Loading...
3.6 Well #11 ProjectRequest for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Public Works City Engineer Wagner August 28, 2023 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.6 – Well #11 Project STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff recommends the City Council approve Plans and Specifications and order Advertisement for Bids. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: Plans and specifications have been prepared for drilling the new Well #11 within the West WWTF property. The project consists of drilling and testing a municipal well and includes the pump and motor as well as site improvements. Next year, power supply, raw water line connection, SCADA, and Pumphouse #3 improvements will be completed. The reason for the multi-phase project is to determine the capacity of the well prior to completing design of the pumps and split the project according to contractor specialties. Bid advertisement will initiate on August 29, with a bid opening anticipated for September 20, and City Council consideration of bid award scheduled for September 25. Completion date of work will be March 31, 2024. The City has budgeted a total of $1,500,000 in the CIP for this project: $150,000 in 2023, $950,000 in 2024, and $400,000 in 2025. This phase of the Well #11 project is estimated at $299,894. The Public Works Subcommittee was presented this information at their August 16 meeting with recommendation for City Council consideration and approval. SUPPORTING DOCUMENTS ATTACHED: •Plans and Specifications •Engineer’s Estimate POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to approve the Plans and Specifications and Order Advertisement for Bids for the Well #11 Project. BUDGET INFORMATION FUNDING: BUDGETED: Fund 601 – Water Utility Yes PROJECT LOCATION XXXXXXXXXXXXXXXXXXXXXXXXXXXXWWWEXISTING TEST WELLPROPOSED WELL #11 WELL #11 ENGINEER'S COST ESTIMATE CITY OF OTSEGO Bid Schedule "A" - Well #11 Site Work Item No. Item Description Unit Estimated Quantity Unit Price Total Estimated Extension 1 Mobilization LS 1 20,000$ 20,000$ 2 Site Cleanup, Establishment Turf and Controlling Erosion LS 1 2,500$ 2,500$ 3 Bollards (City Supplied)EA 8 250$ 2,000$ Bid Schedule "B" - Well #11 Item No. Item Description Unit Estimated Quantity Unit Price Total Estimated Extension 3 Drill & Drive 24" Casing LF 195 240$ 46,800$ 4 Drill 24" Open Hole LF 321 200$ 64,200$ 5 Furnsih Pea-rock to backfill 24" bore CY 10 10$ 100$ 6 Furnish & Install 18" casing LF 262 120$ 31,440$ 7 Furnish & Install Grout CY 15 750$ 11,250$ 8 Remove Pea-rock fill after drilling out concrete plug LF 61 67$ 4,087$ 9 Plumb and Alignment LS 1 850$ 850$ 10 Furnish, Install and Remove Development Equipment LS 1 6,000$ 6,000$ 11 Furnish, install, dentonate explosives LBS 65 100$ 6,500$ 12 Well Development HRS 80 400$ 32,000$ 13 Sandstone removal by air lift equipment CY 75 100$ 7,500$ 14 Haul Standstone Away CY 75 20$ 1,500$ 15 Discharge Tee on 24" Casing, Valve, Flge Cap LS 1 600$ 600$ 16 Temporary Cap and well sanitize LS 1 350$ 350$ 17 Temporary Discharge Piping 10" Dia LF 195 15$ 2,925$ 18 Furnish, Install and Remove Test Pump Equipment LS 1 6,500$ 6,500$ 19 Test Pumping 200 KW & 150 HP Pump HRS 30 220$ 6,600$ 20 Water Analysis STD Menu With Radionuculicide LS 1 2,500$ 2,500$ 21 Data Logger For Test Pump Recording EA 1 500$ 500$ 22 Video Log LS 1 1,500$ 1,500$ 23 Gamma Log LS 1 2,000$ 2,000$ 24 Well Report LS 1 200$ 200$ 25 MDH Permits and filing fees LS 1 375$ 375$ 26 Furnish and Install Pitless Adapter EA 1 30,000$ 30,000$ 27 Furnish and Install 8" Drop Pipe LF 140 150$ 21,000$ 28 Furnish and Install Transducer EA 1 3,000$ 3,000$ 29 Furnish and Install Grundfos Model 1100S Pump EA 1 10,500$ 10,500$ 30 Furnish and Install Franklin 125HP Electric Motor EA 1 18,500$ 18,500$ 236,277$ Bid Schedule "A" - Well #11 Site Work 24,500$ Bid Schedule "B" - Well #11 236,277$ TOTAL ESTIMATED Construction COST 260,777$ 15% Administration, Legal, & Engineering 39,117$ TOTAL ESTIMATED PROJECT COST 299,894$ Total - Bid Schedule "B" S:\Municipal\AOTSEGO\539 Well #11\B-PROJECT DEVELOPMENT\3-DESIGN\OT539 EngEst Page 1 of 1 XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXWWWEXISTING TEST WELLPROPOSED WELL #11FUTURE RAW WATERMAIN