Project Cost
8
Project Cost
9
10
146 Units @ $1,092 = $159,432
13% of project cost estimate
Proposed Assessment
10
VASSEURS OAK GROVE ESTATES 3RD & 4TH ADDITIONS
& PID 118500291101
11
12
HALLS 1ST, 2ND, & 3RD ADDITIONS
12
Timeline
13
March 21: OPEN HOUSE
March 25: public Hearing
April 8: Approve plans and specifications and authorize ad for bids
May 8: bid opening
May 13: award bids
June 1: construction starts
August 2: project completion
Project Timeline
14
15
The proposed improvements are necessary, cost effective and feasible from a technical and engineering standpoint, and benefit the properties proposed to be assessed. The project can
be efficiently completed as a stand-alone project.
Conclusion
15
Recommendation
16
Resolution 2024-28
staff recommends the City Council approve Resolution ordering plans and specifications for the improvement of streets within Vasseur’s Oak Grove 3rd and 4th Additions and Halls 1st,
2nd, and 3rd Additions.