Item 3.4 East WWTF Odor Accept Quote and Authorize Installation of an Control Unit Request for City Council Action DEPARTMENT INFORMATION ORIGINATING DEPARTMENT REQUESTOR: MEETING DATE: Utilities Utility Manager Neidermeier August 26, 2024 PRESENTER(s) REVIEWED BY: ITEM #: Consent City Administrator/Finance Director Flaherty 3.4 – Odor Control Unit STRATEGIC VISION MEETS: THE CITY OF OTSEGO: Is a strong organization that is committed to leading the community through innovative communication. X Has proactively expanded infrastructure to responsibly provide core services. Is committed to delivery of quality emergency service responsive to community needs and expectations in a cost-effective manner. Is a social community with diverse housing, service options, and employment opportunities. Is a distinctive, connected community known for its beauty and natural surroundings. AGENDA ITEM DETAILS RECOMMENDATION: City staff is recommending the City Council accept a quote and authorize installation of an odor control unit. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: City staff has identified the beneficial need of an odor control unit for a solids processing building at the East WWTF. The odor risk location is at the belt thickening process established with the original wastewater facility construction and the odors have trended with solids processing frequencies from weekly to triweekly. The specific location is currently not odor controlled. Engineering, equipment representatives and neighbor involvement guided staff to the addition of an odor control unit for this solids processing building. A variety of odor control options were reviewed from organic passive, inline filters and mechanical equipment. The proposed equipment is a smaller version of existing pretreatment and biosolids building equipment, benefiting manufacturer and representation of parts and material efficiencies. Comparable consideration was given for the reuse of an existing unit being removed from service at the West WWTF, however a reduced life cycle, added media, and operating costs did not prove this option viable. The addition of the proposed unit would be the third odor control device connected to individual buildings to mitigate odor risks at the facility. Approval now ensures equipment is in place and operational this fall as a lead time of 10 weeks exists. City staff recommends authorization of the quoted odor control unit for installation at the East WWTF. Additional costs associated with the installation include electrical connections quoted at $4,875, a variety of piping modifications estimated at $4,013, and concrete pad estimate of $2,500. Funding for this replacement is not budget detailed, however funding is available within the Rehabilitation and Replacement budget line item. The Public Works Subcommittee was presented with this information at their August 21, 2024, meeting and provided direction for City Council consideration of approval. SUPPORTING DOCUMENTS ATTACHED: • Quote: Purafil POSSIBLE MOTION PLEASE WORD MOTION AS YOU WOULD LIKE IT TO APPEAR IN THE MINUTES: Motion to accept the quote from Purafil in the amount of $49,048.22 and to authorize installation of an odor control unit with electrical, piping, and concrete requirements for installation. BUDGET INFORMATION FUNDING: BUDGETED: Fund 602 – Sanitary Sewer Utility Yes DATE OF PROPOSAL: August 13, 2024 Q-38739 Rev. 6 Kurt Neidermeier 13400 90TH Street NE Otsego, MN 55330 Email: KNeidermeier@ci.otsego.mn.us Otsego MN East WWTP - WAS Tank DS-1000 Engineered to Order Details for: C-45919 Item Qty Drum Scrubber 1000 Blower Adder:DS1000,230V/1ph/60hz 1 Skid Adder: Drum Scrubber 1000 1 Mist Eliminator Adder:Drum Scrubber 1000 1 Gage, assembly, 1 gage, AL, Magnehelic, 0-3 iwg 1 Odorcarb Ultra Media (Box for equipment)31 Odormix SP Media (Box for equipment)8 C-45919 Subtotal $ 45,909.77 Extended Total (US)1 $ 45,909.77 Consumable Items: Item Description Qty Unit Price Ext. Price Loc REMMED Removal of OCBU and MSP 1 $ -9,597.55 $ -9,597.55 PCBAM-SB Puracarb AM - Slingbag 1,600 $ 7.96 $ 12,736.00 US Notes: Tax not included Lead time - 6-8 weeks ****PCBAM media replacing the normal OCBU/MSP media Estimated freight: $6,000 Pricing Summary Total:$ 49,048.22 Freight:$ 0.00 Grand Total:$ 49,048.22 Expiration: This quote is valid for 30 days after quote build date. Build date: 2024-8-13 *If a Purchase Order is submitted that requires approval prior to production (HFA), then the validity of pricing is 90 days from quote build date. DATE OF PROPOSAL: August 13, 2024 Q-38739 Rev. 6 2654 Weaver Way | Doraville, GA 30340 | Office: 770.662.8545 | www.purafil.com Page 2 *Any approval after the expiration will require a requote. *Request to cancel a Purchase order is subject to a cancellation fee. This quote is subject solely to the terms and conditions attached. Any purchase order submitted by Buyer pursant to this quote will be governed solely by the Terms. https://www.purafil.com/purafil-terms-and-conditions-of-sale/ 1/1 2654 Weaver Way | Doraville, GA 30340 Office: 770.662.8545 | www.purafil.com Drum Scrubber Configuration Summary Sizing Media Size:1000 CFM Volume Type Active:230V/1ph/60hz 31 Odorcarb Ultra Media (Box) Inlet:Standard per Size 8 Odormix SP Media (Box) Sizing Electrical Voltage:230V/1ph/60hz Outlet Type: Frequency:60 Outlet Size: Phase:Skid:Y Motor Type:Standard Hold Downs:Y Blower Coating:Powder Mist Eliminator:Yes ME Gage:Yes