3.7 Walesch Estate Pay Estimate #1
Request for
City Council Action
DEPARTMENT INFORMATION
ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE:
Public Works City Engineer Wagner August 22, 2022
PRESENTER(s) REVIEWED BY: ITEM #:
Consent City Administrator/Finance Director Flaherty 3.7 – Project Payment
2022 Street Renewal
STRATEGIC VISION
MEETS: THE CITY OF OTSEGO:
Is a strong organization that is committed to leading the community through innovative
communication.
X Has proactively expanded infrastructure to responsibly provide core services.
Is committed to delivery of quality emergency service responsive to community needs and
expectations in a cost-effective manner.
Is a social community with diverse housing, service options, and employment opportunities.
Is a distinctive, connected community known for its beauty and natural surroundings.
AGENDA ITEM DETAILS
RECOMMENDATION:
City staff recommends City Council approval of Pay Application #1 to Minnesota Paving & Materials.
ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED?
No No
BACKGROUND/JUSTIFICATION:
Pay Application #1 includes payment for reclamation and bituminous removals, culvert installation, street
grading, concrete curb, and gutter, paving both lifts of bituminous, and turf establishment.
Final miscellaneous items are being completed including irrigation and some bituminous punch list
items. Turf establishment is minimal with this year’s project, but the topsoil has been seeded. The
retainage amount for the project will be enough to ensure an acceptable amount of growth has occurred.
This payment also includes a change order for some field changes. The total resulting change order is a
reduction in the amount of $1,915.73.
- One culvert was discovered to be an 18” diameter (plans showed a 15” pipe). The cost to upsize
this pipe is part of change order.
- The City’s standard outlet pipe erosion control calls for articulated concrete block but do to the
narrow and steep ditches it was decided erosion control blanket would work better. This resulted
in a reduction in the project cost and is include as part of the change order.
- Three of the culverts ended up having gas main placed directly adjacent or over the existing
culverts. The change order is for additional time and material cost incurred by the contractor to
hand dig around the existing utilities and move them so the new pipe could be placed.
In accordance with Minnesota Statute, the City is withholding the maximum of 5% retainage of work
completed, which amounts to $37,132.71 at this time.
SUPPORTING DOCUMENTS ATTACHED:
• Pay Application #1
POSSIBLE MOTION
PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES:
Motion to approve Pay Application #1 in the amount of $705,521.39 to Minnesota Paving & Materials for
work completed on 2022 Street Renewal Project.
BUDGET INFORMATION
FUNDING: BUDGETED:
Fund 201 – Pavement Management
Yes
Contractor's Application for Payment No.To (Owner): Application Application Date:Period:Project: From (Contractor): Via (Engineer):Application For PaymentChange Order Summary1. ORIGINAL CONTRACT PRICE............................................ $Number2. Net change by Change Orders...................................................$13. Current Contract Price (Line 1 ± 2)..........................................$4. TOTAL COMPLETED AND STORED TO DATE $5. RETAINAGE: $a. 5% X Work Completed..................... $b. 0% X Stored Material........................$c. Total Retainage (Line 5.a + Line 5.b)............................$6. AMOUNT ELIGIBLE TO DATE (Line 4 - Line 5.c)............. $7. LESS PREVIOUS PAYMENTS................................................$8. AMOUNT DUE THIS APPLICATION................................... $Contractor's CertificationENGINEER: HAKANSON ANDERSON Certification: We recommend payment for work and quantites shown.DateOWNER: CITY OF OTSEGOContractor SignatureBy: Date:Date(Owner)NET CHANGE BY-$1,915.73CHANGE ORDERS(Engineer)$705,521.39TOTALS$25,030.95 $26,946.68$705,521.39$0.00$37,132.71$37,132.71Approved Change Orders$766,326.07Additions Deductions-$1,915.73$25,030.95 $26,946.68$764,410.34$742,654.101City of OtsegoAugust 16, 20222022 Street Renewal ProjectHakanson AndersonMinnesota Paving & MaterialsThe undersigned Contractor certifies, to the best of its knowledge, the following:(1) All previous progress payments received from Owner on account of Work done under the Contract have been applied on account to discharge Contractor's legitimate obligations incurred in connection with the Work covered by prior Applications for Payment;(2) Title to all Work, materials and equipment incorporated in said Work, or otherwise listed in or covered by this Application for Payment, will pass to Owner at time of payment free and clear of all Liens, security interests, and encumbrances (except such as are covered by a bond acceptable to Owner indemnifying Owner against any such Liens, security interest, or encumbrances); and(3) All the Work covered by this Application for Payment is in accordance with the Contract Documents and is not defective.
PAY ESTIMATE #1City of Otsego2022 Street Renewal Project ITEM NO.ITEM DESCRIPTIONESTIMATED QUANTITY UNITCONTRACT UNIT PRICECONTRACT AMOUNTUSED TO DATEEXTENSION1 Mobilization1 LS $25,222.51 25,222.51$ 1 25,222.51$ 2 Remove Sewer Pipe (Storm) 464 LF $15.25 7,076.00$ 440 6,710.00$ 3 Rehab Drainage Structures 3 EA $915.11 2,745.33$ 2 1,830.22$ 4 Salvage and Reinstall Sign and Post 3 EA $325.95 977.85$ -$ 5 Remove Bituminous Pavement (Driveways) 617 SY $11.98 7,391.66$ 755 9,044.90$ 6 Remove Concrete Pavement (Driveways) 60 SY $15.75 945.00$ 72 1,134.00$ 7 Sawing Bituminous Pavement (Full Depth) 1496 LF $2.05 3,066.80$ 1142 2,341.10$ 8 Sawing Concrete Pavement (Full Depth) 84 LF $6.02 505.68$ 82 493.64$ 9 Sprinkler System Allowance 1 LS $10,000.00 10,000.00$ -$ 10 Aggregate Base Class 5 (Driveways) 66 TON $39.89 2,632.74$ 35 1,396.15$ 11 Salvage, Haul and Stockpile Reclaim Material (3") (EV) 2890 CY $18.68 53,985.20$ 2890 53,985.20$ 12 Aggregate Base Preparation (P) 35185 SY $0.61 21,462.85$ 35185 21,462.85$ 13 Full Depth Reclamation (7.5") (P) 33033 SY $1.22 40,300.26$ 33033 40,300.26$ 14 Mill Bituminous Surface (1.5") 15 SY $21.06 315.90$ 6 126.36$ 15 Bituminous Material For Tack Coat 1564 GAL $1.81 2,830.84$ 1600 2,896.00$ 16 Type SP 9.5 Wearing Course Mixture (2,B) Driveways 113 TON $133.42 15,076.46$ 175 23,348.50$ 17 Type SP 9.5 Wearing Course Mixture (2,B) 2728 TON $68.96 188,122.88$ 2783 191,915.68$ 18 Type SP 12.5 Non Wear Course Mixture (2,B) 3637 TON $68.91 250,625.67$ 3641 250,901.31$ 19 12" RC Pipe Apron4 EA $1,525.19 6,100.76$ 8 12,201.52$ 20 12" RC Pipe Culvert 72 LF $70.16 5,051.52$ 152 10,664.32$ 21 15" RC Pipe Apron 14 EA $1,672.63 23,416.82$ 6 10,035.78$ 22 15" RC Pipe Culvert 388 LF $84.39 32,743.32$ 112 9,451.68$ 23 New Castings and Adjust to Finish Grades 3 EA $1,238.46 3,715.38$ 2 2,476.92$ 24 Articulated Interlocking Block Open Cell, Type A 46 SY $234.88 10,804.48$ -$ 25 Concrete Curb & Gutter Surmountable 828 LF $26.43 21,884.04$ 825 21,804.75$ 26 6" Concrete (Driveways) 564 SF $8.37 4,720.68$ 649 5,432.13$ 27 Relocate Mail Box and Support 27 EA $200.59 5,415.93$ 7 1,404.13$ 28 Traffic Control1 LS $2,908.52 2,908.52$ 1 2,908.52$ 29 Culvert Inlet Protection 9 EA $150.44 1,353.96$ 9 1,353.96$ 30 Pulverized Topsoil Borrow (LV) 175 CY $53.06 9,285.50$ 64 3,395.84$ 31 Turf Establishment (Hydro Seed) 1.25 AC $4,513.22 5,641.53$ 0.75 3,384.92$ 766,326.07$ 717,623.15$ Bid Schedule "A" - Full Depth ReclamationTotal Bid Schedule 'A'S:\Municipal\AOTSEGO\392 CIP_Renewals\2022\C-CONSTRUCTION PHASE\4-PAY ESTIMATES\OT392-2022 - Pay Estimate.xlsxPE - 1
PAY ESTIMATE #1City of Otsego2022 Street Renewal Project ITEM NO.ITEM DESCRIPTIONESTIMATED QUANTITY UNITCONTRACT UNIT PRICECONTRACT AMOUNTUSED TO DATEEXTENSION1 15" RC Pipe Apron(4)EA $1,672.63 (6,690.52)$ -$ 2 18" RC Pipe Apron 4 EA 1,932.00$ 7,728.00$ 4 7,728.00$ 3 15" RC Pipe Culvert(112)EA $84.39 (9,451.68)$ -$ 4 18" RC Pipe Culvert 112 EA 93.45$ 10,466.40$ 112 10,466.40$ 5Articulated Interlocking Block Open Cell, Type A(46)EA $234.88 (10,804.48)$ -$ 6 Erosion Control Blanket, Category 0 44 SY 5.25$ 231.00$ 44 231.00$ 7 Utility/Storm Culvert Conflicts 1 LS 6,605.55$ 6,605.55$ 1 6,605.55$ (1,915.73)$ 25,030.95$ $717,623.15$25,030.95$742,654.10TOTALChange Order No. 1Bid Schedule "A" - Full Depth ReclamationChange Order No. 1Total Change Order No. 1S:\Municipal\AOTSEGO\392 CIP_Renewals\2022\C-CONSTRUCTION PHASE\4-PAY ESTIMATES\OT392-2022 - Pay Estimate.xlsxPE - 2