Item 3.3 Mississippi Landing3601 Thurston Avenue Anoka, MN 55303 763.231.5840 TPC@PlanningCo.com 1 PLANNING REPORT TO: Otsego Planning Commission FROM: D. Daniel Licht REPORT DATE: 15 May 2025 120-DAY DATE: RE: Otsego – Otsego Waterfront; PUD Development Stage Plan TPC FILE: 101.02 BACKGROUND Modern Construction of Minnesota, Inc. has submitted plans for a mixed-use development of 13.80 acres located east of TH 101 and south of 90th Street to be known as “Otsego Waterfront”. The subject property exists as three lots with an area of 7.21 acres and one outlot with an area of 6.57 acres. The proposed development includes one lot for a principal building including 135 multiple family dwellings together with retail and service commercial space, as well as planned future open space adjacent to the Mississippi River. The developer intends this to the first of multiple phases, but the proposed development can exist as a standalone project. The City Council on 13 March 2023 approved a PUD District amendment, PUD Development Stage Plan, and preliminary plat for a similar proposal known as “Mississippi Landing”. Section 11-36-4.D.6 of the Zoning Ordinance establishes that a final PUD Final Plan must be submitted within six months of a PUD Development Stage Plan being approved. Minnesota Statutes 462.356, Subd. 3c provides that approval of a preliminary plat is valid for one year from the date of approval. City staff notified the developer the 2023 approvals were expired. The developer has submitted revised plans intended to address concerns raised by the Planning Commission and City Council with the prior request. The application again requires consideration of a PUD Development Stage Plan, preliminary plat, and vacation of existing drainage and utility easements. A public hearing to consider the applications has been noticed for the Planning Commission meeting on 19 May 2025 at 7:00 PM. Item 3.3 2 Exhibits:  Site Location Map  Architectural plan set dated 05/12/25 (8 sheets)  Preliminary Plat Development Plans dated 04.05.25 (14 sheets)  Preliminary Plat dated 12/16/2022  Park Development Concept ANALYSIS Comprehensive Plan. The 2023 Comprehensive Plan guides the subject site for mixed-use land uses to be developed with high density residential and commercial land uses. The proposed development, which is intended by the developer to be the first phase of a larger overall project, provides for construction of multiple family dwellings together with retail and service commercial building space within a single principal building consistent with the recommendations of the Comprehensive Plan. Zoning. The subject site is zoned PUD, Planned Unit Development District. Allowed uses within the PUD District currently include only those permitted, conditional, interim, and accessory uses provided for within the B-1, Retail Business District and multiple family dwellings. The commercial spaces within the proposed building are suitable for the allowed uses within the B- 1 District. Inclusion of the proposed residential dwellings is consistent with the recommendations of the 2023 Comprehensive Plan to develop with a mix of commercial and residential uses upon the subject property and the PUD District Surrounding Uses. The subject site is surrounded by the existing and planned land uses shown in the table below. The proposed mixed-use development would transition to the uses developed within Otsego Waterfront East to the north through Outlot A. The 101 Market is also compatible with the proposed use, although screening of the outdoor storage area should be considered, but would be difficult to implement given the proposed building heights illustrated with the architectural plans. Direction Land Use Zoning Existing Use North Commercial Park PUD District 101 Market Carrick’s Landing East -- -- Mississippi River South Rural A-1 District Mississippi Riverwood campground West -- -- Trunk Highway 101 3 EAW. The proposed development required processing of an Environmental Assessment Worksheet (EAW) in accordance with Minnesota Rules 4410.4300, Subp. 32. In accordance with Minnesota Rules 4410.1500, the EAW was completed and distributed to persons and agencies on the official Environmental Quality Board (EQB) distribution list and published on the City website. A notice of EAW availability was published in the EQB Monitor on 20 September2022, initiating a 30-day public comment period. A press release was submitted to the Elk River Star newspaper. The comment period ended on 20 October 2022. The City received written comment letters from the Minnesota Department of Transportation, Minnesota State Historic Preservation Office, and Minnesota Department of Natural Resources. None of the comments recommended preparation of an Environmental Impact Statement (EIS). The City Council on 14 November 2022 adopted responses to the comments confined to substantive issues that “address the accuracy and completeness of the material contained in the EAW, potential impacts that may warrant further investigation before the project is commenced, and the need for an EIS on the proposed project” (MN Rules 4410.1600). The City Council also adopted Findings of Fact that preparation of an Environmental Impact Statement is not required in accordance with Minnesota Rules 4410.1700, Subp 7. The development proposed with the revised plans for the subject property is within the scope of review analyzed by the EAW; an amendment of the EAW findings is not warranted or required. Building. The PUD Development Stage Plan includes one six story building on the north side of Lot 1, Block 1. The total area of the proposed building 177,409 square feet with 135 multiple family dwellings, 12,784 square feet of retail and service commercial space, and an enclosed at grade garage with 65 parking spaces. The multiple family dwellings are located above the enclosed garage, whereas the commercial space is located at grade together with the multiple family building entrance and common spaces south of the enclosed garage.  Exterior Materials. Section 11-17-4.C of the Zoning Ordinance establishes exterior finish requirements for multiple family buildings and Section 11-17-4.D.1 of the Zoning Ordinance for commercial buildings. The primary difference between the two requirements is that multiple family buildings must have 50 percent of the exterior materials comprised of brick or stone with commercial buildings required to have 65 percent of the exterior finish comprised of brick, store, or glass. The Planning Commission has recommended in the past that the commercial standard apply to mixed use development and is proposing to implement this requirement for the M-1, Mixed Use District under consideration. The proposed building utilizes large windows throughout, three colors of fiber cement siding for the second story and above and a CMU block for the base of the building. The colors of the fiber cement siding provide some variation for the building design, but use of different textures or panels would increase the degree of variation and improve aesthetics. 4 The submitted plans indicate that the proposed exterior finish is comprised of 26.7 percent glass and 5.3 percent CMU materials for at total of 32.0 percent Grade A finishes. The exterior materials must be revised to bring use of Grade A materials to be at least 65 percent of the exterior finish of the proposed building.  Building Height. The proposed building is six stories in height measuring 70 feet to the flat roof. There is a roof deck on the Mississippi River side of building. The are also elevator and HVAC mechanicals on the roof that are exempt from height limits by Section 11-17-3.B of the Zoning Ordinance. For comparison purposes, the height of other buildings in the City are as follows: Stories Height Mid-Point Peak Wyndham Hotel 4 46ft. 69ft. Riverview Landing 4 55ft. 57ft. The Village 4 40ft. 47ft. The proposed height of the building is within the 75 feet being considered by the Planning Commission for the M-1, Mixed Use District. The Emergency Services Director has stated there is no issue from a public safety perspective with the height of the proposed building.  Multiple Family Dwelling Units. Section 11-17-6 of the Zoning Ordinance requires the following minimum floor area for each multiple family dwelling unit to ensure an adequate living area. The floor area proposed for the multiple family dwelling units all exceed the minimum requirements of the Zoning Ordinance. # of Bedrooms Number of Units % of Total Units Minimum Floor Area Required Proposed Floor Area Studio 14 10% 500sf. 548-579sf. 1 Bedroom 87 64% 700sf. 711-870sf. 2 Bedroom 29 22% 780sf. 1,050-1,267sf. 3 Bedroom 5 4% 860sf. 1,633sf. Section 11-17-7 of the Zoning Ordinance limits studio apartments to 10 percent of the total number of dwelling units, but the 2020 Multiple Family Housing Study recommends allowing up to 30 percent studio apartments based on current construction practices. The proposed 14 studio apartments are 10 percent of the total number of dwelling units. The proposed multiple family dwellings have 1.3 bedrooms per dwelling unit. 5  Lot Requirements. Without considering the commercial floor area, the density of the proposed development of Lot 1, Block 1 with the initial 150 dwelling units is 27.1 dwelling units per acre. The 2023 Comprehensive Plan does not establish a limit for residential density of mixed-use development, but the M-1 District under consideration by the Planning Commission would includes a 1,000 square foot per dwelling unit lot area requirement (or a density of 43 dwelling units per acre). The proposed density of the dwelling units is appropriate for an urban density mixed-use development envisioned for the subject property by the 2023 Comprehensive Plan.  Floor Area Ratio: The M-1, Mixed Use District being considered by the Planning Commission does not include a maximum floor area ratio limit for a residential or mixed use building unless the lot abuts certain residential zoning districts. The subject property does not abut any existing or planned residential districts. However, for reference purposes, the floor area ratio of the proposed building, not including the garage, on Lot 1, Block 1 is: o Multiple family space only: 0.66 o Multiple family and commercial space: 0.72 The floor area ratio for the mixed use building is appropriate for the site given that Outlot A cannot be developed except as public or private open space. Setbacks. Setbacks may be established specific to a PUD District and modified by a PUD Development Stage Plan.  The proposed building is setback 10.0 feet from the Quantrelle Avenue right-of-way. The typical setback required from public street rights-of-way is 30 feet, which is the standard proposed for the M-1, Mixed Use District. The proposed 10 foot setback does not cause issue with visibility on the public street and maximizes the development of the subject property between Quantrelle Avenue and the 300 foot setback from the Mississippi River required for by the WS District provisions.  The proposed building 19.3 feet from the north property line, which leaves space for only a 12.0 foot wide access drive along the north property line (with no setback from the private drive to the north property line. The developer must provide documentation that the proposed building setback from the north property line complies with the Fire Code and that a 20.0 wide fire lane is not required, which is to be subject to review and approval of the Emergency Services Director. 6 A shared access agreement for the private drive abutting the north line of Lot 1, Block 1 is also to be required to allow the encroachment into the typical five foot setback required by Section 11-21-5.B.2 of the Zoning Ordinance as shown on the site plan.  Outlot A provides for permanent physical separation of the proposed building from the Mississippi River and any applicable setback requirements related to the WS, Wild, Scenic, and Recreational River District. The setbacks proposed on the site plan are appropriate in order to maximize the developable property within the subject site outside of the Wild, Scenic and Recreational River District. Traffic. The subject site is accessed via Quantrelle Avenue. Quantrelle Avenue is an existing two lane street with shoulders and concrete curb having a width of 32 feet. Quantrelle Avenue intersects 90th Street at a four-way intersection to the north of the subject property. The developer completed a Traffic Impact Study for development of 387 dwelling units, 51 hotel rooms and 35,000 square feet of commercial space as part of the Environmental Assessment Worksheet to estimate the trips generated by the proposed project and potential impacts at the intersection of Quantrelle Avenue and 90th Street to evaluate the potential need for improvements. The study found no considerable delays or queueing issues caused by the proposed for any of the approaches to the Quantrelle Avenue and 90th Street intersection and no mitigation efforts were recommended. With the current proposed development scaled back from the scope of the project analyzed by the EAW traffic study, adequate capacity exists with existing streets to serve the proposed development. Access. The subject property is proposed to have two initial and up to three accesses to Quantrelle Avenue. Section 11-21-6.B.2 of the Zoning Ordinance requires accesses for multiple use developments onto Quantrelle Avenue to be a minimum of 50 feet apart of another driveway. All of the proposed accesses comply with the spacing requirements established by the Zoning Ordinance. Section 11-21-C.2 of the Zoning Ordinance limits the width of an access to a public street to 30 feet unless approved by the City Engineer for circulation and turning movement purposes. The three accesses are all less than 30 feet in width and comply with the requirements of the Zoning Ordinance. Street lighting is to be extended from Otsego Waterfront East along Quantrelle Avenue to the south line of Lot 1, Block 1 in accordance with Section 8-8-5 of the City Code. The location of proposed street lighting is to be subject to review and approval of the City Engineer. The developer will pay a fee for the installation of the street lighting as provided for by the fee schedule and City Code. Off-Street Parking. The table below outlines the number of parking stalls required for the proposed development based on the requirements of Section 11-21-8 of the Zoning Ordinance: 7 Otsego Zoning Ordinance Calculation of Required Parking Spaces Requirement Unit/Area Required Spaces Multiple Family Dwelling 2.0 stalls/du 135du. 270 Commercial 1 stall/200sf. 12,784sf. 64 Total 334 The developer also engaged with SRF Consulting Group, Inc. to prepare a study of estimated parking demand for the proposed use. The study evaluated parking estimates for a mixed-use development established by the City of Wayzata, which the Planning Commission is considering for inclusion in the Zoning Ordinance to address mixed use developments. The Wayzata methodology for calculating off-street parking requirements for mixed-use land uses provides for a reduction in the number of off-street parking stalls needed based on a shared parking arrangement and daily time periods for weekdays and weekends. The calculation of parking requirements for the proposed development based on the Wayzata formula for determining shared parking is shown in the table below: Wayzata Mixed-Use Estimate of Required Parking Spaces Zoning Ordinance Required Stalls Weekday Weekend 12:00AM- 7:00AM 7:00AM- 6:00PM 6:00PM- 12:00AM 12:00AM- 7:00AM 7:00AM- 6:00PM 6:00PM- 12:00AM Multiple Family 270 270 162 270 270 203 270 Commercial 64 0 58 39 0 64 39 Total 334 270 220 305 270 267 309 The table below summarizes construction of 246 parking spaces within the enclosed garage identified on the architectural plans and surface parking illustrated on the site plan within Lot 1, Block 1. Parking Area Spaces Garage 65 Surface 181 Total 246 8 The number of proposed off-street parking spaces is 88 stalls less than required by the Zoning Ordinance and 63 spaces less than the mixed use analysis for determining the number of parking spaces to be provided on site. The number of parking spaces within the garage is also less than the 121 spaces required to provide at least one enclosed parking space for each multiple family dwelling unit having one or more bedrooms as is being considered by the Planning Commission for the M-1, Mixed Use District. The site plan also illustrates an additional 106 off-street parking spaces proposed as proof-of- parking. City staff recommends that the site plan be revised to provide for construction of 246 off-street parking stalls including one space within an enclosed structure attached to the principal building for each multiple family dwelling unit with one bedroom or more (121 spaces). The surface parking area is designed with spaces that are nine feet wide by 20 feet deep accessed by drive aisles that are 24 feet in width. The parking area is to be surfaced with asphalt or concrete and surrounded by concrete curb as required by Section 11-21-7.B, C, and D. The design and construction of the surface off-street parking area is to be subject to review and approval of the City Engineer. The proposed off-street parking area is not setback from the Quantrelle Avenue right-of-way the 15 feet required by Section 11-21-5.B.1 of the Zoning Ordinance. Building the parking at the property line is acceptable in the interest of maximizing the developable area of Lot 1, Block 1 in consideration of preserving Outlot A through the WS District. The boulevard between Quantrelle Avenue and the off-street parking area is sufficiently wide to avoid any visual impairment for vehicles entering the public street. The pedestrian sidewalk is also centered in the boulevard to avoid potential conflicts with vehicles entering or leaving the subject property. Pedestrian Access. There is no sidewalk on Quantrelle Avenue. Pedestrian connectivity of the proposed development to Otsego Waterfront East and Carrick’s Landing is to be provided for by:  Construction of a five foot wide concrete sidewalk the full width of Quantrelle Avenue abutting Lot 1, Block 1.  A trail overlaid by public access easement through Outlot A and Outlot B as a condition of approval with timing to be determined at the time of final plat approval. Landscaping. The submitted plans do not include a landscape plan as required by Section 11- 19-2.B if the Zoning Ordinance. A landscape plan must, at a minimum, be submitted prior to consideration of the application by the City Council and is to be subject to review by the Zoning Administrator. 9 Exterior Lighting. Section 11-16-6 of the Zoning Ordinance establishes performance standards for exterior lighting. All exterior light fixtures are to have a 90-degree horizontal cut-off and not cast more than 0.4 foot-candles of light at the property lines as required by Section 11-16-6.C of the Zoning Ordinance. An exterior lighting plan including photometric measurements of light intensity and indicating the type, location, and height of all exterior light fixtures must be submitted prior to issuance of a building permit and is subject to review and approval of the Zoning Administrator. Signs. The architectural plans include identification signs on the west and north elevations of the building. City staff recommends establishing sign allowances for Lot 1, Block 1 as wall signs affixed on any elevation up to 15 percent of the wall area, but not including the at-grade parking garage, with the maximum area of any individual sign limited to 200 square feet. Utilities. The proposed development is to be served by City sewer and water utilities. There are existing trunk sewer and water lines within Quantrelle Avenue adjacent to the subject site. The developer has submitted plans for connection to sewer and water utilities, as well as improvement of the existing sewer lift station in Quantrelle Avenue necessary to accommodate the proposed development. All utility plans are subject to review and approval of the City Engineer. The developer is required to pay Utility Availability Charges at the time of final plat approval. The Utility Availability Charges are to be based on a Residential Equivalent Connection (REC) equated to the estimated sewer flow for the proposed development. Utility Connection Charges calculated in accordance with the provisions of the City Code will be required to be paid at the time a building permit is issued. Grading Plan. All of Outlot A and Outlot B are within the Floodway zone along the Mississippi River. Outlot A is bisected north-to-south by a drainageway overlaid by a drainage and utility easement to provide an outlet for the City regional stormwater basin to the north within Outlot A, Waterfront East. The outlet for the regional stormwater basin must be maintained as part of the grading plan for the subject site to the point at which the stormwater is discharged to the Mississippi River. The developer has submitted plans for grading, drainage, and erosion control for development of Lot 1, Block 1. All floodplain, grading, drainage, and erosion control issues are to be subject to review and approval of the City Engineer. Easements. Section 11-8-12.A of the Subdivision Ordinance requires 10 foot wide drainage and utility easements to be dedicated at the perimeter of Lot 1, Block 1, which are shown on the 10 preliminary plat. Temporary drainage and utility easements that expire upon platting will only be required over Outlots A, B, and C. All drainage and utility easements are to be subject to review and approval of the City Engineer. Outlots. The preliminary plat includes three outlots:  Outlot A is the portion of the subject property governed by the provisions of the Wild Scenic Recreational River District adopted by the City as Chapter 92 of the Zoning Ordinance in accordance with Minnesota Rules. Outlot A includes an existing City park easement for a trail along the Mississippi River extending south of Carrick’s Landing and out to Quantrelle Avenue, as well as a drainageway overlaid by drainage and utility easement. The developer has submitted a concept plan for potential recreational development of Outlot A. Private and public recreational activities are an allowed use within Subdistrict C of the WSRR District subject to management plan standards. These proposed improvements are not being considered as part of the current PUD Development Stage Plan application. Future proposals to undertake these improvements will require a separate application for PUD Development Stage plan approval. As part of the development of Outlot A, the City reserves the right to require dedication of land and/or park and trail easement for public access to the area, as well as ingress/egress and shared parking easements over Lot 1, Block 1 for public park purposes. Public access would be finalized as part of the PUD Development Stage Plan for Outlot A as a condition of approval.  Outlot B is the portion of the subject property that is within the floodway zone of the Mississippi River. The developer is working with the Army Corps of Engineers remove Outlot B from the floodway zone to make the area developable with a future phase of the project. No action regarding Outlot B is required as part of the current PUD Development Stage Plan application.  Outlot C is a remnant parcel to the south of a Minnesota Department of Transportation outlet to the Mississippi River that will also be retained by the developer for potential future development. Park Dedication. The PUD Development Stage Plan does not contemplate dedication of land to the City for public park purposes. The City will reserve the right to require dedication of land and or easements over Outlot A for public park purposes as part of a future PUD Development Stage Plan when improvement of Outlot A is proposed. For the current PUD Development Stage Plan, park dedication requirements are proposed to be satisfied as a cash fee in lieu of land based on the fee schedule in effect at the time of final plat approval. 11 Development Contact. Section 10-10-4.A of the Subdivision Ordinance requires that the developer enter into a development contract with the City to provide for construction of the project, completion of any public improvements, establishment of required securities, and payment of applicable fees. The development contract will address performance relative to the PUD Development Stage Plan as required by Section 11-9-7 of the Zoning Ordinance. The development contract is to be executed by the developer prior to approval by resolution of the City Council and recorded with the property. RECOMMENDATION Our office recommends approval of the applications as outlined below. POSSIBLE ACTIONS A. Motion to recommend approval of a preliminary plat, PUD Development Stage Plan for Lot 1, Block 1, and vacation of drainage and utility easements for Otsego Waterfront, subject to the following stipulations: 1. Approval of the preliminary plat shall not guarantee access to sanitary sewer service. The City shall only allocate sanitary sewer capacity to approved final plats with signed development contracts to assure the City of timely development. 2. The subject site shall be developed in accordance with the site and building plans submitted to the City subject to the stipulations, limitations, and conditions as approved by the City Council in accordance with Section 11-9-4 of the Zoning Ordinance. 3. The exterior finish materials for the proposed building shall comply with Section 11-17-4.D.1 of the Zoning Ordinance, subject to review and approval of the Planning Commission. 4. The developer shall document that the building setback from the north lot line and fire access and circulation north of the building complies with the Fire Code, subject to review and approval of the Emergency Services Director. 5. An ingress/egress agreement shall be required between Lot 1, Block 1 and the abutting parcel to the north to allow the drive aisle encroachment into the setback required by Section 11-21-5.B.2. 6. Street lighting shall be installed along Quantrelle Avenue from Otsego Waterfront East abutting the Nathe Addition and proposed plat as required by Title 8, Chapter 8 of the City Code, subject to review and approval of the City Engineer. 12 7. Off-Street Parking: a. A minimum of 309 off-street parking spaces shall be constructed. b. A minimum of 121 off-street parking spaces shall be provided within an enclosed structure attached to the principal building. c. A minimum of 121 enclosed off-street parking spaces shall be allocated only for use by residents of the multiple family dwelling units. d. The developer shall dedicate an easement to the City allowing public parking within the surface parking of Lot 1, Block 1 for access to Outlot A, subject to review and approval of the Zoning Administrator. 8. The submitted plans shall be revised to include a pedestrian connection from the proposed building to the public trail at Carrick’s Landing through Outlot A and Outlot B overlaid by a public trail easement with timing of construction to be determined at final plat approval 9. A landscape plan meeting the requirements of Section 11-19-2.B of the Zoning Ordinance, subject to review and approval of the Zoning Administrator, shall be submitted prior to consideration of the application by the City Council. 10. An exterior lighting plan including photometric measurements of light intensity and indicating the type, location, and height of all exterior light fixtures in compliance with Section 11-16-6 of the Zoning Ordinance shall be submitted and is subject to review and approval of the Zoning Administrator. 11. Lot 1, Block 1 shall be allowed only wall signs on any elevation up to 15 percent of the wall area, but not including the at-grade parking garage, with the maximum area of any individual sign limited to 200 square feet; a sign permit is required prior to placement of any sign upon the property, subject to review and approval of the Zoning Administrator. 12. All utility plans shall be subject to review and approval of the City Engineer. 13. The developer shall pay Utility Availability Charges at the time of final plat approval based on a Residential Equivalent Connection (REC) equated to the estimated sewer flow for the proposed development. 14. All floodplain, grading, drainage, and erosion control plans and issues shall be subject to review and approval of the City Engineer. 13 15. Outlot A, Outlot B, and Outlot C shall be overlaid by temporary drainage and utility easements to expire upon approval of a final plat as a Lot/Block and/or PUD Development Stage Plan. 16. All drainage and utility easements shall be subject to review and approval of the City Engineer. 17. Park dedication requirements for the preliminary plat shall be satisfied as a cash fee in lieu of land calculated and paid at the time of final plat approval. 18. The City reserves the right to required dedication of land and or easement for park purposes over Outlot A as a condition of a future PUD Development Stage Plan approval. 19. The developer shall enter into a development contract at the time of final plat approval as required by Section 10-10-4.A of the Subdivision Ordinance and Section 11-9-7 of the Zoning Ordinance, subject to review by the City Attorney and approval of the City Council. B. Motion to deny the applications based on a finding that the request is inconsistent with the policies of the Comprehensive Plan and intent of the Zoning Ordinance. C. Motion to table. c. Adam Flaherty, City Administrator/Finance Director Audra Etzel, City Clerk Ron Wagner, City Engineer David Kendall, City Attorney Site Location Map 460 ft Overview Legend Roads CSAHCL CTYCL MUNICL PRIVATECL TWPCL Road Labels Highways Interstate State Hwy US Hwy City/Township Limits c t Parcels Torrens 020(1780'(6,*1*5283//&'&21&(37'(6,*16800$5<48$175(//($9(276(*201276(*2:$7(5)5217',675,&71257+3$5&(/6287+3$5&(/6,7(727$/$5($%8,/',1*&29(5$*(/27&29(5$*(%8,/',1*)$5352-(&729(59,(:6)6)6)352-(&77($0'(9(/23(5$5&+,7(&7&,9,/(1*,1((5/$1'6&$3($5&+,7(&702'(51&216758&7,212)0,11(627$2*'(1675((71:(/.5,9(501020(1780'(6,*1*528335,25$9(168,7($673$8/01'(0$5&/$1'6859(<,1* (1*,1((5,1*5'$9(1%522./<13$5.016,7($''5(66 &855(17 48$175(//($9(18(276(*20,11(627$186$*($5($%</(9(/VW)ORRU &,5&8/$7,21 6)VW)ORRU &20021 6)VW)ORRU *$5$*( 6)VW)ORRU 5(7$,/ 6)VW)ORRU 6(59,&( 6)VW)ORRU 9(57,&$/&,5&8/$7,21 6)QG)ORRU &,5&8/$7,21 6)QG)ORRU &20021 6)QG)ORRU 6(59,&( 6)QG)ORRU 81,7 6)QG)ORRU 9(57,&$/&,5&8/$7,21 6)UG)ORRU &,5&8/$7,21 6)UG)ORRU 6(59,&( 6)UG)ORRU 81,7 6)UG)ORRU 9(57,&$/&,5&8/$7,21 6)WK)ORRU &,5&8/$7,21 6)WK)ORRU 6(59,&( 6)WK)ORRU 81,7 6)WK)ORRU 9(57,&$/&,5&8/$7,21 6)WK)ORRU &,5&8/$7,21 6)WK)ORRU 6(59,&( 6)WK)ORRU 81,7 6)WK)ORRU 9(57,&$/&,5&8/$7,21 6)WK)ORRU &,5&8/$7,21 6)WK)ORRU &20021 6)WK)ORRU 6(59,&( 6)WK)ORRU 81,7 6)$5($%<86$*(&,5&8/$7,21 6)&20021 6)*$5$*( 6)5(7$,/ 6)6(59,&( 6)81,7 6)9(57,&$/&,5&8/$7,21 6)*UDQGWRWDO 6)*5266$5($%</(9(/VW)ORRU 6)QG)ORRU 6)UG)ORRU 6)WK)ORRU 6)WK)ORRU 6)WK)ORRU 6)*UDQGWRWDO 6)81,70,;%(' 6)6)  %(' 6)6)  %(' 6)6)  %(' 6)6)  %(' 6)  678',2 6)6)  727$/81,76&2175$&725%$8(5'(6,*1%8,/'67$9(13/<0287+01 $ 48$175(//($9((0(5*(1&<75$)),&21/<3529,'(%$55,(5$65(48,5('(0(5*(1&<75$)),&21/<3529,'(%$55,(5$65(48,5('  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//638%/,&3/$=$38%/,&5(7$,/(175</2%%<(175<)/22':$</,1(3(5)(0$0$36((&,9,/'5$:,1*667$,5(;,767$,5(;,7*$5$*((175<  %,&<&/(67$//6),5('(3$570(17$&&(6652$'75$16)250(5$1'*(1(5$725 127($//),1$/&,9,/$1'/$1'6&$3('(6,*16$1'3/$16$5(72%(6((1,1&,9,/'5$:,1*66,7(3/$1$5&+,7(&785$//<6+2:1)255()(5(1&(21/<   38%/,&5(7$,/(175<38%/,&5(7$,/(175<38%/,&5(7$,/(175<38%/,&5(7$,/(175<5(7$,/6(59,&(&2857*$5$*(67$//6,1),/75$7,21%$6,13522)2)3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//6  $7685)$&(3$5.,1*67$//63$5.,1*6800$5<*$5$*(67$//6$7685)$&(3$5.,1*67$//63522)2)3$5.,1*67$//6727$/3$5.,1*67$//6522)'(&.020(1780'(6,*1*5283//&'&21&(37'(6,*1 6,7(3/$148$175(//($9(276(*201276(*2:$7(5)5217',675,&71  6,7(3/$1 *$5$*(&,5&8/$7,216(59,&(&200215(67$85$175(7$,/*$5$*((175$1&(5(6,'(17,$/75$6+&+87(6)*$5$*(6)%,.(66)67$,56)75$6+6)(/(9$7256)/2%%<6)0$,/6)3$&.$*(6)5(7$,/6)67$,56):$7(56)9(676)(/(9$7256)(/(9/2%%<6)2)),&(6)556)/281*(6)-8,&(%$56)556)),71(666)*2/)6,08/$7256)(/(&75$16)250(5 *(1(5$725020(1780'(6,*1*5283//&'&21&(37'(6,*1 ),567)/22548$175(//($9(276(*201276(*2:$7(5)5217',675,&71  VW)ORRU %('81,7%('81,7678',2&,5&8/$7,216(59,&(&200215(67$85$175(7$,/6)81,726)81,736)81,736)81,7/6)81,7/6)81,7)6)81,7)6)*$0(/281*(6)81,7)6)81,716)81,7(6)81,7/6)81,7/6)81,7)6)81,7)6)81,7*6)&20081,7<52206)81,7.6)81,726)81,746)81,7+6)81,706)81,7/6)81,7&6):)+2)),&(6)81,7/6)81,7%6)81,7/6)81,726)81,736)81,736)81,7/6)81,7/6)81,7)6)81,7)6)81,7-6)81,7)6)81,716)81,7(6)81,7/6)81,7/6)81,7)6)81,7)6)81,7*6)81,726)81,7.6)81,726)81,746)81,7+6)81,706)81,7/6)81,7&6)81,7%6)81,7/6)81,7%6)81,7/020(1780'(6,*1*5283//&'&21&(37'(6,*1 6(&21' 7+,5')/22548$175(//($9(276(*201276(*2:$7(5)5217',675,&71  QG)ORRU  UG)ORRU %('81,7%('81,7%('81,7&,5&8/$7,216(59,&(&20021%('81,7678',2%('81,76)81,726)81,736)81,736)81,7/6)81,7/6)81,7)6)81,7)6)81,7-6)81,7)6)81,716)81,7(6)81,7/6)81,7/6)81,7)6)81,7)6)81,7*6)81,726)81,7.6)81,726)81,746)81,7+6)81,706)81,7/6)81,7&6)81,7%6)81,7/6)81,7%6)81,7/6)81,726)81,736)81,736)81,7/6)81,7/6)81,7)6)81,7)6)81,7-6)81,7)6)81,716)81,7(6)81,7/6)81,7/6)81,7)6)81,7)6)81,7*6)81,726)81,7.6)81,726)81,7+6)81,706)81,7/6)81,746)81,7&6)81,7%6)81,7/6)81,7%6)81,7/020(1780'(6,*1*5283//&'&21&(37'(6,*1 )2857+ ),)7+)/22548$175(//($9(276(*201276(*2:$7(5)5217',675,&71  WK)ORRU  WK)ORRU %('81,7%('81,7%('81,7&,5&8/$7,216(59,&(&20021%('81,7678',26)81,726)81,736)81,736)81,7/6)81,7/6)81,7)6)81,7)6)81,7-6)81,7)6)81,716)81,7(6)81,7/6)81,7/6)81,7)6)81,7)6)81,7*6)81,726)81,7.6)81,726)81,7/6)81,7&6)81,7%6)81,7/6)81,746)6.</281*(6)81,7%6)81,7/522)'(&.020(1780'(6,*1*5283//&'&21&(37'(6,*1 6,;7+)/225 522)48$175(//($9(276(*201276(*2:$7(5)5217',675,&71  WK)ORRU  5RRI VW)ORRU 5RRI QG)ORRU UG)ORRU WK)ORRU WK)ORRU WK)ORRU  ; :,1'2:7<36:,1*,1*3$7,2'2257<3+25,=217$/),%(5&(0(176,',1*&+$5&2$/+25,=217$/),%(5&(0(176,',1*7$1&08%$6('$5.*5(<+25,=217$/),%(5&(0(176,',1*$&&(17$7,16(76:+,7($/80,180%$/&21<:3,&.(75$,/,1*:+(5(6+2:1%/$&.$/80,180%$/&21<:3,&.(75$,/,1*7<3 ; :,1'2:$7&08%$6(7<3%/$&.$/80,180%$/&21<:*/$665$,/,1*7<3$7$&&(17,16(760$7(5,$/3(5&(17$*(66,',1*6)  *5$'(%0$7(5,$/%5,&.6)  *5$'($0$7(5,$/&086)  *5$'(%0$7(5,$/*/$=,1*6)  *5$'($0$7(5,$/0$7(5,$/*5$'(3(5&(17$*(6*5$'($0$7(5,$/ *5$'(%0$7(5,$/ VW)ORRU 5RRI QG)ORRU UG)ORRU WK)ORRU WK)ORRU WK)ORRU +25,=217$/),%(5&(0(176,',1* &+$5&2$/+25,=217$/),%(5&(0(176,',1* 7$1&08%$6('$5.*5(<+25,=217$/),%(5&(0(176,',1* $&&(17$7,16(76:+,7($/80,180%$/&21<:3,&.(75$,/,1*:+(5(6+2:16:,1*,1*3$7,2'2257<3%/$&.$/80,180%$/&21<:3,&.(75$,/,1*7<3%/$&.$/80,180%$/&21<:*/$665$,/,1*7<3$7$&&(17,16(76 ; :,1'2:7<3),%(5&(0(173$1(/6725()52176 3$,17&2/2563(57(1$17 %5,&.9(1((5&+$5&2$/$/80,1806725()52176<67(0&/($5$12',=('0$7(5,$/3(5&(17$*(66,',1*6)  *5$'(%0$7(5,$/%5,&.6)  *5$'($0$7(5,$/&086)  *5$'(%0$7(5,$/*/$=,1*6)  *5$'($0$7(5,$/0$7(5,$/*5$'(3(5&(17$*(6*5$'($0$7(5,$/ *5$'(%0$7(5,$/ 020(1780'(6,*1*5283//&'&21&(37'(6,*1 1257+ 6287+(/(9$7,21648$175(//($9(276(*201276(*2:$7(5)5217',675,&7  1RUWK(OHYDWLRQ  6RXWK(OHYDWLRQ VW)ORRU 5RRI QG)ORRU UG)ORRU WK)ORRU WK)ORRU WK)ORRU &08%$6('$5.*5(<+25,=217$/),%(5&(0(176,',1*&+$5&2$/%5,&.9(1((5&+$5&2$/0$7(5,$/3(5&(17$*(66,',1*6)  *5$'(%0$7(5,$/%5,&.6)  *5$'($0$7(5,$/&086)  *5$'(%0$7(5,$/*/$=,1*6)  *5$'($0$7(5,$/%/$&.$/80,180%$/&21<:3,&.(75$,/,1*7<3 ; :,1'2:7<36:,1*,1*3$7,2'2257<3*/$665$,/,1*$7522)'(&.0$7(5,$/*5$'(3(5&(17$*(6*5$'($0$7(5,$/ *5$'(%0$7(5,$/ VW)ORRU 5RRI QG)ORRU UG)ORRU WK)ORRU WK)ORRU WK)ORRU +25,=217$/),%(5&(0(176,',1*&+$5&2$/%5,&.9(1((5&+$5&2$/+25,=217$/),%(5&(0(173$1(/$&&(17$7,16(7&08%$6('$5.*5(< ; :,1'2:&$676721(%$6(0$7(5,$/3(5&(17$*(66,',1*6)  *5$'(%0$7(5,$/%5,&.6)  *5$'($0$7(5,$/&086)  *5$'(%0$7(5,$/*/$=,1*6)  *5$'($0$7(5,$/ ; :,1'2:7<3%/$&.$/80,180%$/&21<:3,&.(75$,/,1*7<36:,1*,1*3$7,2'2257<3$/80,1806725()52176<67(0&/($5$12',=('0$7(5,$/*5$'(3(5&(17$*(6*5$'($0$7(5,$/ *5$'(%0$7(5,$/ 020(1780'(6,*1*5283//&'&21&(37'(6,*1 ($67 :(67(/(9$7,21648$175(//($9(276(*201276(*2:$7(5)5217',675,&7  (DVW(OHYDWLRQ  :HVW(OHYDWLRQ 12" SCARIFIED SOIL BOT. ELEV.= 855.8BERM MIN. = 860.01:4 MAX.1:4 MAX.100-YR HWL = 859.40EOF = 859.5TURF REINFORCEMENT MAT CATEGORY 2BERM = 860.0BERM = 860.0OVERFLOW PER 2/C25" SOIL MEDIA70% SAND (MEETING SM CLASSIFICATION)30% MNDOT 3890 GRADE 2 COMPOST STESSEN 89°58'51" W 400.00N 76°02'53" WN 26°3 6' 1 3" W 5 4 8. 2 2N 89°37'22" W 628.91S 01°23'24" W 492.39N 89°37'08" W82.6675.4580.0S 89°29'15" E 356.92S 89°58'51" E 356.92S 26°3 6' 1 3" E 9 0. 5 1 S 63°31'58" W 81.63L O T 1B L O C K 1O U T L O T CO U T L O T ASSSSSSEO U T L O T B40.0083.16505.75S 02°08'34" E 629.3077.50129.41SL=131.82 R=523.00 =14°26'2 7 " Buildin g S et b a c k Li n e Front - 3 0 f e et Side - 1 0 f e etS 06°26'07" W 159.81S 00°16'26" E 148.31S 07°47'30" E 128.31S 04°28'21" W 190.44NNTree Protection Fence ►► ►► ►►►►►►►►►►►►►►►►▌▌▌▌▌▌▌▌▌▌▌ESSE►▌SSSL O T 1B L O C K 1O U T L O T AO U T L O T B14.311.3R20.0R20.0R20.0R20.024.0 24.0 24.0 R8.0R8.0R10.012.024.08.5 (TYP.))8.5 (TYP.)8.5(TYP.)24.020.0(TYP.)8.5(TYP.)((20.0(TYP.)24.0R2.0R4.0R4.0R2.08.5(TYP.)20.0(TYP.)24.0R18.0R10.08.5(TYP.)20.0(TYP.)R10.068.852.924.0R30.0R8.012.0►►►▌ ESSE80.0SSSSESSSSSSSS█████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████ ████ ████ █████ ███ ████ ████ ████ ████ ███ ████ ████ ████ ████ ████ ████████ █████ ███ █ ██████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████►► ►► ►►►►►►►►►►►►►►►►862860860862862864864862862862858858860854 854856856858▌▌▌▌▌▌▌▌▌▌▌►►830███ ►►DSESSESSSSESSSSSSSS►► ►► ►►►►►►►►►►►►►►►►▌▌▌▌▌▌▌▌▌▌▌ ▌▌SSE S 0+001+002+003+004+004+670+00862.1862.081+00862.6862.632+00862.3862.303+00862.0861.994+00862.4862.395+00844848852856860864868844848852856860864868 ████►►ESSESSSS40.0083.16505.75S 02°08'34" E 629.3077.50129.41S 06°26'07" W 159.81S 00°16'26" E 148.31S 07°47'30" E 128.31S 04°28'21" W 190.44..██████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████ ███████ ██████ ███████████ ███████ ████4141██ ████2929██ ████████████ ██████ █████ █████ ████ ████ ████ ██████ ██████████ ██████ █████ █ ████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████862860860862862864864862862862858858860854 854856856858►► ►► ►►►►►►►►►►►►►►►►▌▌▌▌▌▌▌▌▌▌▌ESSSSSSSS505.7505 755S 06°26'07" W 159.81S 04°28'21" W 1W190 4490.4404 2821W1904██████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████████8628628628686286286086086086086086086286286286286286444864486448644864486448648648648648648648888888888862862862862862862862862862862862862►► ►►►►► ►►►►►►►►►►►►►►►►►►►►►►►►►►►▌▌▌▌▌▌▌▌▌▌7575▌▌▌▌██████████████████████████████████████████████████████████████████████████████86286286228628629W2██28█0►4E20S█S8►854█ █ █ █ █9►►585888█►██ █████►►███8585██44444444██99███ ███►►►SS00622EE4841000█222WW99████████86888█1606SS████████████8686868686868686██SS666W15188███████████████████████████████ Building Setback LineFront - 30 feetSide - 10 feet16'-20'OPENING16'-20'OPENING N 0 SCALE 1” = 100’ 100 200 400 MISSISSIPPI LANDING OTSEGO, MN CONCEPTUAL LANDSCAPE DESIGN 2024.03.25 1 FOUNTAIN PLANTED ISLAND EXERCISE STATION PARK BENCH PAVED PATH TO FISHING AREA SLED HILL BOAT DOCK OPEN SPACE POLLINATOR GARDEN & TRAILS BOARDWALK EVENT LAWN AMPHITHEATER PICNIC & HAMMOCK GROVE RESORT STYLE AMENITY POOL PAVILION OUTDOOR DINING PLAYGROUND 1 1 1 2 2 2 3 3 3 3 4 4 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 LEGEND MISSISSIPPI RIVERCARRICK’S LANDING PARKMN STATE HIGHWAY 10110 15 16 17 16 17 Review No. 1 ENGINEERING REVIEW Commercial/Residential Subdivision Preliminary Plat Development Plans for the City of Otsego by Hakanson Anderson Submitted to: Honorable Mayor and City Council cc: Adam Flaherty, City Administrator/Finance Director Audra Etzel, City Clerk Dan Licht, City Planner Dave Kendall, City Attorney Jesse Hartung, Modern Construction of MN Jeffery Prasch, Demarc Land Surveying & Engineers Reviewed by: Ronald J. Wagner, P.E. Date: May 15, 2025 Proposed Development: Otsego Waterfront District Development Location: A portions of the NE ¼ of the NW ½ of Section 236, T121, R23. East of Quantrelle Avenue and South of 90th Street Applicant: Jesse Hartung Developer: Modern Construction of MN 18837 Ogden Street Elk River, MN 55330 Owners of Record: Modern construction of MN, Inc. Purpose: This is a proposed mixed use PUD development including residential and commercial space on approximately 13.8+ acres in the City of Otsego, Wright County, Minnesota. The proposed development will be served with municipal water, sanitary sewer, storm sewer, and public streets typical of an urban setting. Jurisdictional Agencies: City of Otsego, Wright County, Minnesota Department of (but not limited to) Health, Minnesota Department of Natural Resources, Minnesota Pollution Control Agency, Wright Soil and Water Conservation District. Permits Required: NPDES, Minnesota Department of Health (water), (but not limited to) Minnesota Pollution Control Agency (sanitary sewer), and Wright County PAGE 2 C:\Users\Katie\AppData\Local\Microsoft\Olk\Attachments\ooa-81b9e686-7eb7-4627-bd6b- 66c6e8655f3d\74e2054e0782466fd4566d1618a8642695198bb8d282d9a875cdba7a13c92b46\OT2525.03 RVW1.docx TABLE OF CONTENTS INFORMATION AVAILABLE SITE DEVELOPMENT PLANS (PRELIMINARY) TITLE SHEET DETAILS EXISTING CONDITIONS & REMOVALS SITE PLAN GRADING AND DRAINAGE PLAN UTILITY PLAN SANITARY FORCEMAIN PLAN AND PROFILE LIFT STATION PLAN & PROFILE SWPPP STORM WATER MANAGEMENT WETLAND/ENVIRONMENTAL OTHER CONSIDERATIONS SUMMARY AND/OR RECOMMENDATIONS PAGE 3 C:\Users\Katie\AppData\Local\Microsoft\Olk\Attachments\ooa-81b9e686-7eb7-4627-bd6b- 66c6e8655f3d\74e2054e0782466fd4566d1618a8642695198bb8d282d9a875cdba7a13c92b46\OT2525.03 RVW1.docx INFORMATION AVAILABLE Preliminary Plat for, dated 4/5/25, by Demarc Land Surveying and Engineering Preliminary Site Development Plans for Mississippi Landings, dated 4/5/2025, by Demarc Land Surveying and Engineering SWPP & Flood Analysis, for Modern Construction of Minnesota, dated 4-5-25 by Demarc Land Surveying and Engineering Geotechnical Report for Proposed Apartment Development, dated 8/25/2021, by Haugo Geotechnical Services Piezometer Water Level Summary for Otsego Apartment Development, dated 7/19/2021 and 8/25/2021, by Haugo Geotechnical Services Traffic Impact Study – Mixed Use Development, dated 1/6/2022 by SRF Additional Information Minnesota Rules, Chapter 4410 – EAW Requirement City of Otsego Engineering Manual City of Otsego Zoning and Subdivision Ordinances National Wetland Inventory Map FEMA flood map – effective 6-20-2024 PAGE 4 C:\Users\Katie\AppData\Local\Microsoft\Olk\Attachments\ooa-81b9e686-7eb7-4627-bd6b- 66c6e8655f3d\74e2054e0782466fd4566d1618a8642695198bb8d282d9a875cdba7a13c92b46\OT2525.03 RVW1.docx PRELIMINARY SITE DEVELOPMENT PLANS TITLE SHEET (C1) 1. Provide an approval signature block for the City Engineer. DETAILS (C2-C4) 2. Provide irrigation service detail standard plate no. 210. 3. Remove standard plate 308 as not used by City any longer. EXISTING CONDITIONS & REMOVALS (C5) 4. The 100-year flood elevation is based on the latest FEMA floodplain regulation study as of 6/20-2024. The elevation shall be 861.8. 5. Existing signs located near entries to development shall be relocated. SITE PLAN (C6) 6. The proposed fire lane shall meet fire code width (20’). 7. Ensure turn radius for a standard fire engine is met. Turn radius info is included. 8. The disturbed area exceeds the lot area. 9. Parking setback is required to be 15’ from ROW. Currently at 0’. 10. ADA ramps are required at all entry crossings of sidewalk. GRADING AND DRAINAGE PLAN (C7) 11. Storm sewer from infiltration pond should be directed to the ditch to the south through a swale rather than overland. 12. The existing drainage swale from the regional pond to the north shall be covered by a drainage and utility easement or be within an Outlot Deeded to the City. 13. An ingress/egress easement is necessary from Quantrelle Ave to the storm pond to allow for City inspection and City maintenance. 14. The curbing and parking island 2 parking groups south of building has no outlet for stormwater. Extend storm sewer and add catch basins as necessary. PAGE 5 C:\Users\Katie\AppData\Local\Microsoft\Olk\Attachments\ooa-81b9e686-7eb7-4627-bd6b- 66c6e8655f3d\74e2054e0782466fd4566d1618a8642695198bb8d282d9a875cdba7a13c92b46\OT2525.03 RVW1.docx UTILITY PLAN (C8) 15. Watermain shall be looped around the building to ensure adequate volume to hydrants. 16. Two hydrants must be added on the south side of the building. One near SE corner of the building and one within 100’ of the FDC. 17. Watermain size shall be 8” DIP for potential to extend around future buildings as a loop. 18. An irrigation deduct meter and back flow preventer are required. Assuming these will be located within the utility room accessible from outside of the building. 19. Show locations for an oil and flammable waste separator for the restaurant and a sprinkler riser room for utilities. 20. Profile will be required for all watermain with final plan submittal. SANITARY FORCEMAIN PLAN & PROFILE (C9) 21. Maintain lift station operation during upgrade procedure. Flow of sewage could be collected in upstream structures via honey wagon (for low demand lines), or temporary pumps placed in an upstream structure and connected to the existing 3” FM at some point downstream of the wet well. The contractor will need to provide a method and means for the upgrade process that will be acceptable to the City. 22. The existing forcemain shall be abandoned. 23. Show 90th Street. 24. The proposed forcemain shall be connected to the existing forcemain. See sheet C9 for redline. 25. Pumps and appurtenances will require final approval from the City Utility Manager. 26. Add trace wire for the forcemain. 3 wires for directional bore and 2 wires for open cut. LIFT STATION PLAN & PROFILE 27. Provide new lid to accommodate new hatch. 28. The city requires all lift station pumps to be Fairbanks-Morse, Hdromatic, or approved equal. 29. Note, the contractor shall meet the general requirements for Lift Station Design. See Appendix E in City of Otsego Engineering Manual. PAGE 6 C:\Users\Katie\AppData\Local\Microsoft\Olk\Attachments\ooa-81b9e686-7eb7-4627-bd6b- 66c6e8655f3d\74e2054e0782466fd4566d1618a8642695198bb8d282d9a875cdba7a13c92b46\OT2525.03 RVW1.docx 30. Verify the existing space is enough to accommodate the upgrade of the lift station in the cabinet. 31. The manhole where the new forcemain connect to shall have a new ring and match the finish grade. Manholes (existing or new) shall meet existing Otsego standard plates. 32. The contractor shall work with the city intergrader for SCADA “AE2S” with all lift station work. 33. Pad lock shall be added for the lift station cabinet. 34. Add a streetlight shall be installed for the lift station. SWPPP 35. Adjust plan to 861.8 for 100 year rather than 861.0. STORM WATER MANAGEMENT PLAN 36. Infiltration requirements appear to be met. Will require double infiltration ring test to verify infiltration is met. WETLAND/ENVIRONMENTAL 37. Statement certifying the environmental condition of the site including the presence of any hazardous substance as defined in Minnesota Statutes 115B.02, Subd 8. OTHER CONSIDERATIONS 38. Traffic Study by SEH has been received and shows no discernable level of service reductions. 39. A Geotechnical Report with Piezometer ground water measurements have been submitted. SUMMARY AND/OR RECOMMENDATION Please revise and resubmit.