3.10 2024 Mill and Overlay Project Accepting Bids and Awarding Contract Request for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Public Works City Engineer Wagner February 26, 2024 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.10 – 2024 Mill & Overlay Project STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff recommends the City Council adopt a resolution accepting bids and awarding a contract. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? Yes No BACKGROUND/JUSTIFICATION: In January 2024, the City Council authorized the bid process for the 2024 Mill & Overlay Project. Bids were opened on February 21, 2024. A total of 13 bids were received as shown on the attached Bid Tabulation. The Pavement Management Program which is part of the CIP for the City included funding for estimated project costs in the amount of $1,318,650. When plans and specifications were completed, the Engineer Estimated Costs for the project were $1,316,162.03. As bid, the current Estimated Costs for the project total $906,183.77. Northwest Asphalt of Shakopee, Minnesota is the apparent responsible low bidder. City staff recommend awarding the contract to the low bidder, Northwest Asphalt, who has completed projects within the City in the past with the work completed to specifications and in a timely manner. SUPPORTING DOCUMENTS ATTACHED: • Engineer’s Estimate • Bid Tabulation • Resolution 2024-25 POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to adopt Resolution 2024-25 Accepting Bids and Awarding Contract to Northwest Asphalt of Shakopee, Minnesota for the 2024 Mill & Overlay Project, City Project No. 24-02 in the amount of $863,032.16. BUDGET INFORMATION FUNDING: BUDGETED: Fund 201 – Pavement Management Yes Engineers Estimate 2024 Otsego Street 1.5" Mill and Overlay Project City of Otsego 78th Quaday, Arbor Place, Meadowlands Cedarburg, Arbor Creek 1, 2, 3, Otsego Preserve 1, 2, 3 SCHEDULE "A" - MILL AND OVERLAY No.MnDOT Description Unit Price Extension 1 2021.501 MOBILIZATION 4 EA 2,500.00$ 10,000.00$ 2 2357.506 BITUMINOUS MATERIAL FOR TACK COAT 5850 GAL 3.50$ 20,475.18$ 3 2232.501 MILL BITUMINOUS SURFACE 112519 SY 3.25$ 365,688.23$ 4 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT 9969 TON 85.00$ 847,324.24$ 5 2563.601 TRAFFIC CONTROL 4 EA 5,000.00$ 20,000.00$ SCHEDULE "A" MILL AND OVERLAY ESTIMATED TOTAL COST $1,253,487.65 SCHEDULE "A" - MILL AND OVERLAY $1,253,487.65 TOTAL ALL SCHEDULES $1,253,487.65 Engineering and Construction Administration (5%)$62,674.38 TOTAL ALL SCHEDULES $1,316,162.03 Estimated Quantity OT387-2024 MO EngEst 1-5-2024 Mill Overlay Estimate 1 1/17/2024 8:41 AM BID TABULATION CITY OF OTSEGO 2024 MILL AND OVERLAY PROJECT Bids were opened at 2:00 p.m., February 21, 2024. There were 13 bids received, as shown herein. SCHEDULE "A" - ARBOR CREEK ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 1 2021.501 MOBILIZATION LS 1 2,700.00$ 2,700.00$ 8,955.12$ 8,955.12$ 1,500.00$ 1,500.00$ 2 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 2154 5.50$ 11,847.00$ 2.31$ 4,975.74$ 3.20$ 6,892.80$ 3 2232.501 MILL BITUMINOUS SURFACE SY 42111 0.90$ 37,899.90$ 0.85$ 35,794.35$ 1.20$ 50,533.20$ 4 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 3731 70.20$ 261,916.20$ 71.41$ 266,430.71$ 69.95$ 260,983.45$ 5 2563.601 TRAFFIC CONTROL LS 1 1,850.00$ 1,850.00$ 1,010.00$ 1,010.00$ 725.00$ 725.00$ Schedule A Total $316,213.10 $317,165.92 $320,634.45 SCHEDULE "B" - OTSEGO PRESERVE ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 6 2021.501 MOBILIZATION LS 1 2,200.00$ 2,200.00$ 7,484.79$ 7,484.79$ 1,500.00$ 1,500.00$ 7 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1305 5.50$ 7,177.50$ 2.31$ 3,014.55$ 3.20$ 4,176.00$ 8 2232.501 MILL BITUMINOUS SURFACE SY 24853 0.95$ 23,610.35$ 1.08$ 26,841.24$ 1.20$ 29,823.60$ 9 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2202 71.62$ 157,707.24$ 72.36$ 159,336.72$ 69.95$ 154,029.90$ 10 2563.601 TRAFFIC CONTROL LS 1 1,250.00$ 1,250.00$ 656.50$ 656.50$ 725.00$ 725.00$ Schedule B Total $191,945.09 $197,333.80 $190,254.50 SCHEDULE "C" - MEADOWLANDS/CEDARBURG & NAPIER ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 11 2021.501 MOBILIZATION LS 1 2,200.00$ 2,200.00$ 5,892.02$ 5,892.02$ 1,500.00$ 1,500.00$ 12 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1019 5.50$ 5,604.50$ 2.31$ 2,353.89$ 3.20$ 3,260.80$ 13 2232.501 MILL BITUMINOUS SURFACE SY 19404 1.05$ 20,374.20$ 0.89$ 17,269.56$ 1.20$ 23,284.80$ 14 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 1719 72.15$ 124,025.85$ 73.19$ 125,813.61$ 69.95$ 120,244.05$ 15 2563.601 TRAFFIC CONTROL LS 1 1,150.00$ 1,150.00$ 353.50$ 353.50$ 725.00$ 725.00$ Schedule C Total $153,354.55 $151,682.58 $149,014.65 SCHEDULE "D" - 78TH & QUADAY ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 16 2021.501 MOBILIZATION LS 1 2,700.00$ 2,700.00$ 5,892.02$ 5,892.02$ 1,500.00$ 1,500.00$ 17 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1373 5.50$ 7,551.50$ 2.31$ 3,171.63$ 3.20$ 4,393.60$ 18 2232.501 MILL BITUMINOUS SURFACE SY 26152 0.94$ 24,582.88$ 1.00$ 26,152.00$ 1.20$ 31,382.40$ 19 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2317 71.12$ 164,785.04$ 70.68$ 163,765.56$ 72.25$ 167,403.25$ 20 2563.601 TRAFFIC CONTROL LS 1 1,900.00$ 1,900.00$ 909.00$ 909.00$ 1,725.00$ 1,725.00$ Schedule D Total $201,519.42 $199,890.21 $206,404.25 Schedule A + B + C + D Total $863,032.16 $866,072.51 $866,307.85 Northwest Asphalt Park Construction Company Omann Brothers Paving Inc. Page 1 of 5 BID TABULATION CITY OF OTSEGO 2024 MILL AND OVERLAY PROJECT Bids were opened at 2:00 p.m., February 21, 2024. There were 13 bids received, as shown herein. SCHEDULE "A" - ARBOR CREEK ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 1 2021.501 MOBILIZATION LS 1 2 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 2154 3 2232.501 MILL BITUMINOUS SURFACE SY 42111 4 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 3731 5 2563.601 TRAFFIC CONTROL LS 1 Schedule A Total SCHEDULE "B" - OTSEGO PRESERVE ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 6 2021.501 MOBILIZATION LS 1 7 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1305 8 2232.501 MILL BITUMINOUS SURFACE SY 24853 9 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2202 10 2563.601 TRAFFIC CONTROL LS 1 Schedule B Total SCHEDULE "C" - MEADOWLANDS/CEDARBURG & NAPIER ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 11 2021.501 MOBILIZATION LS 1 12 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1019 13 2232.501 MILL BITUMINOUS SURFACE SY 19404 14 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 1719 15 2563.601 TRAFFIC CONTROL LS 1 Schedule C Total SCHEDULE "D" - 78TH & QUADAY ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 16 2021.501 MOBILIZATION LS 1 17 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1373 18 2232.501 MILL BITUMINOUS SURFACE SY 26152 19 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2317 20 2563.601 TRAFFIC CONTROL LS 1 Schedule D Total Schedule A + B + C + D Total UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 1,624.18$ 1,624.18$ 6,000.00$ 6,000.00$ 4,200.00$ 4,200.00$ 3.25$ 7,000.50$ 4.00$ 8,616.00$ 3.83$ 8,249.82$ 1.10$ 46,322.10$ 1.16$ 48,848.76$ 0.80$ 33,688.80$ 72.36$ 269,975.16$ 73.95$ 275,907.45$ 76.18$ 284,227.58$ 1,082.79$ 1,082.79$ 1,000.00$ 1,000.00$ 825.00$ 825.00$ $326,004.73 $340,372.21 $331,191.20 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 4,114.59$ 4,114.59$ 5,000.00$ 5,000.00$ 4,000.00$ 4,000.00$ 3.25$ 4,241.25$ 4.00$ 5,220.00$ 3.83$ 4,998.15$ 1.10$ 27,338.30$ 1.02$ 25,350.06$ 0.91$ 22,616.23$ 72.36$ 159,336.72$ 73.13$ 161,032.26$ 77.78$ 171,271.56$ 703.82$ 703.82$ 650.00$ 650.00$ 550.00$ 550.00$ $195,734.68 $197,252.32 $203,435.94 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 3,031.80$ 3,031.80$ 4,850.00$ 4,850.00$ 4,000.00$ 4,000.00$ 3.25$ 3,311.75$ 4.00$ 4,076.00$ 3.83$ 3,902.77$ 0.92$ 17,851.68$ 1.04$ 20,180.16$ 0.82$ 15,911.28$ 70.53$ 121,241.07$ 69.39$ 119,281.41$ 77.29$ 132,861.51$ 378.98$ 378.98$ 350.00$ 350.00$ 550.00$ 550.00$ $145,815.28 $148,737.57 $157,225.56 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 4,222.86$ 4,222.86$ 4,200.00$ 4,200.00$ 6,300.00$ 6,300.00$ 3.25$ 4,462.25$ 4.00$ 5,492.00$ 3.83$ 5,258.59$ 0.99$ 25,890.48$ 0.71$ 18,567.92$ 0.57$ 14,906.64$ 71.53$ 165,735.01$ 66.48$ 154,034.16$ 73.47$ 170,229.99$ 974.51$ 974.51$ 900.00$ 900.00$ 825.00$ 825.00$ $201,285.11 $183,194.08 $197,520.22 $868,839.80 $869,556.18 $889,372.92 Wm. Mueller & Sons S.M. Hentges & Sons, Inc.North Valley, Inc. Page 2 of 5 BID TABULATION CITY OF OTSEGO 2024 MILL AND OVERLAY PROJECT Bids were opened at 2:00 p.m., February 21, 2024. There were 13 bids received, as shown herein. SCHEDULE "A" - ARBOR CREEK ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 1 2021.501 MOBILIZATION LS 1 2 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 2154 3 2232.501 MILL BITUMINOUS SURFACE SY 42111 4 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 3731 5 2563.601 TRAFFIC CONTROL LS 1 Schedule A Total SCHEDULE "B" - OTSEGO PRESERVE ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 6 2021.501 MOBILIZATION LS 1 7 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1305 8 2232.501 MILL BITUMINOUS SURFACE SY 24853 9 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2202 10 2563.601 TRAFFIC CONTROL LS 1 Schedule B Total SCHEDULE "C" - MEADOWLANDS/CEDARBURG & NAPIER ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 11 2021.501 MOBILIZATION LS 1 12 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1019 13 2232.501 MILL BITUMINOUS SURFACE SY 19404 14 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 1719 15 2563.601 TRAFFIC CONTROL LS 1 Schedule C Total SCHEDULE "D" - 78TH & QUADAY ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 16 2021.501 MOBILIZATION LS 1 17 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1373 18 2232.501 MILL BITUMINOUS SURFACE SY 26152 19 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2317 20 2563.601 TRAFFIC CONTROL LS 1 Schedule D Total Schedule A + B + C + D Total UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 15,000.00$ 15,000.00$ 4,215.00$ 4,215.00$ 11,050.00$ 11,050.00$ 2.80$ 6,031.20$ 2.00$ 4,308.00$ 0.01$ 21.54$ 0.88$ 37,057.68$ 1.15$ 48,427.65$ 1.14$ 48,006.54$ 74.03$ 276,205.93$ 75.00$ 279,825.00$ 74.85$ 279,265.35$ 770.00$ 770.00$ 600.00$ 600.00$ 1,908.00$ 1,908.00$ $335,064.81 $337,375.65 $340,251.43 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 8,000.00$ 8,000.00$ 4,215.00$ 4,215.00$ 7,000.00$ 7,000.00$ 2.80$ 3,654.00$ 2.00$ 2,610.00$ 0.01$ 13.05$ 0.88$ 21,870.64$ 1.20$ 29,823.60$ 1.14$ 28,332.42$ 74.03$ 163,014.06$ 74.55$ 164,159.10$ 72.20$ 158,984.40$ 770.00$ 770.00$ 600.00$ 600.00$ 1,188.00$ 1,188.00$ $197,308.70 $201,407.70 $195,517.87 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 8,000.00$ 8,000.00$ 4,215.00$ 4,215.00$ 6,200.00$ 6,200.00$ 2.80$ 2,853.20$ 2.00$ 2,038.00$ 0.01$ 10.19$ 0.88$ 17,075.52$ 1.05$ 20,374.20$ 1.14$ 22,120.56$ 74.03$ 127,257.57$ 74.65$ 128,323.35$ 74.85$ 128,667.15$ 770.00$ 770.00$ 600.00$ 600.00$ 870.00$ 870.00$ $155,956.29 $155,550.55 $157,867.90 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 7,400.00$ 7,400.00$ 4,215.00$ 4,215.00$ 7,300.00$ 7,300.00$ 2.80$ 3,844.40$ 2.00$ 2,746.00$ 0.01$ 13.73$ 0.88$ 23,013.76$ 1.05$ 27,459.60$ 1.14$ 29,813.28$ 74.03$ 171,527.51$ 71.55$ 165,781.35$ 74.85$ 173,427.45$ 770.00$ 770.00$ 600.00$ 600.00$ 1,477.00$ 1,477.00$ $206,555.67 $200,801.95 $212,031.46 $894,885.47 $895,135.85 $905,668.66 GMH Asphalt CorporationAsphalt Surface Technologies Corp.Minnesota Paving & Materials Page 3 of 5 BID TABULATION CITY OF OTSEGO 2024 MILL AND OVERLAY PROJECT Bids were opened at 2:00 p.m., February 21, 2024. There were 13 bids received, as shown herein. SCHEDULE "A" - ARBOR CREEK ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 1 2021.501 MOBILIZATION LS 1 2 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 2154 3 2232.501 MILL BITUMINOUS SURFACE SY 42111 4 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 3731 5 2563.601 TRAFFIC CONTROL LS 1 Schedule A Total SCHEDULE "B" - OTSEGO PRESERVE ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 6 2021.501 MOBILIZATION LS 1 7 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1305 8 2232.501 MILL BITUMINOUS SURFACE SY 24853 9 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2202 10 2563.601 TRAFFIC CONTROL LS 1 Schedule B Total SCHEDULE "C" - MEADOWLANDS/CEDARBURG & NAPIER ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 11 2021.501 MOBILIZATION LS 1 12 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1019 13 2232.501 MILL BITUMINOUS SURFACE SY 19404 14 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 1719 15 2563.601 TRAFFIC CONTROL LS 1 Schedule C Total SCHEDULE "D" - 78TH & QUADAY ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 16 2021.501 MOBILIZATION LS 1 17 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1373 18 2232.501 MILL BITUMINOUS SURFACE SY 26152 19 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2317 20 2563.601 TRAFFIC CONTROL LS 1 Schedule D Total Schedule A + B + C + D Total UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 2,000.00$ 2,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 3.80$ 8,185.20$ 0.01$ 21.54$ 2.00$ 4,308.00$ 1.20$ 50,533.20$ 2.05$ 86,327.55$ 1.40$ 58,955.40$ 76.50$ 285,421.50$ 70.55$ 263,222.05$ 78.50$ 292,883.50$ 1,800.00$ 1,800.00$ 1,000.00$ 1,000.00$ 800.00$ 800.00$ $347,939.90 $355,571.14 $361,946.90 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 2,000.00$ 2,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 3.80$ 4,959.00$ 0.01$ 13.05$ 2.00$ 2,610.00$ 1.20$ 29,823.60$ 2.05$ 50,948.65$ 1.40$ 34,794.20$ 76.50$ 168,453.00$ 70.55$ 155,351.10$ 78.50$ 172,857.00$ 1,500.00$ 1,500.00$ 1,000.00$ 1,000.00$ 525.00$ 525.00$ $206,735.60 $212,312.80 $215,786.20 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 2,000.00$ 2,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 3.80$ 3,872.20$ 0.01$ 10.19$ 2.00$ 2,038.00$ 1.45$ 28,135.80$ 2.05$ 39,778.20$ 1.50$ 29,106.00$ 79.00$ 135,801.00$ 70.55$ 121,275.45$ 79.25$ 136,230.75$ 950.00$ 950.00$ 1,000.00$ 1,000.00$ 525.00$ 525.00$ $170,759.00 $167,063.84 $172,899.75 UNIT PRICE EXTENSION UNIT PRICE EXTENSION UNIT PRICE EXTENSION 2,000.00$ 2,000.00$ 5,000.00$ 5,000.00$ 6,000.00$ 6,000.00$ 3.80$ 5,217.40$ 0.01$ 13.73$ 2.00$ 2,746.00$ 1.40$ 36,612.80$ 2.05$ 53,611.60$ 1.30$ 33,997.60$ 76.50$ 177,250.50$ 67.55$ 156,513.35$ 77.25$ 178,988.25$ 3,000.00$ 3,000.00$ 1,000.00$ 1,000.00$ 800.00$ 800.00$ $224,080.70 $216,138.68 $222,531.85 $949,515.20 $951,086.46 $973,164.70 C. S. McCrossan Construction, Inc.Knife River Corporation Valley Paving, Inc. Page 4 of 5 BID TABULATION CITY OF OTSEGO 2024 MILL AND OVERLAY PROJECT Bids were opened at 2:00 p.m., February 21, 2024. There were 13 bids received, as shown herein. SCHEDULE "A" - ARBOR CREEK ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 1 2021.501 MOBILIZATION LS 1 2 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 2154 3 2232.501 MILL BITUMINOUS SURFACE SY 42111 4 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 3731 5 2563.601 TRAFFIC CONTROL LS 1 Schedule A Total SCHEDULE "B" - OTSEGO PRESERVE ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 6 2021.501 MOBILIZATION LS 1 7 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1305 8 2232.501 MILL BITUMINOUS SURFACE SY 24853 9 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2202 10 2563.601 TRAFFIC CONTROL LS 1 Schedule B Total SCHEDULE "C" - MEADOWLANDS/CEDARBURG & NAPIER ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 11 2021.501 MOBILIZATION LS 1 12 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1019 13 2232.501 MILL BITUMINOUS SURFACE SY 19404 14 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 1719 15 2563.601 TRAFFIC CONTROL LS 1 Schedule C Total SCHEDULE "D" - 78TH & QUADAY ITEM NO. Mn/DOT SPEC. NO.ITEM DESCRIPTION UNIT ESTIMATED QUANTITY 16 2021.501 MOBILIZATION LS 1 17 2357.506 BITUMINOUS MATERIAL FOR TACK COAT GAL 1373 18 2232.501 MILL BITUMINOUS SURFACE SY 26152 19 2360.509 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B) 1.5" LIFT TON 2317 20 2563.601 TRAFFIC CONTROL LS 1 Schedule D Total Schedule A + B + C + D Total UNIT PRICE EXTENSION 25,000.00$ 25,000.00$ 4.95$ 10,662.30$ 2.23$ 93,907.53$ 80.38$ 299,897.78$ 750.00$ 750.00$ $430,217.61 UNIT PRICE EXTENSION 25,000.00$ 25,000.00$ 4.95$ 6,459.75$ 2.23$ 55,422.19$ 80.38$ 176,996.76$ 500.00$ 500.00$ $264,378.70 UNIT PRICE EXTENSION 25,000.00$ 25,000.00$ 4.95$ 5,044.05$ 2.35$ 45,599.40$ 81.75$ 140,528.25$ 500.00$ 500.00$ $216,671.70 UNIT PRICE EXTENSION 25,000.00$ 25,000.00$ 4.95$ 6,796.35$ 2.35$ 61,457.20$ 82.45$ 191,036.65$ 750.00$ 750.00$ $285,040.20 $1,196,308.21 Duininck, Inc. Page 5 of 5 1 CITY OF OTSEGO COUNTY OF WRIGHT STATE OF MINNESOTA RESOLUTION NO: 2024-25 ACCEPTING BIDS AND AWARDING CONTRACT FOR THE 2024 MILL & OVERLAY PROJECT WHEREAS, pursuant to an advertisement for bids for the construction of the 2024 Mill & Overlay Project, City Project No. 24- 02, bids were received, opened on February 21, 2024, and tabulated according to law, and the following bids were received complying with the advertisement; and Contractor Total Base Bid 1. Northwest Asphalt $863,032.16 2. Park Construction Company $866,072.51 3. Omann Brothers Paving Inc. $866,307.85 4. North Valley, Inc. $868,839.80 5. Wm. Mueller & Sons $869,556.18 6. S.M. Hentges & Sons, Inc. $889,372.92 7. Asphalt Surface Technologies Corp. $894,885.47 8. Minnesota Paving & Materials $895,135.85 9. GMH Asphalt Corporation $905,668.66 10. C.S. McCrossan Construction, Inc. $949,515.20 11. Knife River Corporation $951,086.46 12. Valley Paving, Inc. $973,164.70 13. Duininck, Inc. $1,196,308.21 WHEREAS, it appears that Northwest Asphalt of Shakopee, Minnesota is the lowest responsible bidder. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF OTSEGO, MINNESOTA: 1. The Mayor and City Clerk are hereby authorized and directed to enter a contract with Northwest Asphalt of Shakopee, Minnesota in the name of the City of Otsego for the 2024 Mill & Overlay Project, City Project No. 24-02, according to the plans and specifications therefore approved by the City Council and on file in the office of the City Clerk. 2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the bid bond made with their bids, except that the bid bond of the successful bidder and the next lowest bidder shall be retained until a contract has been signed. 2 ADOPTED by the Otsego City Council this 26th day of February, 2024. MOTION BY: SECONDED BY: IN FAVOR: OPPOSED: CITY OF OTSEGO __________________________________ Jessica L. Stockamp, Mayor ATTEST: __________________________________ Audra Etzel, City Clerk