5.1 PowerPoint Presentation2024 Street Renewal Project
VASSEURS OAK GROVE ESTATES 3RD AND 4TH ADDITIONS &
HALLS 1ST, 2ND, & 3RD ADDITIONS
FEBRUARY 26, 2024
Proposed Project Location
VASSEURS OAK GROVE
ESTATES 3RD & 4TH ADDITIONS
& PID 118500291101
4
HALLS 1ST, 2ND, & 3RD
ADDITIONS
6
7
Project Cost
Project Cost
FEASIBILITY ESTIMATECIP ESTIMATE
$1,198,472$1,186,019
10
146 UNITS @ $1,092 = $159,432
13% OF PROJECT COST ESTIMATE
Proposed Assessment
VASSEURS OAK GROVE
ESTATES 3RD & 4TH ADDITIONS
& PID 118500291101
12
HALLS 1ST, 2ND, & 3RD
ADDITIONS
Timeline
•MARCH 25: PUBLIC HEARING
•APRIL 8: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE AD FOR BIDS
•MAY 8: BID OPENING
•MAY 13: AWARD BIDS
•JUNE 1: CONSTRUCTION STARTS
•AUGUST 2: PROJECT COMPLETION
Project Timeline
15
THE PROPOSED IMPROVEMENTS ARE NECESSARY, COST
EFFECTIVE AND FEASIBLE FROM A TECHNICAL AND ENGINEERING
STANDPOINT, AND BENEFIT THE PROPERTIES PROPOSED TO BE
ASSESSED. THE PROJECT CAN BE EFFICIENTLY COMPLETED AS A
STAND-ALONE PROJECT.
Conclusion
Recommendation
Resolution 2024-17
STAFF RECOMMENDS THE CITY COUNCIL APPROVE RESOLUTION RECEIVING
FEASIBILITY REPORT FOR IMPROVEMENT OF STREETS WITHIN VASSEUR’SOAK GROVE
3RD AND 4TH ADDITIONS AND HALLS 1ST, 2ND, AND 3RD ADDITIONS AND SET A DATE FOR
A PUBLIC HEARING FOR RESIDENTS TO BE PRESENTED PROJECT SCOPE AND POSSIBLE
ASSESSMENT COSTS.
Thank you