Loading...
Item 4.1 2023_Dec19_OtsegoPC presentation_hkgiCarrick’s Landing UpdatePARK COMMISSION MEETINGDECEMBER 19, 2023 CARRICK’S LANDING UPDATE–Project Status & Schedule Update–Preferred Concept Plan–Cost EstimateNEXT STEPSAgenda Project Status COMPLETED TASKS–2021-2022: Concept Planning and Public Engagement–March 2023: DNR Outdoor Rec Grant Application Submitted–June 2023: Grant Awarded–September 2023: Archaeological Survey work–November 2023: Grant Agreement ApprovedREMAINING TASKS–December-January 2024: Prepare Construction Drawings–February-March 2024: City Council Approve CD set and Specifications, Authorization to Bid–March-April 2024: Bidding–Spring/Summer 2024: ConstructionProject Status & Schedule Update Preferred Concept Plan Project Location Site Plan Parking Access River Access Cross Section Proposed Shelter and Sign Proposed Sign Proposed River Access Cost Estimate OTHER ITEMS NOT INCLUDED–Permitting Coordination (Stormwater permit, DNR Permits)–Geotechnical–Paddle PortCost EstimateCOSTITEM$225,000KAYAK LAUNCH, ACCESSIBLE RAMP, RIVER ACCESS/SHORE FISHING$100,000BOARDWALK (8 FT WIDE), NATURE OBSERVATION/OVERLOOK$9,000TRAILS (APPROX. 1,400 SF, 8 FT WIDE, BITUMINOUS)$130,000PICNIC SHELTER$185,000SITE WORK, SITE AMENITIES, SIGNAGE, LIGHTING$72,000DESIGN & ENGINEERING (HKGI + HAA)$721,000TOTAL Next Steps –Meet with DNR to review permitting needs–Develop Construction Drawings and SpecificationsNext Steps Questions or Comments? Thank youGABRIELLE GRINDE