE OTSEGO, MN 55330 $1,092.00
83 118036001010 TANNER J & BRIDGET J ANDERSON 8206 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
84 118037001010 CHARLES J & SHARON SHIMEK 14248 82ND ST NE OTSEGO, MN 55330 $1,092.00
85 118037001020 MATTHEW LALLY 14210 82ND ST NE OTSEGO, MN 55330 $1,092.00
86 118037001030 DALE J HANSON 14158 82ND ST NE OTSEGO, MN 55330 $1,092.00
87 118037001040 EDWARD A & KATHLEEN WOODFORD 14106 82ND ST NE OTSEGO, MN 55330 $1,092.00
88 118037001050 JEFFERY A & KIMBERLY A SWANSON 14086 82ND ST NE OTSEGO, MN 55330 $1,092.00
89 118037001060 ALAN D WURZINGER 14062 82ND ST NE OTSEGO, MN 55330 $1,092.00
90 118037001070 JOHN G FIFE & ANGELA S GUSTAFSON 14030 82ND ST NE OTSEGO, MN 55330 $1,092.00
91 118037001080 CRAIG J & MEGHAN M ZIMMER 14061 82ND ST NE OTSEGO, MN 55330 $1,092.00
92 118037001090 MICHAEL C & KATIE GAMMELGAARD 14205 82ND ST NE OTSEGO, MN 55330 $1,092.00
93 118037001100 CECILIA R OLSON & VIRGINIA A PUFAHL 14247 82ND ST NE OTSEGO, MN 55330 $1,092.00
94 118037001110 DAWN L BACKER 8125 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
95 118037001120 PAUL & SARA BRIGGS 8103 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
96 118037001130 DAVID K JANSEN 8073 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
97 118037001140 KAREN ERICKSON 8045 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
98 118037001150 JULIO MENDOZA 8019 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
99 118037001160 SCOTT V THEISEN 7985 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
100 118037001170 KEVIN N & CRESILDA P BUSCHKOWSKY 7953 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
101 118037001180 RICHARD N & BARBARA L SAUTER 7933 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
102 118037001190 JEFFREY JUDISCH 7917 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
103 118037001200 GREGORY J RAEKER 7905 OCHOA AVE NE OTSEGO, MN 55330 $1,092.00
104 118037001210 BOBBIE JO & JOE ANDERSON 14042 79TH ST NE OTSEGO, MN 55330 $1,092.00
105 118037001220 WALTER E & ELLEN C NELSON 14014 79TH ST NE OTSEGO, MN 55330 $1,092.00
Page 2 of 2
EXHIBIT E
HakansonAnderson
1
CITY OF OTSEGO
COUNTY OF WRIGHT
STATE OF MINNESOTA
RESOLUTION NO: 2022-26
ORDERING PREPARATION OF PLANS AND SPECIFICATIONS FOR THE
2022 STREET RENEWAL IMPROVEMENT OF STREETS
WITHIN WALESCH ESTATES AND O’DAY ACRES
WHEREAS, a resolution of the City Council adopted the 14th day of February 2022, fixed a date for a Council
Hearing on the proposed improvement of streets within Walesch Estates and O’Day Acres subdivisions; and,
WHEREAS, ten days mailed noticed and two weeks’ published notice of the hearing was given and the hearing
was held thereon on the 14th day of March, 2022, at which all persons desiring to be heard were given an
opportunity to be heard thereon.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF OTSEGO, MINNESOTA:
1. Such improvement is necessary, cost-effective, and feasible as detailed in the feasibility report.
2. Such improvement is hereby ordered.
3. Hakanson Anderson is hereby designated as the engineer for this improvement, and are hereby
directed and authorized to prepare plans and specifications for the making of such improvements.
2
ADOPTED by the Otsego City Council this 14th day of March 2022.
MOTION BY:
SECONDED BY:
IN FAVOR:
OPPOSED:
CITY OF OTSEGO
__________________________________
Jessica L. Stockamp, Mayor
ATTEST:
__________________________________
Audra Etzel, City Clerk