Loading...
3.6 Otsego Creek Project 23-12 Plans & Specs and Order Ad for Bids Request for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Public Works City Engineer Wagner September 25, 2023 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.6 – Otsego Creek Project STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff recommends the City Council approve Plans and Specifications and order Advertisement for Bids. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: The development of Prairie Pointe requires a crossing of Otsego Creek. The City of Otsego applies a storm water impact fee per acre to developers within the Otsego Creek drainage area. This fee is intended to either credit the developer or is for use by the City to complete storm water related work within the creek or trunk storm sewer within the drainage area. That fund will pay for the project costs. The City has taken the lead on the crossing and the restoration of the creek through Prairie Pointe to facilitate approvals needed from the DNR and US Army Corp as the waterway is considered a DNR waterway. The crossing has been determined to need two 72” RCP to pass the “100 YR” event without increasing the flood stages up stream. One of the culverts is set 1’ below the creek invert to allow the bottom to fill in naturally for aquatic resource requirements. The DNR has stated the project is approvable as per these plans. The surface of the crossing will be left at subbase level for a future street, trail, and sidewalk to be constructed by the developer when future additions of Prairie Pointe are approved. The current construction cost estimate of the crossing is $214,370.66. Engineering, modeling of this creek, EAW processing and permitting by DNR and US Army Corp has added a significant cost to this project. A related project of restoration of this creek continues to be worked on and is anticipated to be a 2024 project. The City has been awarded a grant from Wright County that will be used for this future portion of the project. Bid opening would be October 17 with City Council consideration of approval on October 23. Construction would be in November and into December if needed with a completion date of December 15, weather permitting. That time of year is generally favorable for construction due to lower water flows and usually no large rainfall events to contend with. The Public Works Subcommittee was presented with this information at their September 20 meeting with recommendation for City Council consideration and approval. SUPPORTING DOCUMENTS ATTACHED: • Plans and Specifications • Engineer’s Estimate POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to approve the Plans and Specifications and order Advertisement for Bids for the Marquette Avenue Culvert Construction Otsego Creek Project, City Project No. 23-12. BUDGET INFORMATION FUNDING: BUDGETED: Fund 408 – Otsego Creek Yes DRAINAGE& UTILITYEASEMENT D R A I N A G E U T I L I T YE A S E M E N TDRAINAGE& UTILITYEASEMENTAND ^^^^^^^^^^ ^ ^ ^ ^ ^ ^ ^ ^ ^^^^^^^^^^|||||||||||||||||||||||| | | | | | | | | | | | | | | | | | | | | |910915920925930935940910915920925930935940 905910915920925930935940905910915920925930935940 ℄6+00924928932936940944924928932936940944℄6+25924928932936940944924928932936940944℄8+56926928932936940944926928932936940944℄6+50924928932936940924928932936940℄6+75922924928932936922924928932936℄7+00920924928932936940920924928932936940℄7+25916920924928932936940916920924928932936940℄7+50918920924928932936940918920924928932936940℄7+75922924928932936940922924928932936940℄8+00924928932936940924928932936940℄8+25924928932936940924928932936940℄8+50926928932936940944926928932936940944 ENGINEERS ESTIMATE CITY OF OTSEGO MARQUETTE AVENUE CULVERT CONSTRUCTION OTSEGO CREEK PROJECT NO. 23-12 ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY UNIT PRICE EXTENSION 1 2021.501 MOBILIZATION LUMP SUM 1 11,700.00$ 11,700.00$ 2 2101.505 CLEARING ACRE 0.5 5,850.00$ 2,925.00$ 3 2101.505 GRUBBING ACRE 0.5 5,850.00$ 2,925.00$ 4 2105.507 SELECT GRANULAR BORROW (LV)CU YD 280 39.00$ 10,920.00$ 5 2105.601 CREEK BYPASS LUMP SUM 1 19,500.00$ 19,500.00$ 6 2451.507 COARSE FILTER AGGREGATE (CV)CU YD 120 55.77$ 6,692.40$ 7 2501.502 72" RC PIPE APRON EACH 4 4,909.58$ 19,638.32$ 8 2501.503 72" RC PIPE CULVERT DESIGN 3006 CLASS III LIN FT 224 534.30$ 119,683.20$ 9 2511.504 GEOTEXTILE FILTER TYPE IV SQ YD 175 4.16$ 728.00$ 10 2511.507 RANDOM RIPRAP CLASS III CU YD 90 149.24$ 13,431.60$ 11 2573.501 STABILIZED CONSTRUCTION EXIT LUMP SUM 1 2,500.00$ 2,500.00$ 12 2573.503 SILT FENCE; TYPE MS LIN FT 200 2.37$ 473.20$ 13 2573.503 FLOTATION SILT CURTAIN TYPE MOVING WATER LIN FT 20 24.96$ 499.20$ 14 2574.508 FERTILIZER TYPE 1 POUND 300 1.01$ 304.20$ 15 2575.504 EROSION CONTROL BLANKET CATEGORY 3N SQ YD 800 1.97$ 1,578.72$ 16 2575.505 SEEDING ACRE 0.5 146.90$ 73.45$ 17 2575.505 DISK ANCHORING ACRE 0.25 92.30$ 23.08$ 18 2575.508 SEED MIXTURE 25-121 POUND 55 5.43$ 298.58$ 19 2575.508 SEED MIXTURE 35-221 POUND 12.5 26.90$ 336.31$ 20 2575.509 MULCH MATERIAL TYPE 1 TON 0.5 280.80$ 140.40$ Total Construction Cost Estimate $214,370.66