Loading...
3.4 Left Hand Turn Signals Request for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Public Works City Engineer Wagner July 25, 2022 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.4 – Left Turn Signals STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff recommends the City Council approve plans and specifications and authorize staff to seek quotes. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: Plans and specifications have been prepared for signal improvements at the ramps of TH101 and County State Aid Highways 36, 38, and 42 by installing flashing left hand turn signals. The latest construction cost estimate of $125,000 was significantly less than the original estimate allowing the City to obtain quotes rather than advertise for bids. Staff proposes to send a request for quotes to multiple qualified local contractors with a quote opening of August 9. City Council consideration on award of contract would be August 22. Project completion is set for November 15, 2022. The project is to be completed in 2022 and funding from MnDOT and Wright County will be available for reimbursement to the City in July of 2023. The Public Works Subcommittee reviewed this information at their July 20 meeting and recommended consent agenda consideration at an upcoming City Council meeting. SUPPORTING DOCUMENTS ATTACHED: • Construction Cost Estimate • Plans and Specifications (Cover sheet only, full plans available in online packet) POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to approve the Plans and Specifications and authorization to obtain Quotes for the TH101 Traffic Signal Systems Revisions at CSAH 36, 38, and 42. BUDGET INFORMATION FUNDING: BUDGETED: Fund 414 – Capital Improvement Yes Conversion of Signal Systems to Left Hand Turn Flashing Yellow Arrows SP8606-35 Construction Cost Estimate July 2022 Item No.MnDOT No.Item Description MnDOT/LLP Wright County City of Otsego Total Cost 1 2021.501 Mobilization 1,916.67$ 2,500.00$ 583.33$ 5,000.00$ 2 2563.601 Traffic Control 3,833.33$ 5,000.00$ 1,166.67$ 10,000.00$ 3 2565.001 Revise Signal System at 101/42 East Ramp 5,000.00$ 5,000.00$ -$ 10,000.00$ 4 2565.002 Revise Signal System at 101/42 West Ramp 3,750.00$ 7,500.00$ 3,750.00$ 15,000.00$ 5 2565.003 Revise Signal System at 101/38 East Ramp 8,000.00$ 10,000.00$ 2,000.00$ 20,000.00$ 6 2565.004 Revise Signal System at 101/38 West Ramp 5,000.00$ 10,000.00$ 5,000.00$ 20,000.00$ 7 2565.005 Revise Signal System at 101/36 East Ramp 7,500.00$ 7,500.00$ -$ 15,000.00$ 8 2565.006 Revise Signal System at 101/36 West Ramp 15,000.00$ 15,000.00$ -$ 30,000.00$ TOTALS 50,000.00$ 62,500.00$ 12,500.00$ 125,000.00$ 7/18/2022 Engineer Signature Date