02-22-99 CCAGENDA SECTION:
CITY OF OTSEGO
REQUEST FOR COUNCIL ACTION
DEPARTMENT: MEETING DATE:
DEPARTMENT: PREPARED BY:
4. Open Forum:(5 Minute Limit)
MEETING DATE
Elaine Beatty
Council of:
2/22/99-6:30PM
ITEM NUMBER: ITEM DESCRIPTION: PREPARED BY:
4.1.SPECIAL PRESENTATION:
A. TED FIELD, Engineer from Bonestroo - Consider Acceptance of
Wastewater Treatment Plant Bids.
B. GARY GROEN - Discussion of 1998 Budget Report
BArZGROUND
4.1.A. As you know, The bids were opened for the wastewater treatment
plant on Tuesday, February 16, 1999. Ted Field will be present to
give you the results and ask for your consideration to accept same.
4.2.B. Attached are two Memos, one dated February 17' 1999 Re: 1998
Preliminary Budget Surplus and one dated February 16, 1999 Re: 1998
Preliminary Final Budget Report from Mike Robertson, City
Administrator. Gary Groen and Mike Robertson will be present to
explain and answer questions.
o ECOM ENDAT I ON
These are for Council consideration and approval.
Thanks,
Elaine
REVENUES
The City projected revenues of $1,246,052 in 1998
and received revenues of $1,334,888, for a surplus
of $88,836. The major contributors to the surplus
were the following;
Building Permits - These were projected at $50,000
and came in at $86,374, a surplus of $36,374.
Though we normally project Building Permits very
conservatively because of their volatility, this is
an amazing feat when you consider that we had a
subdivision moratorium on.
Mining P -s - No amount is normally budgeted for
this item because this is such a volatile category,
so the entire amount of $13,995 was a surplus.
De indent Taxes - This also not budgeted. The
City's tax collection rate is 98%, which is very
good. The $12,225 collected in delinquent taxes
probably represents back taxes owed for more than
one year.
Othert L- Aid Grants - We never budget for
grants, so the entire amount of $10,141 that we
received was a surplus. This includes the
Minnesota Historic Society Grant of $5,000 for the
Otsego Historic Context Study, the State Mighty
Kids Grant of $2,500 for a variety of recreational
activities, and others.
Sem i rmitg - We projected $2,750 in septic
permits and received $9,920 for a surplus of
$7,170. This is primarily due to the County's
"Point of Sale" Ordinance which requires a septic
system to meet code when a property is sold.
Interest - This was projected at $18,000 and came
in at $24,008, a surplus of $6,008.
2
EXPENDITURES
The City projected expenditures of $1,246,052 in
1998 and actually spent $1,161,456, a savings of
$84,596. This savings represents 6.8% of the
budget. Normally, unbudgeted expenditures should
be in the range of 2-5%, but I think this is likely
a one year aberration. Most of this surplus was in
the Street Department ($62,600). Besides the
aforementioned good weather, other contributors to
the surplus were the fact that we budgeted for
three full time public works employees but spent
most of the year with 2-1/2. We also had
substantial unexpended funds in City Council
Contingency ($26,805); City Engineer ($11,533); and
City Planner ($7,977).
I have listed below each department and how it
finished 1998.
MAYOR & COUNCIL
Mayor & Council was budgeted for $72,410 and spent
38,466, for a surplus of $33,944. The major
contributor to the surplus was $26,805 in unspent
Contingency funds. In 1999 Mayor & Council is
budgeted at $66,110, and the Contingency Fund has
been reduced to $24,000.
ADMINISTRATION
Administration was budgeted at $256,465 and spent
$245,686 for a surplus of $10,779. The major
contributor to the surplus was $6,388 in unspent
Office Supplies. In 1999 Administration is
budgeted at $255,525.
FINANCE
Finance was budgeted at $27,295 and spent $26,912
for a surplus of $382. Contracted Services (Gary
Groen's time) was budgeted at $21,200 and spent
$14,821 for a surplus of $6,378. However, the City
purchased new financial software at an unbudgeted
cost of $5,436 which took care of most of that
surplus. In 1999 Finance is budgeted at $23,600.
3
ASSESSING
Assessing was budgeted at $16,760 and spent
$18,779, for a deficit of $2,019. The increase was
due to the increased number of parcels Pete Merges
reviewed. In 1999 Assessing is budgeted at
$17,500.
LEGAL
Legal was budgeted for $40,000 and spent $41,302
for a deficit of $1,302. In 1999 Legal is budgeted
for $50,000.
PLANNING COMMISSION
Planning Commission is budgeted for $3,700 and
spent $3,445 for a surplus of $255. In 1999
Planning Commission is budgeted for $3,700.
PLANNER
The Planner was budgeted for $53,500 and spent
$45,523 for a surplus of $7,977. In 1999 the
Planner is budgeted for $54,000.
EDA
The EDA was budgeted for $6,491 and spent $320 for
a surplus of $6,171. In 1999 the EDA is budgeted
for $6,291.
CITY HALL/PEAVEY HOUSE
City Hall/Peavey House was budgeted for $78,076 and
spent $71,327 for a surplus of $6,749. Contracted
Services had a surplus of $2,822 and Cleaning
Services had a surplus of $2,024. This helped to
make up for a deficit of $2,127 in Repairs &
Maintenance -Equipment. In 1999, City Hall/Peavey
House is budgeted for $75,556.
POLICE
Police was budgeted for $103,806 and spent
$103,806. In 1999 Police is budgeted for $135,310.
BUILDING INSPECTION
Building Inspection costs are a percentage of the
amount of Building Permits. The Building Inspector
was paid $48,009.75 in 1998. The City earned
$86,374 from Building permits, so it came out
$38,364.25 ahead.
0
ENGINEERING
Engineering was budgeted for $52,000 and spent
$40,466 for a surplus of $11,534. In 1999
Engineering is budgeted for $52,000.
STREET LIGHTING
Street Lighting was budgeted at $12,000 and spent
$13,022 for a deficit of $1,022. In 1999 Street
Lighting has been budgeted at $16,000.
STREET MAINTENANCE
Street Maintenance was budgeted at $374,846 and
spent $312,246 for a surplus of $62,600. The major
contributors to the surplus were having 2-1/2 men
rather than the budgeted 3 ($23,000), savings on
Sealcoating ($25,644); Gravel ($25,258);
Crackfilling ($11,196); Salt & Sand ($9,569); and
Gas & Oil ($4,444). These savings helped to cover
overruns in Repairs & Maintenance -Equipment
($24,258); Culverts ($5,623); and Repair &
Maintenance -Supplies ($2,897). In 1999 Street
Maintenance is budgeted at $396,703.
ANIMAL CONTROL
Animal Control was budgeted at $3,500 and spent
$1,964 for a surplus of $1,536. In 1999 Animal
Control is budgeted at $3,500.
RECYCLING
Recycling was budgeted at $32,000 and spent $32,506
for a deficit of $506. In 1999 Recycling has been
budgeted at $32,000.
CLEANUP DAY
Cleanup Day was budgeted at $8,000 and spent
$10,725 for a deficit of $2,725. This is another
area where an overrun is not such a bad thing. In
1999 Cleanup Day has been budgeted at $11,000.
RIVER RIDER
River Rider was not budgeted but we spent $3,195
out of the Mayor & Council Contingency Fund. In
1999 River Rider has been budgeted at $3,195.
5
COMMUNITY RECREATION
Community Recreation was budgeted at $19,003 and
spent $19,003. In 1999 Community Recreation has
been budgeted at $19,900.
PARR MAINTENANCE
Park Maintenance was budgeted at $17,791 and spent
$26,181 for a deficit of $8,390. The deficit was
caused by spending $8,000 on tree cleanup in
Prairie Park. This was paid for by FEMA Funds. In
1999 Park Maintenance is budgeted at $20,891.
HISTORIC PRESERVATION
Historic Preservation was budgeted at $6,091 and
spent $8,474 for a deficit of $2,474. This deficit
was caused by spending to produce the Historic
Context Study. This study was covered by a grant
the City received from the State.
cc: City Staff
C
MEMO
Date: February 17, 1999
To: Mayor & Council
From: City Administrator Mike Robertson
Re: 1998 Preliminary Budget Surplus
Another memo has detailed the preliminary 1998
final budget figures, which have shown a budget
surplus of $174,432 in 1998. As noted, this
surplus is due to a variety of positive factors,
all of which are not likely to reoccur again. The
decision for the City Council is what to do with
the 1998 budget surplus.
You could leave the surplus as fund balance. Fund
balance is that amount of the City's cash left over
at the end of the year. Since the City receives
its second half tax settlement and LGA payments in
mid-December, its fund balance always looks nice.
However, the fund balance has to last for over 6
months because the City will not receive anymore
tax money until next July.
Because of this, City auditors always recommend
that a City have 45-50% of its yearly budget in
fund balance. At the start of 1998, Otsego had a
fund balance of $504,884. Otsego's budget for 1999
is $1,281,422. To have a fund balance of 45-50% of
the 1999 budget, Otsego would need $576,000-
$640,711 in fund balance.
That means that the City Council should add a
minimum of $72,000 from the budget surplus to its
fund balance. That is what City Financial
Consultant Gary Groen and I recommend. That means
that the City has $102,434 in remaining surplus
funds. What follows is a list of possible
recommendations for the use of those funds, along
with the pros and cons of each. This list is not
assumed to include all possibilities.
1998 BUDGET SURPLUS OPTIONS
1. RETURN THE MONEY TO THE TAXPAYERS
Pros - Everyone loves this idea.
Cons - The City is not set up to do this. I
could talk to the County to see if they have a
mechanism for doing this. I would guess that the
costs of doing this would use up a substantial
amount of the surplus.
2. PLACE THE MONEY IN A SEWER & WATER BOND RESERVE
FUND TO MARE BOND PAYMENTS IF THERE IS NOT ENOUGH
DEVELOPMENT
Pros - It would provide additional reserve for
the Sewer/Water bond payments.
Cons - The budget surplus money is tax and
general revenue money. This method would use it to
pay off enterprise fund bonds.
3. PLACE THE MONEY IN THE CAPITAL EQUIPMENT FUND
TO PURCHASE FUTURE CAPITAL EQUIPMENT
Pros - This would provide additional money to
the fund and make it less likely that future
capital equipment purchases would require tax
increases.
Cons - The Capital Equipment Fund is currently
adequate to meet all immediate needs.
4. PLACE THE MONEY IN THE REVOLVING CAPITAL
IMPROVEMENT FUND TO BE USED ON FUTURE CITY
IMPROVEMENT PROJECTS
Pros - This provides additional money for
projects that cannot be assessed 100% and that are
difficult to fund through other sources.
Cons - This money is generated through 1998
taxes and receipts but will probably not be spent
for a few years.
5. USE THE MONEY AS SEED MONEY FOR ECONOMIC
DEVELOPMENT EFFORTS
Pros - This provides money for marketing or a
funding source for incentives to attract industrial
or commercial development.
Cons - The existence of a pot of money can
sometimes cause it to be spent frivolously.
E
6. PLACE THE MONEY IN THE MUNICIPAL BUILDING FUND
TO BE USED FOR FUTURE EXPANSION OF CITY HALL
Prn - This provides additional money for a
future expansion of City Hall (Police Station?)
(Post Office?) etc. that could most likely be
funded only through tax supported bonds.
Cons - This money is generated through 1998
taxes and receipts but will probably not be spent
for quite a few years.
7. USE THE MONEY TO FUND FUTURE SCHEDULED PARK
IMPROVEMENTS
Pros - Everyone loves park improvements.
COLS - City policy has been to fund those
improvements through development fees and grants.
8. PAY DOWN THE LEASE ON CITY HALL
Pros - This frees up money in the future if we
make those payments now.
Cork - The financial benefit to the City is not
realized for several years until the lease is all
paid up.
9. USE THE MONEY AS A REVENUE SOURCE FOR THE 2000
BUDGET AND REDUCE THE PROPERTY TAX RATE
Prns - This provides additional revenue for the
2000 budget allowing less dependence on property
taxes.
.Cons - A budget surplus cannot be guaranteed
every year and if the City becomes dependent upon
it as a revenue source they would have to reduce
spending or raise taxes suddenly if there was not
any surplus.
10. USE THE MONEY TO FUND THE GENERAL OPERATIONS OF
THE CITY
Pres - This provides additional revenue for the
general budget allowing less dependence on property
taxes.
Conn - A budget surplus cannot be guaranteed
every year and if the City becomes dependent upon
it as a revenue source they would have to reduce
spending or raise taxes suddenly if there was not
any surplus.
3
11. PROVIDE ONE TIME BONUSES TO THE FINANCIAL
CONSULTANT AND CITY ADMINISTRATOR
Pros - Since they're great guys they're worth
every penny.
Cons - It's a stupid idea and the rest of the
staff and the citizens would probably want to shoot
you for doing it.
cc: City Staff
C!
CITY OF OTSEGO
REQUEST FOR COUNCIL ACTION
AGENDA SECTION: DEPARTMENT: MEETING DATE:
DEPARTMENT: PREPARED BY: MEETING DATE
r
Dan Licht, Assistant City Planner Elaine Beatty, City Clerk
Council of:
2/22/99-6:30PM
ITEM NUMBER: ITEM DESCRIPTION: PREPARED BY:
6.1. Consider the proposed Zoning Ordinance Amendment; An Ordinance Amending
The Otsego Zoning Ordinance Accessory Building Standards.
BACKGROUND:
6.1.
The Planning Commission held a Public Hearing on February 16, 1999 on
this item. I am attaching draft minutes, a copy of a Memo from Dan
Licht of February 17, 1999 and the proposed ordinance information
for your review. Dan Licht will be present to give you any more
information and answer questions.
RECOMMENDATION!
This is for Council consideration for approval
Thanks,
Elaine
I
CITY OF OTSEGO
Q
CITY OF OTSEGO PLANNING COMMISSION/
CITY COUNCIL. MEETING
MINUTES
TUESDAY, FEBRUARY 16, 1999 - 8PM
1. Chair Carl Swenson will call meeting to order:
Chair Carl Swenson called the meeting to order at 8:03PM
ROLL CALL:
Carl Swenson, Chair, Patrick Moonen, Richard Nichols, Jim Kolles and Gene
Goenner. Bruce Rask, Arleen Nagel and Christian Mbanefo, Alt. were absent from the
P.C.
Larry Fournier, Mayor, Virginia Wendel, Vern Heidner, Suzanne Ackerman
Council Members were present. Mark Beming was absent.
Mike Robertson, City Administrator, Elaine Beatty, City Clerk/Zoning
Administrator and Dan Licht, City Planner from Staff.
2. Consideration of the Planning Commission Minutes of:
A. February 1. 1999 Otsego P.C./CC Meeting
RICHARD NICHOLS MOTIONED TO ADOPT THE MINUTES OF FEBRUARY
1, 1999 OTSEGO PC/CC MEETING MINUTES. JIM KOLLES SECONDED THE
MOTION. MOTION CARRIED UNANIMOUSLY.
3 Hearing to consider the proposed Zoning Ordinance Amendments An
Ordinance Amending the Otsego Zoning Ordinance Accessory Building
Standards,
Elaine Beatty noted that the proper publication, and posting had been
completed.
Dan Licht explained the current proposed ordinance (a copy is attached). Two
new zoning districts have been added on Pg. 4, RC and I-3. Section 4 was stricken out
and reserved for future use.
Chair Swenson noted the formal Public Hearing procedure on the back side of the P.C.
Agenda.
PUBLIC HEARING WAS OPENED TO THE PUBLIC
Keith Knutson He asked if a gazebo and if it is an accessory building. Mr.
6630 Odean Ave NE Licht answered all structures over 150 sq. ft are accessory
buildings. Mr. Knutson questioned if he can go ahead with his
existing CUP? Dan answered he can proceed with the conditions
as approved. Mr. Knutson was curious to know why he was
rejected with his request? Chair Swenson said it would be
appropriate to ask the City Council about that. Mr. Knutson
discussed the buildings he was asked to remove. Could he extend
his time to complete that removal? Mr. Robertson answered, to
change the CUP would be an amendment. Mr. Licht agreed and
said he would need to come before the City Council to consider
an amendment.
CITY OF OTSEGO PLANNING COMMISSION/CITY COUNCIL
MEETING MINUTES TUESDAY, FEBRUARY 16, 1999 - 8PM
-PAGE 2 -
Richard Will - Asked if new regulations are passed would you still need an
9309 Nellmark Administrative Permit to go over the 100 sq. ft? Answer: No.
On his lot he can build up to 2,000sq. ft. of detached buildings or
smaller buildings. Gene Goenner told Mr. Will to keep in mind
he would still need to obtain a building permit.
Dale Beaudry Mr. Beaudry has 5 acres of land in the Rural Service Area. He
7675 MacIver wants a 1800 sq. ft pole building. Will that be allowed? Mr.
Licht explained that he could build the size he wanted but would
have to build a stick -built structure instead building instead of a
pole building. Pole buildings are only allowed on lots of over five
acres in size. Mr. Beaudry feels it should read " 5 acres or more".
Chair Swenson noted that we have had a lot of discussion on this
issue.
Discussion went back to the P.C.
Patrick Moonen - Questioned the change to eliminate 1,000 sq. ft. accessory
building space on one acre lots. What was the consideration to limit the larger
structures? Mr. Licht explained we looked at the size of items typically stored in a
garage. The only change is to eleminate exceptions through the CUP process. One acre
lots are allowed a total of 2,000 sq. ft. in accessory building space including one detached
garage. Mike Robertson added that the Council was trying to deal with the fact that none
of the CUP's were being turned down and people were spending $500 to $800 on the
CUP application.
Hearing was re -opened to the public.
Keith Knutson Agreed with Dale Beaudry that the size required should be
stated as "equal to or greater than 5 acres in size". A five
acre lot is quite a bit to maintain.
Mr. Will Agreed with Dale Beaudry, He also felt that on a one acre
lot one-half acre is taken up with septic. If you stick
another 1,000 sq. ft on it, it will be cramped.
Dale Beaudry It is my understanding that if I had 5.1 acres I could build
a big shed, but I am limited because I only have 5 acres.
Chair Swenson noted that the problem is there has to be a
line drawn somewhere. Other people around
me have 5 acre lots with big pole buildings and I have
petitions from my neighbors that agree
CITY OF OTSEGO PLANNING COMMISSION/CITY COUNCIL
MEETING MINUTES TUESDAY, FEBRUARY 16, 1999 - 8PM
-PAGE 3 -
with me building a pole building. He felt that some stick
built buildings he sees are in worse shape than the pole
buildings. Chair Swenson - Noted that in general we are
talking about a residential area and pole buildings do not
look good in a residential area. Mr. Beaudry noted that
he lives on MacIver Ave. Dan Licht noted he is a
residential use.
HEARING WAS CLOSED BY CHAIR SWENSON
Discussion brought back to the P.C.
Gene Goenner - All the people who spoke want it to read 5 acres and greater. Do
we want to revisit it? I will be honest. I voted for over 5 acres. Richard Nichols - We
went round and round on this for weeks at a time. I understand Dale's concern. I am
personally not in favor of a change. We have to look at what's best for the City.
Dan Licht - 10 acres or greater was the original size and we lowered it to pick up
the larger than 5 acre hobby farms.
RICHARD NICHOLS MOTIONED TO RECOMMEND APPROVAL OF THE
AMENDMENT TO THE ZONING ORDINANCE FOR ACCESSORY BUILDING
STANDARDS AS WRITTEN. GENE GOENNER SECONDED THE MOTION.
MOTION CARRIED WITH PAT MOONEN VOTING AGAINST.
This item will be on the Council Agenda of February 22, 1999 at 6:30PM.
4. Any other P.C. Business
Chair Swenson noted that another problem we have is the minimum lot size in the
Rural Service Area. Dan Licht explained that the proposed one acre minimum lot size in
the Rural Service Area may be a problem. Possibly 2-1/2 acres to 5 acres is appropriate.
On the issue of lot sizes smaller than the proposed minimum lot size, we can grandfather
the one acre minimum lots that are established now.
Gene Goenner. The main concern is the sewer system. Why not have them show
ample sewer sites (2 or 3 sites). 2-1/2 acres is a lot to maintain. Chair Swenson agreed
with them on having multiple septic sites. Mr. Goenner asked if we will require
clustered 4 per 40's? Mr. Licht - Yes clustered, unless 10 acre divisions. A-1 is the Ag.
Preservation District. A-2 more rural 4 per 40, four 10 -acre lots or clustered lots. More
discussion. Chair Swenson noted that they would need road frontage on existing roads.
Mike Robertson asked if the 4 per 40 are administrative splits or do they take
P.C./ CC action? More discussion of 4 per 40 being administrative or application. Gene
Goenner noted that if we are not notified of a neighbors 4 per 40 splits, someone could
put their house on a 12" drain tile. He wanted to see the notice go out to neighbors.
Richard Nichols - That would be true regardless of acreage. Elaine - Noted
CITY OF OTSEGO PLANNING COMMISSION/CITY COUNCIL
MEETING MINUTES TUESDAY, FEBRUARY 16, 1999 - 8PM
-PAGE 4 -
that for 4 per 40 it would have to be rezoned from A-1 to A-2. Dan Licht will prepare a
matrix regarding this issue. P.C. did not want this on for hearing. They want it on for an
Agenda item to discuss lot size.
Mike Robertson gave the P.C. the good news that we received our sewer
discharge permit and the wastewater treatment plant bids came in $271,000 below the
engineers estimate. The low bidder is a very reputable company. The bids will be
brought to the Council on the 22nd of February.
5. Adjourn by 10PM
RICHARD NICHOLS MOTIONED TO ADJOURN THE PLANNING COMMISSION
MEETING. PATRICK MOONEN SECONDED THE MOTION. MOTION CARRIED
UNANIMOUSLY. MEETING ADJOURNED AT 8:55PM.
CITY OF OTSEGO:
ARLEEN NAGEL, SECRETARY
MINUTES BY: ELAINE BEATTY, CITY CLERK/RECORDING SECRETARY
EB
FU -E: 99-PCNIN.WPs
FEB -17-1999 08:11 NAC 612 595 9837 P.02i02
N
MEMORANDUM
TO_
FROM:
DATE:
RE:
FILE NO.:
Otsego Mayor and City Council
Daniel Licht
17 February 1999
Otsego - Zoning Ordinance Update. Accessory Buildings
176.08 - 98.07
J LTANTS
RESEARCH
The Planning Commission considered the proposed amendment to the accessory building
provisions of the Zoning Ordinance at a public hearing on February 16, 1999. The
proposed ordinance was in the format last discussed at the Planning Commission / City
Council workshop on February 1, 1999.
Three residents spoke as part of the public hearing regarding allowing pole buildings only
on lots larger than 5 acres. The three residents believed that the regulation should be
established allowing pole buildings on parcels "5 acres in size or larger". The Planning
Commission and City Council had discussed this issue at length during the workshop
sessions. The intent of the regulation as written was to allow pole buildings on true hobby
farms or large rural parcels but discourage them from subdivisions of clustered suburban
sized lots. The Planning Commission did not suggest changing the requirement.
The Planning Commission voted to recommend approval of the proposed ordinance
amendment by a vote of 4-1. The amendment will be considered by the City Council at
their meeting on February 22, 1999.
If there are any further questions regarding this matter, please do not hesitate to call me.
PC. Mike Robertson
Elaine Beatty
Jerry Olsen
Andy MacArthur
5775 WAYZATA BOULEVARD. SUITE 555 ST. LOUIS PARK, MINNESOTA 5541 6
PHONE 61 2-595-9636 FAX 612-595-9837 E-MAIL NAC WINTERNET.COM
TOTAL P.02
N W^ f�% NORTHWEST ASSOCIATED CONSULTANTS
INC COMMUNITY PLANNING - DESIGN - MARKET RESEARCH
MEMORANDUM
TO: Otsego Mayor and City Council
Otsego Planning Commission
FROM: Daniel Licht
DATE: 2 February 1999
RE: Otsego - Zoning Ordinance Update: Accessory Buildings
FILE NO.: 176.08 - 98.07
The attached ordinance for accessory building regulations reflects changes from the
Planning Commission/City Council meeting on February 1, 1999. The only change was
to reduce the area requirements for construction of a pole building in the rural service area
from 10 acres or greater to greater than 5 acres.
A public hearing to consider this amendment has been scheduled for the Planning
Commission meeting on Tuesday, February 16, 1999 at 8:00 PM.
PC. Mike Robertson
Elaine Beatty
Jerry Olsen
Andy MacArthur
5775 WAYZATA BOULEVARD, SUITE 555 ST. LOUIS PARK, MINNESOTA 554 1 6
PHONE 61 2-595-9636 FAX 612-595-9837 E-MAIL NAC@WINTERNET.COM
ACCESSORY BUILDING REGULATION MATRIX
(02/02/98)
Existing Regulations
New Regulations
Urban Service Area
Rural Service Area
(All Districts)
Sewer
No Sewer
Districts
Districts
(R-4R5/R-6/R-7)
(A-1/A-2JR-C/
R -1/R -2/R-3
Exemptions
Farm and hobby farm uses
Farms and uses in the R -MH District to be regulated in the R -
MH District section.
Attached
1,000 sq. ft. permitted,
Min 480 sq. ft /
Min 480 sq. ft /
Min 480 sq. ft /
Accessory
Over 1,000 sq. ft. by CUP
Max 1,000 sq. ft.
Max 1,000 sq. ft.
Max 1,000 sq. ft.
Structures
Detached
1,000 sq. ft. permitted,
Max 150 sq. ft.
1,000 sq. ft. +
1,000 sq. ft. + 500 sq. ft.
Accessory
1,000 sq. ft. to 1,500 sq. ft. by
w/ attached
500 sq. ft. for
for each additional
Structures
administrative permit,
garage or 1,150
each additional
acre > 1 acre up to
Over 1,500 sq. ft. by CUP
w/out attached
acre > 1 acre up
3,000 sq. ft. Maximum
garage
to 2,000 sq. ft.
size of a building = 1,500
Maximum size of
sq. ft.
a building =
1,500 sq. ft.
Total
Maximum 2,000 sq. ft.
Max 1,150 sq. ft.
2,000 sq. ft. to
2,000 sq. ft. to 4,000 sq.
Combined
Over 2,000 sq. ft. by CUP
3,000 sq. ft.
ft. based on lot size
Accessory
based on lot size
Area
Number of
No more than one detached,
No more than
No more than
No more than two
structures
more than one detached by
one detached
two detached
detached structures
CUP
structure per
structures per
per dwelling.
dwelling.
dwelling.
Relation to
Except in the case of
No regulation
Total floor area
Total floor area of all
Size of
manufactured homes, no
of all accessory
accessory structures
Principal
accessory building may
structures shall
shall not exceed 200
Structure
exceed the size of the
not exceed 200
percent of the gross floor
principal structure, except by
percent of the
area of the principal
CUP
gross floor area
structure or the
of the principal
maximum combined
structure or the
area allowed based
maximum
upon lot size, whichever
combined area
is least for parcels < 5
allowed based
acres. No limit for
upon lot size,
parcels > 5 acres.
whichever is
least.
Setbacks
10 ft from side/rear lot line
10 ft from side/rear lot line < 1,000 sq. ft.
Principal building setback > 1,000 sq. ft.
Pole
Allowed by CUP in A-1 and
Not allowed
Allowed in A-1 and A-2
Buildings
A-2 District
District on parcels > 5
acres.
CITY OF OTSEGO
WRIGHT COUNTY, MINNESOTA
ORDINANCE #98 -
AN ORDINANCE AMENDING THE RESIDENTIAL ACCESSORY STRUCTURE
PROVISIONS OF THE OTSEGO ZONING ORDINANCE TO RESPOND TO DIRECTIVES
OUTLINED IN THE COMPREHENSIVE PLAN UPDATE.
THE CITY COUNCIL OF THE CITY OF OTSEGO DOES HEREBY ORDAIN:
Section 1. Section 20-16-4 of the Zoning Ordinance is hereby
amended to read as follows:
20-16-4: ACCESSORY BUILDINGS, USES, AND EQUIPMENT:
A. Exceptions:
1. Farm operations are exempt from the requirements of
this subsection and are regulated by Section 26 of
this Chapter.
2. R -MH District: Accessory buildings, uses, and
equipment shall be as regulated within the district
provisions of Section 60 of this Chapter.
B. Detached Single Family and Two Family Uses:
1. No accessory use, building, structure or equipment
shall be allowed within a required front yard.
With the exception of a garage, no accessory
building, structure, use or equipment may be placed
within a front yard.
2. No accessory building, structure, and/or detached
garage for a single family dwelling shall occupy
more than ten (10) percent of the area of the
required rear yard in the A-1, A-2, R -C, R-1, R-2
and R-3 Zoning Districts or not more than twenty-
five (25) percent of the area of the required rear
yard in the R-4, R-5, R-6, and R-7 Zoning
Districts.
3. Accessory buildings with an area of one thousand
(1,000) square feet or less may encroach into the
principal building required side and rear yard
setbacks within the rear yard of a lot, except,
however, that no such encroachment may occur on
1
required easement, or in a required side yard
setback abutting a street in the case of a corner
lot and that no such encroachment shall be closer
than ten (10) feet to any lot line, occur upon a
required easement, or in a required side yard.
4. Attached accessory garages or structures within
both the Urban and Rural Service areas, as defined
by the Comprehensive Plan:
a. The total floor area of an attached accessory
garage shall not be less than four hundred
eighty (480) square feet and shall not be
greater than the gross floor area of the
principal structure or one thousand (1,000)
square feet, whichever is least.
5. Detached accessory buildings and structures within
the Urban Service Area, as defined by the
Comprehensive Plan:
a. Within the A-1, A-2, R -C, R-1, R-2, and R-3
Zoning Districts:
(1) The total floor area of detached
accessory buildings shall not exceed one
thousand (1,000) square feet, plus five
hundred (500) square feet of additional
detached accessory building area for each
one (1) acre of lot area greater than one
(1) acre. But in no case shall the
floor area of an individual detached
accessory building exceed one thousand
five hundred (1,500) square feet or the
total detached accessory building area
exceed two thousand (2,000) square feet.
(2) The total floor area of all accessory
structures shall not exceed two
hundred(200)percent of the gross floor
area of the principal structure or shall
not exceed the maximum combined accessory
area allowed based upon lot size, as
outlined in this section, whichever is
least.
2
(3) No building permit shall be issued for
more than two (2) detached private
garages or accessory structure -a for each
detached single or two-family dwelling.
b. Within the R-4, R-5, R-6, and R-7 Zoning
Districts:
(1) No accessory detached building shall
occupy more than one hundred fifty (150)
square feet when accompanied by an
attached garage on the same lot nor shall
the combined total floor area of an
accessory detached building and/or
attached garage exceed one thousand one
hundred fifty (1,150) square feet.
(2) No building permit shall be issued for
more than one (1) detached private garage
or accessory structure for each detached
single or two-family dwelling.
6. Detached accessory buildings within the Rural
Service Area as defined by the Comprehensive Plan:
a. The total floor area of all detached accessory
structures shall not exceed one thousand
(1,000) square feet, plus five hundred (500)
square feet of additional detached accessory
building area for each one (1) acre of lot
area greater than one (1) acre. But in no
case shall the floor area of an individual
detached accessory building exceed one
thousand five hundred (1,500) square feet or
the total detached accessory area exceed three
thousand (3,000) square feet.
b. No building permit shall be issued for more
than two (2) detached private garages or
accessory structures for each single family
dwelling.
C. For parcels with an area of five (5) acres or
less, the total floor area of all accessory
structures shall not exceed two
hundred(200)percent of the gross floor area of
the principal structure or shall not exceed
the maximum combined accessory area allowed
3
based upon lot size, as outlined in this
section, whichever is least.
Section 2. Section 20-16-4.G (Building Type and Standards) of
the Zoning Ordinance is hereby amended to read as follows:
2. Pole buildings as defined by this Chapter are allowed as
a permitted accessory structure within the A-1 and A-2
District provided that:
a. The lot or parcel lies within the Rural Service
Area, as defined by the Comprehensive Plan.
b. The area of the lot or parcel on which the building
is to be constructed is greater than five (5)
acres.
Section 3. Section 20-16-4.F (accessory building height) of
the Zoning Ordinance is hereby amended to read as follows:
F. Except as expressly allowed by conditional use permit,
accessory buildings shall comply with the following
height limitations:
1 Zoning
District Maximum Heiaht
A-1
District
limit but
not higher
than the
principal
building
A-2
District
limit but
not higher
than the
principal
building
R -C
16 feet
R-1
16 feet
R-2
16 feet
R-3
16 feet
R-4
16 feet
R-5
16 feet
R-6
16 feet
R-7
16 feet
R -B
16 feet
INS
District
limit but
not higher
than the
principal
building
B-1
16 feet
B-2
16 feet
B-3
16 feet
B -W
20 feet
4
B -C District limit but not higher
than the principal building
I-1 District limit but not higher
than the principal building
I-2 District limit but not higher
than the principal building
I-3 District limit but not higher
than the principal building
Section 4. Section 20-16-4.H (Administrative Permits) of the
Zoning Ordinance is hereby amended to read as follows:
H. Reserved.
Section 5. Section 20-60-5.C.6 (R -MH District - Building
requirements) of the Zoning Ordinance is hereby amended to read as
follows
b. Accessory Buildings:
(1) Accessory buildings including garages
shall be limited to one (1) per mobile
home lot.
(2) Maximum allowable floor area shall not
exceed six and one-half (6.5) percent of
the lot size.
(3) Maximum Building Height: Sixteen (16)
feet.
(4) Location: The manufactured home park
site plan shall designate the locations
proposed for the development of garages
and/or accessory building on each
manufactured home lot. Said accessory
buildings shall comply with the following
setback requirements:
(a) No accessory building shall be
located in the front yard.
(b) An accessory building may be located
5
in side or rear yards.
(c ) All accessory buildings shall be set
back from all adjoining lots a
minimum of five (5) feet. Garages
may be allowed with a zero lot line
setback and a shared driveway when
built as a double garage and shared
by adjacent lots.
(d) Accessory buildings shall not be
located within any utility
easements.
(e) On lots having a lot width of fifty-
five (55) feet or greater, an
accessory building shall be located
at least ten (10) feet from any
other building or structure on the
same lot. On lots having a fifty
(50) foot lot width, accessory
buildings shall be located at least
nine (8) feet from any building or
structure on the same lot.
Section 6. This Ordinance shall be in full force and effect
upon its passage and publication.
PASSED this day of
ATTEST:
s•:
CITY OF OTSEGO
RY-
Larry Fournier, Mayor
BY:
Elaine Beatty,Zoning Administrator/City Clerk
CITY OF OTSEGO
REQUEST FOR COUNCIL ACTION
AGENDA SECTION: DEPARTMENT: MEETING DATE:
DEPARTMENT: PREPARED BY: MEETING DATE
7. Larry Koshak, City Engineer Elaine Beatty
Council of:
2/22/99-
6:30PM
ITEM NUMBER: ITEM DESCRIPTION: PREPARED BY:
7.1. Action needed based on Workshop on Bituminous Street Overlay Study
for year 1999 - 2002 /Set Hearing Date
7.2. Update on State Aid Funds for 1999
7.3. Accept Plan and Spec for Trunk Sewer & Water Project, Authorize
Going Out For Bids
7.4. Any other Engineering Business
BACKGROUND:
7.1.through 7.3. Larry Koshak will be present to explain these items
and answer any questions. Attached is the information from Larry
Koshak.
RECOMMENDATION:
This is for Council information, update and any decisions.
T} s,
0 �- �
Elaine
Hakanson
Anderson
1-111 Assoc., Inc.
":moil & Municipal Engineering
d Surveying
CITY OF OTSEGO
CITY ENGINEER
COUNCIL AGENDA ITEMS
COUNCIL MEETING
2/22199
ITEM 7.1 BITUMINOUS STREET OVERLAY PROJECT
3601 Thurston Avenue
Suite 101
Anoka, Minnesota 55303
612/427.5860
612/427-0520 Fax
A. Review bonding capacity and limits for this project. Mike has
discussed this issue with the bonding company, and will relate his
findings.
B. Find enclosed a tabulation of potential maintenance costs prepared by
Ron Wagner, P.E., that may need to be spent to maintain the entire
group of streets in the study for a period of 5 years.
This estimated cost assumes continued failure of sections of street in
Hall's Addition and 80th Street that would require dig outs and patching
with asphalt. The amounts shown are probably a worst case scenario.
C. Consider setting a public hearing for the overlay project(s).
ITEM 7.2 STATE AID FUNDS OF 1999
The unencumbered funds in the State Aid account as of 12/31/98 were
$993,913.
The allotment for 1999 is $306,366, of which $76,592 is maintenance
funds and the remaining $229,774 is placed in the construction fund.
The total of construction funding available in 1999 is $1,223,687. The
Odean Avenue project could use up to $730,000 of the State Aid
funds in 1999.
Since no new streets were added in the City for 1998, the annual
Certification of Mileage does not allow for placing additional mileage on
the system. That will change with development. The City did lose
funding for 1998-1999. That is largely from the $993,913 being
deducted for the Needs Apportionment funding calculation. By not
spending the construction fund allotted, the City is penalized.
City Engineer Council Agenda Items
PIge 1 of 2
February 17. 1999
(; 1:i(h ii:Ib'VPrIitildoc
ITEM 7.3 TRUNK SEWER AND WATER PROJECT, COP #98.04
We will have a set of plans available for review at the City Hall on
Monday 2/22/99. The specifications are not ready for this meeting, but
will be for the next meeting on March 8, 1999. At that meeting, the
Council may consider approval of the plans & specifications and order
bids. A resolution for this process is attached to the item. Also
included is John Harwood's memo on the matter.
ITEM 7.4 ANY OTHER ENGINEERING BUSINESS
City Engineer Council Agenda Items Hakanson
Page 2 of 2 � Anderson
t=ehruary 17, 1999 Assoc., Inc.
C harcliVPnnmiIAOTSFG019iJllof901aiienclaZo-99 doc
7 Hakanson
Anderson
Assoc., Inc.
it & Municipal Engineering
d Surveying
February 17, 1999
Mr. Mike Robertson, Administrator
City of Otsego
8899 Nashua Avenue N.E.
Otsego, MN 55330
RE: Otsego Overlays
Dear Mr. Robertson,
ITEM 7.1 B
3601 Thurston Avenue
Suite 101
Anoka, Minnesota 55303
612/427-5860
612/427-0520 Fax
As requested at the February 8, 1999 City Council meeting, we have determined an
estimated cost of maintenance over the next 5 years for roadways in Otsego that are
proposed for an overlay. The total estimated cost is $264,761.
Roadways within subdivisions were estimated with the following maintenance work to
be completed in the next 5 years:
1999
Patching & Seal Coat
2000
None
2001
Crack Filling
2002
None
2003
Crack Filling
Roadways not within subdivisions were felt to be beyond sealcoat or crack filling type
maintenance. Instead, $5,000 worth of patching per year for those roadways was
estimated.
A breakdown of maintenance costs are shown on the following page
timetable was used for maintenance cost because if the roadways
maintenance would be required around 2004 or so.
t q„r
If you have any,questions or comments, you can contact us at 427-5860.
Sincerely,
HAKANSON ANDERSON ASSOCIATES, INC.
Ronald J. y agner�
/clk
C:\Share\WPmun MOTS EGO\336\ot336mr2.doc
s. A five-year
were overlaid,
Estimated Savings in Maintenance Costs for Roadways Proposed to be Overlayed
PROJECT LOCATION 1999 COST
HALLS 1ST, 2ND,& 3RD ADDITIONS
HALLS 1ST, 2ND,& 3RD ADDITIONS
DEER FIELD ACRES & HIDDEN VALLEY
DEER FIELD ACRES & HIDDEN VALLEY
WALESCH ESTATES & WALESCH ESTATES 2nd ADDITION
WALESCH ESTATES & WALESCH ESTATES 2nd ADDITION
VASSEUR'S OAK GROVE ESTATES 1ST & 2ND ADDITIONS
VASSEUR'S OAK GROVE ESTATES IST & 2ND ADDITIONS
VASSEUR'S OAK GROVE ESTATES 3RD & 4TH ADDITIONS
VASSEUR'S OAK GROVE ESTATES 3RD & 4TH ADDITIONS
OTSEGO ACRES 1ST & 2ND ADDITIONS
OTSEGO ACRES IST & 2ND ADDITIONS
GREAT RIVER ACRES 1ST,2ND & 3RD ADDITIONS
GREAT RIVER ACRES 1ST,2ND & 3RD ADDITIONS
"COUNTRY ROADS" *
1999 MAINTENANCE SUBTOTAL
* NOTE: "COUNTRY ROADS" CONSIST OF:
MASON AVE NE (CSAR 39 TO 83RD ST NE)*
83 RD ST. (MASON AVE. NE TO MARLOWE AVE. NE)*
MARLOWE AVE NE (83RD ST. NE TO 80TH ST. NE)*
80TH ST. (Mac IVER AVE. NE TO MARLOWE AVE. NE*
80 TH ST. (Mac IVER AVE. NE TO CSAH 19)*
SEALCOAT $18,444
PATCHING $82,728
SEALCOAT $5,352
PATCHING $1,788
SEALCOAT $19,021
PATCHING $18,407
SEALCOAT $13,517
PATCHING $3,754
SEALCOAT $8,138
PATCHING $1,788
SEALCOAT $9,622
PATCHING $1,341
SEALCOAT $11,684
PATCHING $4,586
PATCHING $5,000
$205,168
PROJECT LOCATION 2000 COST
"COUNTRY ROADS"
Page 2
PATCHING $5,000
$5,000
Estimated Savings in Maintenance Costs for Roadways Proposed to be Overlayed
PROJECT LOCATION 2001 COST
HALLS 1ST, 2ND,& 3RD ADDITIONS CRACKFILLING $4,257
DEER FIELD ACRES & HIDDEN VALLEY CRACKFILLING $1,235
WALESCH ESTATES & WALESCH ESTATES 2nd ADDITION CRACKFILLING $4,390
VASSEUR'S OAK GROVE ESTATES IST & 2ND ADDITIONS CRACKFILLING $3,120
VASSEUR'S OAK GROVE ESTATES 3RD & 4TH ADDITIONS CRACKFILLING $1,878
OTSEGO ACRES 1ST & 2ND ADDITIONS CRACKFILLING $2,221
GREAT RIVER ACRES 1ST,2ND & 3RD ADDITIONS CRACKFILLING $2,697
"COUNTRY ROADS" * PATCHING $5,000
2001 MAINTENANCE SUBTOTAL $24,796
PROJECT LOCATION 2002 COST
"COUNTRY ROADS" " PATCHING $5,000
2002 MAINTENANCE SUBTOTAL
Page 3
$5,000
Estimated Savings in Maintenance Costs for Roadways Proposed to be Overlayed
PROJECT LOCATION 2003 COST
HALLS 1ST, 2ND,& 3RD ADDITIONS CRACKFILLING $4,257
DEER FIELD ACRES & HIDDEN VALLEY CRACKFILLING $1,235
WALESCH ESTATES & WALESCH ESTATES 2nd ADDITION CRACKFILLING $4,390
VASSEUR'S OAK GROVE ESTATES 1ST & 2ND ADDITIONS CRACKFILLING $3,120
VASSEUR'S OAK GROVE ESTATES 3RD & 4TH ADDITIONS CRACKFILLING $1,878
OTSEGO ACRES 1ST & 2ND ADDITIONS CRACKFILLING $2,221
GREAT RIVER ACRES 1ST,2ND & 3RD ADDITIONS CRACKFILLING $2,697
"COUNTRY ROADS" " PATCHING $5,000
2003 MAINTENANCE SUBTOTAL $24,796
TOTAL ESTIMATED MAINTENANCE COST $264,761
Page 4
ITEM 7.2
Municipalities
Unencumbered
Amount
Available
12-31-97
Unencumbered
Amount
Available
12-31-98
Difference
Between
1997 and
1998
Percentage of
Total Amount
in 1998
Account
Ratio to
City's 1998
Construction
Allotment
North Mankato
$0
$0
$0
0.0000
0.0000
North St. Paul
65,625
0
(65,625)
0.0000
0.0000
)rthfield
711,858
803,785
91,927
1.7923
2.6644
mak Grove
0
0
0
0.0000
0.0000
Oakdale
0
0
0
0.0000
0.0000
Orono
686,185
513,502
(172,683)
1.1450
2.0155
Otsego
762,911
993,913
231,002
2.2163
4.4918
Owatonna
0
0
0
0.0000
0.0000
Plymouth
0
0
0
0.0000
0.0000
Prior Lake
684,598
313,295
(371,303)
0.6986
0.9540
Ramsey
685,006
1,008,450
323,444
2.2487
2.2389
Red Wing
0
0
0
0.0000
0.0000
Redwood Falls
75,740
208,630
132,890
0.4652
1.5958
Richfield
2,542,856
2,287,265
(255,591)
5.1003
3.1798
Robbinsdale
0
166,389
166,389
0.3710
0.4963
Rochester
714,722
969,847
255,125
2.1626
0.5868
Rosemount
400,471
89,713
(310,758)
0.2000
0.1948
Roseville
1,056,551
0
(1,056,551)
0.0000
0.0000
St. Anthony
502,914
134,314
(368,600)
0.2995
0.8755
St. Cloud
0
0
0
0.0000
0.0000
St. Louis Park
0
0
0
0.0000
0.0000
St. Michael
5,996
199,414
193,418
0.4447
0.8885
-` Paul
0
0
0
0.0000
0.0000
Paul Park
269,430
395,431
126,001
0.8818
0.0000
6t. Peter
696,809
221,712
(475,097)
0.4944
0.7493
Sartell
0
0
0
0.0000
0.0000
Sauk Rapids
0
0
0
0.0000
0.0000
Savage
0
325,425
325,425
0.7257
0.6365
Shakopee
106,202
278,776
172,574
0.6216
0.7778
Shoreview
95,910
0
(95,910)
0.0000
0.0000
Shorewood
1,196,942
1,356,588
159,646
3.0250
7.8981
South St. Paul
1,849,935
1,949,517
99,582
4.3472
5.6694
Spring Lake Park
0
0
0
0.0000
0.0000
Stewartville
0
106,649
106,649
0.2378
0.0000
Stillwater
415,634
505,458
89,824
1.1271
1.7300
Thief River Falls
394,331
447,938
53,607
0.9988
1.2665
Vadnais Heights
0
0
0
0.0000
0.0000
Virginia
0
0
0
0.0000
0.0000
Waite Park
0
0
0
0.0000
0.0000
Waseca
50,623
98,509
47,886
0.2197
0.4933
West St. Paul
0
79,082
79,082
0.1763
0.2212
White Bear Lake
0
0
0
0.0000
0.0000
Willmar
804,543
1,233,415
428,872
2.7504
2.8327
,lona
364,330
655,581
291,251
1.4619
1.2343
jodbury
0
0
0
0.0000
0.0000
Worthin ton
971,073
668,511
302.562
1.4907
2.4717
TOTAL
$49,110,546
$44,845,521
54,265,025
100.0000
0.6413
-54-
MUNICIPALITY
North Mankato
North St. Paul
Northfield
Oak Grove
Oakdale
TOTAL
APPORTION-
MENT
$416,983
337,786
448,628
281,634
648,571
TRUNK
HIGHWAY
TURNBACK
MAINTENANCE
ALLOWANCE
AMOUN '
BOND
INTEREST
APPLIED TO
MAINTENANCE
$96.678
28,217
GENERAL
MAINTENANCE
ALLOCATION
$31,274
84,447
112,157
23,835
133,926
TOTAL
MAINTENANCE
ALLOCATION
$127,952 #
84,447
112,157
23,835
162,143 ####
CONSTRUCTION
ALLOCATION
$289,031
253,339
336,471
257,799
486,428
Orono
355,988
88,997
88,997 *
266,991
Otsego
306,366
76,592
76,592 *
229,774
Owatonna
638,545
26,265
26,265
612,280
Plymouth
1,706,058
65,475
65,475
1,640,583
Prior Lake
442,053
110,513
110,513 *
331,540
Ramsey
614,790
85,000
85,000 #
529,790
Red Wing
672,345
235,321
235,321 **
437,024
Redwood Falls
209,926
52,482
52,482 *
157,444
Richfield
958,768
239,692
239,692 *
719,076
Robbinsdale
348,895
15,090
15,090
333,805
Rochester
2,352,388
250,000
250,000 #
2,102,388
Rosemount
545,332
22,090 27,900
49,990 ###
495,342
Roseville ****
1,026,955
256,739
256,739 *
770,216
St. Anthony
235,502
58,876
58,876 *
176,626
St. Cloud
1,794,713 $8,784
28,986 71,925
109,695 ###
1,685,018
St. Louis Park
1,268,123
443,843
443,843 **
824,280
St Michael
314,377
78,594
78,594 *
235,783
St. Paul
8,495,366
2,633,563
2,633,563 ***
5,861,803
St. Paul Park
168,390
42,098
42,098 *
126,292
St. Peter
367,203
17,550
17,550
349,653
Sartell
246,891
7,440
7,440
239,451
Sauk Rapids
279,710
15,255
15,255
264,455
Savage
597,304
78,825 14,310
93,135 ###
504,169
Shakopee
483,188
120,797
120,797 *
362,391
Shoreview
588,426
20,745
20,745
567,681
ITEM 7.3
CITY OF OTSEGO
RESOLUTION
RESOLUTION APPROVING PLANS & SPECIFICATIONS
AND
ORDERING ADVERTISEMENT OF BIDS
WHEREAS, pursuant to a resolution passed by the Council, Hakanson
Anderson Associates, Inc., the City engineer, has prepared plans and specifications
for Phase I Trunk Sanitary Sewer and Watermain Project, and has presented such
plans and specifications to the Council for approval;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF OTSEGO,
MINNESOTA:
1. Such plans and specifications, a copy of which is attached hereto and
made a part hereof, are hereby approved.
2. The City Clerk shall prepare and cause to be inserted in the official
paper and in the Construction Bulletin an advertisement for bids upon the making of
such improvement under such approved plans and specifications. The
advertisement shall specify the work to be done and shall state that bids will be
opened at 11:00 a.m., on April 6, 1999, in the council chambers of the city hall.
No bids will be considered unless sealed and filed with the clerk and accompanied
by a cash deposit, cashier's check, bid bond or certified check payable to the City
for five (5) percent of the amount of such bid.
Mayor
Clerk
C:\Share\WPmuni\AOTSEGO\612\ot612res2.doc
Hakanson
Anderson
Assoc., Inc.
`wil & Municipal Engineering
I Surveying
3601 Thurston Avenue
Suite 101
Anoka, Minnesota 55303
612/427-5860
612/427-0520 Fax
MEMORANDUM ITEM 7.3
TO: Larry Koshak, Otsego City Engineer
FROM: John A. Harwood, PE
DATE: February 17, 1999
RE: Phase I Trunk Sewer & Watermain Project
Plans & Specs
Enclosed are plans for the Phase I Trunk Sewer & Water Project. These are substantially the
same as the plans dated 5/26/98, which were previously reviewed by the City council. The
major revisions are related to the final location, of the water tower and Pumphouse No. 1. We
have also deleted three jacked sewer & water utility line crossings of CR 42. The enclosed
plans incorporate the details for sewer and water appurtenances as have been recommended
for City of Otsego adoption. The project specifications are not enclosed. They follow MnDOT
and City Engineer Association of Minnesota (CEAM) Standards. The specifications will be
completed with a final quantity takeoff, cost estimate and schedule of structures and will be
prepared prior to bidding.
The schedule for start of construction is dependent on acquisition of right-of-way or easement.
We expect that many if not most easements will be acquired through negotiation but that some
property access will not be available until after the 90 day Eminent Domain period, which will
and in mid-May.
The recommended schedule is as follows:
Council Receipt of Plans Feb 22, 1999
Final Council Approval March 8, 1999
Advertisement Period — 21 days
Bid Opening Date Tuesday April 6, 1999
Council Consideration of Bids and Award April 12, 1999
Completion of Contract Execution and Notice to Proceed May 1, 1999
Full Availability of all Right -of -Way & Easement May 20, 1999
Substantial Completion (120 days) Sept. 17, 1999
Full Completion November 1, 1999
Final Punch List & Warranty Work Spring 2000
The sewer and water system can be ready for service on or about September 17, 1999. This is
before the scheduled completion of the treatment facility. The city could consider allowing
sewer hookups early by providing "honey wagon" service from the Quaday at CR 42 sewer lift
station to disposal. The cost of this trucked disposal needs to be evaluated.
I strongly recommend that the City reconsider the �rovision of sewer service to the west side of
County Road 42 at 85th, at future 87th and at 88tF. These jackings of sewer and water have
current estimated costs near $50,000 each. In the future, due to difficulties of re -constructing
facilities, the crossing costs will increase by about 50%. This future expenditure will likely be a
100% trunk cost, to be funded solely by connection income. If sewer and water service west of
CR 42 is likely to be needed within 10 years or so, the crossings should be made now.
CAS hare=Pmuni\AOTSEGO\612\ot6121k 1.doc
CITY OF OTSEGO
REQUEST FOR COUNCIL ACTION
AGENDA SECTION: DEPARTMENT: MEETING DATE:
DEPARTMENT: PREPARED BY: MEETING DATE
8.Andrew MacArthur, City Attorney: EB Council 2/22/99
6:30PM
ITEM NUMBER: ITEM DESCRIPTION:
8.1. Resolution Authorizing Condemnation for Odean Avenue Road Project.
8.2. Review Proposed Bonestroo Contract
8.3. Any Other Legal Business
BACKGROUND*
No.8.land 8.2 Above:
Attached in the information from Andy MacArthur. He will be present to explain and answer any
questions you may have.
RECOMMENDATION:
This is for Council consideration and Mr. MacArthur will explain which items he needs action on.
Thanks,
Elaine
Michael C. Couri•
COURI & MACARTHUR
Andrew J. MacArthur
Attorneys at Law
Marcus W. Miller
705 Central Avenue East
PO Box 369
amu° Unnued in nfinois
St. Michael, MN 55376-0369
(612) 497-1930
(612) 497-2599 (FAX)
counandmacarthur@pobox com
February 17, 1999
City Council Members
City of Otsego
c/o Elaine Beatty, City Clerk
8899 Nashua Avenue NE
Elk River, MN 55330
RE: Proposed Condemnation Resolution For Odean Avenue
Dear Council Members:
Please find enclosed a proposed resolution authorizing condemnation for Odean Avenue.
I am recommending that this resolution be considered at the next Citv Council meeting.
At this time all appraisals for Odean Avenue have not been completed, and the right of
wav agents leave not yet been able to make offers to the property owners since they are
still working on the sewer and water collection system easements.
I will be available to further discuss the resolution and condemnation process at the
regularly scheduled City Council meeting on Monday night.
Very troy_ yours,
Air drew J./NYacArthuf
COURI A MACARTHUR
Encl.
cc: Larry Koshak, John Harwood, Hakanson Anderson
Matt Storm, Evergreen
Mike Robertson, City Administrator
CITY OF OTSEGO
COUNTY OF WRIGHT
STATE OF MINNESOTA
RESOLUTION AUTHORIZING PROCUREMENT OF PERMANENT AND
TEMPORARY CONSTRUCTION EASEMENTS AND OTHER LANDS FOR
IMPROVEMENTS TO ODEAN AVENUE BY EMINENT DOMAIN
WHEREAS, -the City of Otsego proposes to construct and improve Odean Avenue; and
WHEREAS, the improvements consist of a bituminous overlay and reconstruction of the
roadway, including necessary storm water drainage improvements, retention and holding
pond areas, and a bike path parallel or along the roadway of said Odean Avenue; and
WHEREAS, certain permanent roadway easements, drainage and utility easements, land
parcels, and temporary construction easements are required to construct said Odean Avenue
as set forth on Exhibit A hereto attached; and
WHEREAS, the City has authority to acquire said easements by eminent domain pursuant to
Minn. Stat. 117.011 and 117.042; and
WHEREAS, the City has the right to acquire the easements prior to the filing of an award by
the court appointed Commissioners, pursuant to Minn. Stat. 117.011 and 117.042; and
WHEREAS, the land over which said permanent roadway easements, utility and drainage
easements, separate parcels, and temporary easements are required is owned by the following
persons (See Exhibit A); and
WHEREAS, the following have an interest in said lands (See Exhibit B); and
WHEREAS, the City has contracted with Evergreen Land Services to negotiate said
easements and acquisition of parcels; and
WHEREAS, Evergreen Land Services has, as of this date, been unable to successfully
negotiate the acquisition of the required easements and land parcels.
NOW THEREFORE BE IT RESOLVED, that the City of Otsego City Council hereby
authorizes the acquisition of said land by eminent domain and to take title and possession of
that land prior to the filing of an award by the Court appointed Commissioners, pursuant to
Minn. Stat. 163.02, Subd. 2, 117.011 and 117.042; and
BE IT FURTHER RESOLVED, that the City Attorney is requested to file the necessary
Petition therefor, and to prosecute such action to a successful conclusion or until it is
abandoned, dismissed, or terminated by the City or the Court.
Motion to adopt this Resolution made by
. this
IN FAVOR:
OPPOSED:
ATTEST:
Elaine Beatty
City Clerk
day of
and seconded by Council Member
1999.
CITY OF OTSEGO
Larry Fournier
Mayor
Michael C. Couri-
Andrew J. MacArthur
Marcus W. Miller
*,41w teemed in nfinou
February 17, 1999
City Council Members
City of Otsego
c/o Elaine Beatty, City Clerk
8899 Nashua Avenue NE
Elk River, MN 55330
COURT & MACARTHUR
Attorneys at Law
705 Central Avenue East
PO Box 369
St. Michael, MN 55376-0369
(612) 497-1930
(612) 497-2599 (FAX)
couriandntacarthurOpobox. com
RE: Proposed Agreement between Bonestroo and Otsego For Construction
Inspection Services
Dear Council Members:
Enclosed please find a copy of the proposed Agreement for Construction Observation
between the City of Otsego and Bonestroo, as discussed at a previous City Council
meeting. Since I just received the proposed agreement in the mail today I have not yet
had a chance to review the document.
I will provide the Council with my comments at the vlonday City Council meeting. It is
my understanding that Ted Field from Bonestroo will be in attendance at the meeting.
Very truly yours,
Anch-ew J. MacArthur
COURI & MACARTHUR
Encl.
cc: Ted Field, Bonestroo
Mike Robertson, City Administrator
FEB
Bonestroo
Rosene
Letter of Transmittal A,=ci
Anderlik &
Assodates
Engineers & ArMtects
Date: February 11, 1999 We are sending you:
Project. City of Otsego WWTF ® Attached ❑ Under Separate Cover
File No: 50398003
To: Andrew MacArthur
Couri & MacArthur
705 Central Ave E
P.O. Box 369
St. Michael, MN 55376-0369
Re: PROFESSIONAL SERVICE AGREEMENT
❑ Shop Drawings ❑ Specifications ❑ Plans
❑ Copy of Letter ❑ Samples ❑ Change Order
u
Copies I Description Code
1 Between City of Otsego and Bonestroo, Rosene, Anderlik & Associates, Inc. 4
These are transmitted: (See Code)
1. For approval 5. No exceptions taken 9. Submit _ copies for distribution
2. For your use 6. Make noted corrections 10. Return _ corrected prints
3. As requested 7. Amend and resubmit 11. For Bids Due:
4. For review and comment 8. Resubmit _ copies for review 12.
Remarks:
Signed:
4
Bonestroo, Rosene, Anderlik and Associates, Inc.
St. Paul Office: Milwaukee Office: Rochester Office:
2335 West Highway 36 1516 West Mequon Road 2222 Hwy 52 North
St. Paul, MN 55113 Mequon, WI 53092 Rochester, MN 55901
Phone: 651-6364600 Phone: 414-241-4466 Phone: 507-282-2100
Fax: 651-636-1311 Fax: 414-241-4901 Fax: 507-282-3100
Willmar Office:
205 5th Street SW
Willmar, MN 56201
Phone: 320-214-9557
Fax: 320-214-9458
St. Cloud Office:
2008 8th St. North
St. Cloud, MN 56303
Phone: 320-251-4553
Fax: 320-251-6252
February 11, 1999
City of Otsego
8899 Nashua Ave NE
Otsego MN 55330
Attn: Mike Robertson, City Administrator
Re: Wastewater Treatment Plant Engineering Agreement
Our File No. 50303
Dear l fike:
Enclosed are two signed copies of the engineering agreement for construction services
related to the wastewater treatment plant. A copy has been sent separately to Andy
tifacArthur for his review_ The agreement includes full-time inspection services.
Ii acceptable, please signboth copies and return one to our office.
SLrcert-.l�',
BONESTROO, ROSEINTE, AINDERLIK & ASSOC'L�kTES, PNC.
Ted K. Field
Incl
2335 West Highway 36 ■ St. Paul, MN 55113 ■ 651-636-4600 ■ Fax: 651-636-1311
Bonestroo
60neS000. Rose -e Anderhk and Associates, Inc. is an Affirmative ACtlon/Eoual O000rrumry Employer
PrIrCICAIS Ott: = 3onestroo. PE • Icsepn C. Ancerlik. PE. • Marvin L. Sorvala. PE.
Richard E 'urre'. '_. • Glenn R. rook. PE. • Robert G. Scnunicnt. P.E. •Jerry A. Bourder. PE.
Rooert IN
NEWRosene
Rose-e,'E. and Susan M Eoerhn. C.PA.. Senior Consultants
Anderlik &
Associate Pnncars Howard A. Sanford. PE. • Kean A. Gordon, PE. • Rooert R. Pfefferfe. PE.
Ricnarc '.V Fos%'E • David O. Loskota. PE. Rooert C. Russek. A.I.A. • Mark A. Hanson. P.E.
Associates
Micnael i Rau,- arn. PE. • Ted K. Fte'd. PE. • Kennetn P Anderson. PE. • Mark R. Roifs. ?c ,
Sidney P Wtlhar-scn. PE.. LS. • Rooert F Kotsmitn • Agnes M. Ring • Micnael P Rau. ?E.
Allan lick Schm:c:. PE.
Engineers & Architects
Offices: St.'au: P:cnester. Willmar and St. Cloud. MN • ,Milwaukee. ` l
weos;te ww.vc:^estroo.com
February 11, 1999
City of Otsego
8899 Nashua Ave NE
Otsego MN 55330
Attn: Mike Robertson, City Administrator
Re: Wastewater Treatment Plant Engineering Agreement
Our File No. 50303
Dear l fike:
Enclosed are two signed copies of the engineering agreement for construction services
related to the wastewater treatment plant. A copy has been sent separately to Andy
tifacArthur for his review_ The agreement includes full-time inspection services.
Ii acceptable, please signboth copies and return one to our office.
SLrcert-.l�',
BONESTROO, ROSEINTE, AINDERLIK & ASSOC'L�kTES, PNC.
Ted K. Field
Incl
2335 West Highway 36 ■ St. Paul, MN 55113 ■ 651-636-4600 ■ Fax: 651-636-1311
PROFESSIONAL SERVICES AGREEMENT
Between
CITY OF OTSEGO
and
BONESTROO, ROSENE, ANDERLIK AND ASSOCIATES, INC.
THIS IS AN AGREEMENT, effective on February . 1999, between the City of Otsego,
Minnesota ("Cihj") and Sonestroo, Rosene, Anderlik and Associates, Inc., St. Paul, MN ("Engineer'), for
professional encineering services. City and Engineer agree as follows.
SECTION 1. PROJECT DESCRIPTION AND UNDERSTANDING
The "Project" consists of construction of a 200,000 gpd wastewater treatment facility as designed by and
depicted in the plans and specifications prepared by the Engineer. The estimated construc5on cost is
S2.3 million for the new facility.
SECTION 2. ENGINEER'S SERVICES
2.1. Scooe of Basic Services
The Encireer shall provide Basic Services as outlined in Appendix A, Section 1.
2.2. Supplemental Services
As described in Appendix A, Section 2, if requested and authorized in advance by the City, the
Engineer may furnish "Supplemental Services", services which are not included as Basic Services.
Engineer shall submit a description and an estimate of the cost for any City--equested
Supplemer,al Services for the City's written approval prior to commencement of the work.
SECTION 3. COMPENSATION
3.1. Payment for Basic Services
For completion of the Engineer's Basic Services as outlined in Appendix A„ the City will pay the
Engineer on an hourly basis in accordance with the Billing Rate Schedule attached as Appendix
C, plus reimbursable expenses. Engineer's labor costs are estimated to be $189,000 but actual
costs may vary. Engineer's level of services (and thus, actual charges) will depend in part on
such currently unknown factors as quality and responsiveness of the Contractor, weather
conditions and adherence to the construction schedule, and unforeseen site conditions that may
be reveaied during construction.
3.2. Payment for Supplemental Services
For Supplemental Services authorized by the City and performed by the Engineer, the City will pay
the Engineer on an hourly basis in accordance with the Billing Rate Schedule attached as Appendix
C, plus Reimbursable Expenses.
W DATAWSERWK7AGM0tsego A3 096.doc
SECTION 4. STANDARD TERMS AND CONDITIONS
The Standard Terms and Conditions attached as Appendix B are incorporated in this Agreement.
.......................... H.......... H H....1 H..*.........
IN WITNESS WHEREOF, the parties hereto have made and executed this Agreement as of the day and
year first above written.
ENGINEER:
BONESTROO, ROSENE, ANDERLIK &
ASSOCIATES, INC.
� � 1
By
Ma in L. Sorvala, President
Date `1
CITY:
CITY OF OTSEGO, MINNESOTA
By
Larry Fournier, Mayor
Date
And by
Mike Robertson, Administrator
Date
\\l DATA\USER\MKTPAGR\Otsego A3 0%.doc 2
Appendix A
Engineer's Services
Section 1. Basic Services
Task 1 - Bidding and Award
Purpose: To assist the City in obtaining construction bids and awarding a construction contract to the
lowest responsive bidder.
1.1 Prepare bid proposal and contract forms
1.2 Issue bid advertisement
1.3 Hold pre-bid conference with prospective bidders
1.4 Issue addenda if necessary
1.5 Receive bids
1.6 Analyze bids and recommend award
Task 2 - Contract Administration
Purpose: To develop channels of communication between the contractor, City staff, and Engineer; to
:keep the City informed about the progress of construction; and to review and approve shoo
drawings.
2.1 Organize, attend and assist the City at the pre -construction conference with the successful bidder,
and any other parties, bodies, or agencies who have an interest in the Project.
2.2 Review shoo drawings, samples and other submittals. Engineer shall review shoo drawings,
samples and other submissions of the Contractor solely for their general compatibility with the Engineer's
design intent and conformance with information given in the Contract Documents. The Engineer shall net
be res,ccnsibie for any aspects of a shop drawing submission relating to the duties of the Contractor (such
as the means, methods, techniques, sequences and operations of construcnon, safety precautions and
programs incidental thereto) ail of which are the Contractor's responsibility, and not the responsibility of the
Engineer.
2.3 Review the Contractor's request for progress payments, advise the City in writing as to the
Engineer's opinion of the extent of the work completed in accordance with the terms of the Construction
Contract, and issue for processing by the City ail requests for payment.
2.4 slake recommendations to the City as to all claims relating to the execution and progress of the
construction work.
2.5 Issue such additional instructions to the Contractor as may be necessary to interpret the drawings
and specifications or the illustrated changes required in the Contractor's work.
2.6 After consulting with the City, prepare Change Orders for work not covered by the Contract or for
substantial over -run of estimated 'contract quantities" as defined in the Project's Contract Documents, for
the City's approval and execution. Change Orders shall be processed as soon as practical after the City
provides written approval to the Engineer. The City understands that Change Orders may be required
during a Project for many reasons, including because of incompleteness, errors, or ambiguities in the
Construction Documents. The Engineer shall not be liable for any type or quantity of Change Orders that
are within professional standards. In no event shall the Engineer be responsible for paying the cost of a
Change Order or other change to the extent that it would have been otherwise necessary to the Project or
otherMse adds value or betterment to the Project.
\\10A7AWSERWK71AGR10tseg A3 096.doc A - 1
2.7 Conduct bi-weekly construction progress reviews with the Contractor and the City related to the
Contrectcr's date of completion.
Task 3 - Construction Observation
Purpose: To endeavor to assure that the plant is constructed in conformance with the plans and
specifications.
3.1 Perform on-site construction observation as necessary to become generally familiar with the
progress and quality of the contractor's work and to determine if the work is proceeding in general
accordance with the Contract Dcc=ents. The City has not retained the Engineer to make detailed
inspections or to provide exhaustive or continuous Project review and observation services. Further, the
Engineer does not supervise or have control over the Contractor's work, the means or methods of
construction, or safety precautions in connection with the work. As a result, the Engineer does not
guarantee the performance of a contractor, and has no responsibility for the acts or omissions of any
contractor, subcontractor, supplier or any other entity furnishing materials or performing any work on the
Project.
3.2 Act as City's liaison with contractor
3.3 Maintain field records
> Record of site visits and observations
> Phone call log
> Weather conditions
> Meetings, discussions, observations and decisions
> Photograph project progress and underground construction details
3.4 Provide monthly reports to City
3.5 Coordinate periodic field tests during the course of construction
3.6 Endeavor to assure that record plans are being maintained by all contracting forces
T^e Engin3er's review of the Contractor's work (including reviewing the Contractor's shop drawings and
samples, work product and requests for payments) do not increase the responsibility or duties of the
Engineer beyond those explicitly described elsewhere in this Agreement. By making these review efforts,
the Engineer does not guarantee the performance of the Contractor or assume responsibility for any acts
or omissions of the Contractor, including any failure of the Contractor to properly perform its work or
comply with its obligations, and the City's sole remedy for the Contractor's acts or omissions is from the
Contractor and not the Engineer.
Task 4 - Contract Close Out
Purpose: To neip train plant operators; to endeavor to provide a successful transition from construction
I
o operation; to certify that construction is complete prior to final payment.
4.1 Prepare operation and maintenance manuals regarding operating and maintaining equipment,
machinery and apparatus installed as part of the Project. Such instructions shall be supplied by the
Contractor and manufacturers' representatives.
4.2 Provide plant start-up services.
4.3 Assist with training of operators.
4.4 Conduct an inspection to determine if the work is substantially complete. On the basis of its on-site
observations, the Engineer shall prepare a "punch list" for the Contractor, listing work left to be completed
by the Contractor.
\\1 DATAWSER\MKMAGR\01sego A3 096.doc A-2
A
.5 Conduct, in the presence of the City's Representative, a final inspection of the Project as constructed
to determine whether it:
1) Generaiiy conforms with the Engineer's design concept of the Project as contained in the
Contract Documents, and
2) Appears to be constructed in accordance with the Contract Documents.
The Engineer shall certify a recommendation for acceptance of the work to the City and then shall forward
to the City a written approval of the Contractor's Request for Final Payment which shall be signed by the
Contractor.
4.6 Prepare and furnish the City a set of reproducible "Record Plans" of the Project showing those
changes the Engineer considers significant which were made during the construction process, based on
marked -up prints, drawings, and other data fumished by the Contractor, upon which the Engineer may
rely in preparing the Record Plans.
Section 2. Potential Supplemental Services
If authorized in advance by the City, the Engineer may provide the following Supplemental Services:
2.1 klaking revisions in drawings, specifications or other documents when such revisions are:
2.1.1 Requested by the City and inconsistent with approvals or instructions previously given by the
City;
2.1.2 Required by the enactment or revisions of codes, laws or regulations subsequent to the
preparation of such documents;
2.1.3 Due to changes required as a result of the City's failure to render decisions in a timely manner; or
2.1.4 Due to any other causes beyond the Engineer's control.
2.2 Providing consultation regarding the replacement of all such parts of the Project as may be damaged
by fire or other cause during construction and assisting the City in arranging for continuation of the work
should the Contractor default for any reason.
2.3. Providing services made necessary by the default of a Contractor, by major defects or deficiencies in
the work of a Contractor, or by failure of performance of either the City or a Contractor under the Contract
for construction.
2.4 Construction dispute resolution assistance.
2.5 Providing services in connection with warranty work to be done by the Contractor.
2.6 Providing one or more full-time Resident Project Representatives (and assistant[sj) in order to
provide the City with continuous representation at the Project site during the Construction Phase_
2.7 Assisting the City or its representative in connection with mediation, arbitration, litigation or other
proceedings involving the Project, including preparing to testify and testifying as an expert witness.
2.8 Providing any other service not otherwise included in Basic Services or not customarily furnished in
accordance with generally accepted engineering practice.
\\1 OATA\USER\MK7AGR\Otsego A3 096.doc A-3
Appendix B
Standard Terms and Conditions
SECTION 1. ENGINEER'S SERVICES ccrings, probirgs and subsurface explorations;
-•,drographic surveys, laboratory tests and inspections of
Engineer shall act as the City's ('Cwner's') agent only as samples, materials and equipment; appropriate
provided for within this Agreement. professional interpretations of all of the foregoing;
property, boundary, easement, and right-of-way surveys
SECTION 2. THE OWNER'S RESPONSIBILITIES and property descriptions; zoning and deed restrictions.
The Owner shalt:
1) Provide full information as to its requirements for the
Project.
2)
3)
51
Fumish to the Engineer, prior to any performance by the
Engineer under this Agreement, a copy of any planning,
design and construction standards which the Owner shall
require the Engineer to follow in the conduct of its services
for the Project.
Place at Engineer's disposal all available written data in
the possession of or readily available to the Owner and
pertinent to the Project, including existing reports, plats,
surveys, contour mapping, utility mapping, record plans,
,.vetlands, land -use, and zoning maps, bcrirgs and other
data useful to the Engineer in the performance of its
services.
Acquire all land, easements, and rights-cf-way and
provide for land surveys and the preparation of legal
descriptions and exhibits, certificates or plats. as may be
necessary for the Project.
5) -rovide access to the Project site and make all provisions
for the Engineer to enter upon public and private lands as
required by the Engineer to perorm its se.riices.
o)
7)
N
N
Examir.e all studies, reports. sketc"res. Cpinions of
Probable Construction Costs. specifications, drawings,
proposais and other documents presented by the
Engineer and render a decision when necessary within a
reasonable period of time.
Designate a single person to act as the Owner's
Representative with respect to the Engineer's services.
Such person shall have comciete authority to transmit
instructions, receive information, and interpret and define
the Owner's policies and decisions with respect to services
covered by this Agreement, subject to Owner's governing
body approval when required by law.
Give prompt written notice to the Engineer whenever the
Owner has actual knowledge of any defect in the Project.
or has actual knowledge of any circumstance that affects
the scope or timing of the Engineer's services.
Fumish, or instruct the Engineer to provide at the Owner's
expense, necessary "Supplemental Services' as may be
provided for in this Agreement, or other services as they
may be required.
10) Fumish to the Engineer, as required by the Engineer for
performance of its services, information or consultations
not covered in the Engineer's Basic Services, such as core
11) Fumish approvals and permits from all governmental
authorities having jurisdiction over the Project, except for
these permits and approvals for which the Engineer will be
responsible for providing submittals under this Agreement,
and such approvals and consents from others as may be
necessary for completion of the work.
12) Fumish inspection or monitoring services as the Owner
desires to verify that Contractor is complying with all laws
or regulations and to verify that Contractor is taking all
necessary safety precautions to protect persons and
property, as the Engineer in this Agreement does not
undertake to perform these services.
In per-orming its services, the Engineer may rely upon the
accuracy and completeness of all Owner -provided information,
unless the Engineer has knowledge that the information may
not be complete or accurate.
SECTION 3. COMPENSATION
3.1 Payment for Reimbursable Expenses
Unless otherwise provided, in addition to Engineering fees. the
Owner will pay the Engineer for reasonable Reimbursable
Expenses on the basis of the Engineer's cost. Although not a
complete list, examples of Reimbursable Expenses include:
the tests of plotting drawings and the reproduction of drawings
and scecifications: project -specific printing, duplicating, tabs
and indexes; testing; mileage; travel and per -diem expenses of
the Engineer for out-of-town trips required for the Project; long
distance telephone calls and faxes as required to expedite the
work; the costs for cellular phone calls/service for Engineer's
field personnel on a Project; project photographs taken before
and during construction; construction stakes; postage and
delivery charges; and out-of-pocket expenses incurred directly
for the Project.
3.2. Obiections to Invoices/No Deductions
It is important for the Engineer to be promptly informed of
problems. If the Owner objects to any portion of an invoice,
the Cwner shall notify the Engineer in writing within twenty
days of the invoice's receipt. The Owner agrees to pay any
portion of the invoice which reasonably appears to be
undisputed, but reserves the right to later contest any portion
of the invoice if it is later discovered that the work was not
complete or was not done correctly.
3.3 Suspension of Work
If the Owner fails to make payments when due or otherwise
breaches this Agreement, the Engineer may suspend work
after providing five days notice to the Owner. The Engineer
will not be liable for any costs or damages resulting from such
\\1CA7A\USERIA1KT\AGR`Ct5eg0 A3 096.doc B-1
a suspension of work. If the Engineer fails to timely perform, or
otherwise breaches this Agreement, the Owner may stop
,yment to the Engineer and take whatever steps necessary to
7,plete the Project, including contracting with another
_-gineer for timely completion of the Project. In the event of
such a breach by the Engineer, any additional payment to the
Ergineer will have deducted from it costs incurred by the city in
remedying the breach.
3.4. Progress Payments
The Engineer will submit a property documented invoice when
it has completed the services described in § 1.5 of Appendix A
to this Agreement or April 30, 1998, whichever comes first.
The Owner shall make payment of all undisputed portions of
that invoice (and later invoices, if such invoice is not for all
services contemclated under this Agreement) within 30 days
after the Owner's receipt of such invoice, subject to Section 3.2
of this Appendix. Owner may not reserve as retainage any
portion of a payment due and owing under this Agreement
3.5. Interest/Collection Costs
The Owner agrees to pay the Engineer 1% per month interest
on all portions of Engineer's invoices which are due and owing,
with interest beginning to accrue 30 days after the date of the
invoice. Engineer agrees to pay all subcontractors on the
Project within ten (10) days of receipt of payment of its invoice.
SECTION 4. GENERAL CONSIDERATIONS
'. Standard of Care
. ,:e Engineer shail exercise the same degree of care, skill and
diligence in the performance of its services as is ordinarily
exercised by members of the profession under like
circumstances.
4.2. Delays
cell the Engineer and the Owner will put forth reasonable
ef;crs to compiete their respective duties in a timely manner.
Secause the Encineer's performance must be governed by
sound professional practices, the Engineer is not responsible
fcr delays occasioned by factors beyond its control or that
could not reasonably have been foreseen at the time of
preparation of this Agreement..
4.3. Ooinions of Costs and Schedules
S.-ce the Engineer has no control over the cost of labor and
material or over competitive bidding and market conditions, the
Engineer's Opinion of Probable Construction Cost and of
Project schedules can only be made on the basis of
experience or qualifications as a professional Engineer. The
Engineer does not guarantee that proposals, bids, actual
Project costs or construction schedules will not vary from
Engineers opinions or estimates. If the Owner desires greater
assurance as to the anticipated Construction Cost of the
Project, the Owner shall employ, or instruct the Engineer to
provide as a Supplemental Service, an independent cost
'imator.
4. Insurance
4.4.1. The Engineer agrees to maintain a professional
liability insurance policy for negligent acts, errors or omissions
in an amount of at least 52,000,000 annual aggregate, on a
claims -made basis as long as such insurance is reasonably
available.
4.4.2. The Engineer shall maintain
1) Statutory workers compensation and employers' liability
insurance coverage.
2) Comprehensive general liability and automobile liability
insurance coverage in the sum of not less than
S1,000,000 each.
4.5. Ownership of Instruments of Service
4.5.1 Documents (including Electronic Data) prepared by the
Engineer, such as drawings, specifications and reports
("Engineering Documents") are instruments of the Engineer's
professional services, and not products. A printed copy of the
reports, drawings, and specifications prepared under this
Agreement shall become the property of the Owner upon
completion of the services and payment of all amounts due
and owing the Engineer. However, the Engineer retains its
rights in standard drawing details and specifications, and in its
field data, notes, databases, computer files, software,
proprietary property and intellectual proper,/ developed or
modified in the performance of its services, and further retains
an unrestricted right to use the Engineering Documents in the
course of its business.
4.5.2 The Engineering Documents are prepared for the Project
and may not be used for other projects, except the Owner has
the right to use the Engineering Cccuments for informational
purposes or to illustrate the design and/or location of existing
facilities for purposes of expansion, rehabilitation, or retrofit of
the Project. Except as permitted herein, the Owner agrees it
will not use the Engineering Cccuments for other purposes or
provide them to other persons for purposes other than the
Project. If the Owner violates :his provision by using the
Engineering Documents for unallowed purposes and, as a
result of such violation, damage occurs to it or others, it waives
claims against the Engineer caused by such violation and
agrees to defend and indemnity the Ergineer from claims
pursued by others against Engineer if caused by such
violation.
4.6. Electronic Data
4.6.1. If included in Basic Services er Supplemental
Services and as a convenience to the Owner, the Engineer will
furnish the Owner with electronic data versions of certain
drawings or other written documents ("Electronic Data")
provided in hard copy form. In the event of any conflict
between a hard copy document and the Electronic Data, the
hard copy document governs. The Electronic Data shall be
prepared in the current software in use by the Engineer and is
not warranted to be compatible with other systems or software.
4.6.2. Any Electronic Data submitted by the Engineer to the
City is submitted for an acceptance period of 60 days
('Acceptance Period"). Any defects that the City discovers
during this period and reports to the Engineer will be corrected
by the Engineer at no extra charge. For correction of defects
reported to the Engineer after the Acceptance Period. the City
shall compensate Engineer on an hourly basis at Engineer's
billing rates set forth in Appendix C. The City understands that
'd'CATAWSE.RIMKTAGR1,Otsegc A3 096.doc &2
the Electronic Data is perishable and the City is responsible for
maintaining it.
7. Termination, Suspension or Abandonment
4.7.1 The Cvner or the Engineer may termirate or suspend
:ris Agreemert. The terminating or susperding party shall
,airy the other party 14 calendar days prior :o the effective
Zate of the termiration or suspension.
4.7.2 The Engineer and the Owner will cooperate if the
ngineer's work is terminated, suspended or abandoned for
any reason. In addition, the Owner shall timely pay the
Engineer for services rendered and costs incurred, if they are
�ue and owing under this Agreement. Services and costs shall
.nclude only those due and owing, rendered and incurred up to
:.`.e time of ter—urination, suspension or abandonment. In the
event that the Engineer terminates, suspends, or abandons
this Agreement, and the City has paid all amounts due and
owing under this Agreement, then Engineer shall promptly
supply the Owner with all documents, to the extent prepared or
completed by Engineer, provided, however, if there is a dispute
as to amounts due and owing to Engineer, Owner shall only be
entitled to such documents after payment to a mutuagy
agreeable escrow agent the amount claimed due and owing by
Engineer, and Engineer and Owner shall promptly resolve
such dispute pursuant to § 4.8 of this Appendix.
4.3. Dispute Resolution
4.8.1 In an effort to resolve any conflicts that arise out of
:`a services under this Agreement, all disputes between the
wrier and the Engineer arising out of or relating to this
reement shall be submitted to nonbinding mediation prior to
�mmencing ar^itration or litigation.
4.3.2 Unless the Owner and the Engineer mutually agree
c:hervise, all claims, disputes, and other matters in question
_::sing out of or relating to this Agreement which are not
�asolved by mediation and where the amount in controversy is
ess than S200.3CO3 shall be decided by bindir-g arbitration in
azcordarce witli :.ne then -most current Construc5on Industry
-ules of the An-er,can Arbitration Association.
1.8.3 In the event of litigation or arbitration arising from or
riated to the services provided under this Agreement, the
prevailing party is entitled to recovery of all reasonable costs
incurred. including staff time, court costs, attomeys fees and
c:her related expenses.
;.8.4. if the Engineer or the Owner intends to assert a claim
against ire other as a result of a dispute with a third party, the
c:aiming tarty s -ail notify the other party as soon as possible,
and in any event prior to resolving the dispute with the third
=arty.
4.9. Hazardous Substance
-he Engineer's scope of services does not include any
services related to hazardous or toxic materials, including
asbestos and PCBs. If it becomes known that such materials
^ay be present at or near a Project that may affect the
ngineers services, the Engineer may suspend performance
its services, without liability, and will assist the Owner to
.ain appropriate consultants to adequately identify and abate
such materials so that Engineer's services may resume.
4.10. Governing Law
This Agreement shall be governed by the laws of the State of
Minnesota and any dispute shall be venued in the state or
federal courts in Minnesota.
4.11. Integration
This is an integrated Agreement and it supersedes all prior
negotiations or agreements between the parties. It shall be
modified only by a written document signed by the party sought
to be bound. The provisions of this Agreement are severable,
and if any provision is found to be unenforceable, the
remaining provisions continue to be valid, and the
unenforceable provision shall be reformed with a valid
provision that comes as near as possible to expressing the
intention of the unenforceable provision.
4.12. Assignment
Except for the Engineer's use of necessary consultants, the
Engineer and the Owner shag not assign or delegate their
respective obfigations under this Agreement without the written
consent of the other party, which consent shall not be
unreasonably withheld.
SECTION 5. LIABILITY
Having considered the potential liabiiities that exist during the
performance of the Engineer's services, the benefits of the
Project, the Engineer's fee for its services, and the promises
contained in this Agreement, the Owner and the Engineer
agree that risks should be allocated in accordance with this
section, to the fullest extent permitted by law.
5.1 Indemnification
The Engineer and the Owner each agree to defend and
indemnity each other from liability for claims, losses, damages
or expenses (including reasonable attorney's fees) to the
extent they are caused by their negligent acts, errors or
omissions relating to this Agreement. In the event the claims,
losses, damages or expenses are caused by the joint or
concurrent negligence of the Engineer and the Owner, they
shall be bome by each party in proportion to its own
negligence.
5.2 Limitation of Liability
The Engineer's and its employees' aggregate liability to the
Owner for any and all claims, losses or damages arising out of
any Project or this Agreement for any cause shall not exceed
the total combined sum of 52,000,000.
5.3 deleted
5.4 deleted
CATA11;S_RWK7; GR%0tseg0 A3 046.dcc B-3
Appendix C
1997 Billing Rate Schedule
Classification Hourly Rate
Senior Principal S94.50
Principal/Project Manager; Senior Scientisti 84.50
Registered Engineer/Architect/Landscape Architect; Natural i
!Resource Specialist 73.50
Prosect Engineer/Architect/Landscape Architect/Scientist; Sr.
:Field Supervisor i 64.50 j
GIS Specialist; Senior Designer 1 63.50
Graduate Engineer/Architect/Scientist• Field Supervisor
I 57.50
iSenior Drafter/inspector
i 52.00 !
Inspector, Drafter, Senior Technician
I 48.50 j
Technician
I 34.50
Word Processor
I 34.00
JTotal Station Equipment
20.00
GIS Workstation Equipment
I 20.00
GPS Equipment
( 50.00 / haff da
!Attendance at City Council Meetings I 50.00 / meeting I
I i
(These rates are adjusted annually in accordance with the normal review
'procedures of Bonestroo. Rosene, Anderiik and Associates. Inc.
\\1OATXUSERWKT'AGR\Otsego A3 096.doc C_1
CLAIMS LIST
CITY COUNCIL MEETING
FEBRUARY 22, 1999
TO: City Council
Attached is the Claims List for your consideration.
The grand total you are considering is as follows:
Batch 02-22-99 $154,530.03*
GRAND TOTAL $154,530.03*
*The check issued to Maguire Iron for $66,600.00 and the check issued to
Traut Wells for $24,599.06 were previously approved by the Council and are
now being issued.
If you have any questions or if you would like to review this list further, please let me
know.
Judy Hudson
Deputy Clerk/Treasurer
18 Fab 1999 Claims List Page 1
Thu 6:51 AM CITY OF OTSEGO
Na
Batch Name 022299
ABRA AUTOBODY & GLASS
AFFORDABLE SANITATION
AIRGAS, INC.
BEAR ALARMS
BT OFFICE PRODUCTS
CAROL OLSON
CROW RIVER FARM EQUIPMENT
CROW RIVER NEWS
CUB FOODS ELK RIVER
DJ'S HEATING & AIR CONO
DJ'S TOTAL HOME CENTER
EAST SIDE LEASING CO
ECM PUBLISHERS INC
ECM PUBLISHERS INC
ECM PUBLISHERS INC
ECM PUBLISHERS INC
ELK RIVER PRINTING & PARTY PLU
EVERGREEN LAND SERVICES CO
G & K TEXTILE LEASING SYSTEM
G & K TEXTILE LEASING SYSTEM
G & K TEXTILE LEASING SYSTEM
GLF- 'RUCK CENTER INC
GM JLTANTS, INC.
GROG„ uARY CPA
H G WEBER OIL COMPANY
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
HAKANSON ANDERSON ASSOC INC
ICMA RETIREMENT TRUST
1CMA RETIREMENT TRUST
MAGUIRE IRON, INC.
M E O I C A
MEDICA
MENARC3
MINNESOTA .MUTUAL
Mi' 'A MUTUAL
10.
Dept
Description
Hwys, Streets, & Roads
Culture and Rec (GENERAL)
Hwys, Streets, & Roads
General Govt Buildings -8899
Administration
Hwys, Streets, & Roads
Administration
Culture and Rec (GENERAL)
Hwys, Streets, & Roads
Hwys, Streets, & Roads
Administration
Administration
Administration
Administration
Administration
Administration
Sanitary Sewer Construction
General Govt Buildings -8899
Hwys, Streets, & Roads
Hwys, Streets, & Roads
Hwys, Streets, & Roads
Sanitary Sewer Construction
Finance
Hwys, Streets, & Roads
Water Utilities (GENERAL)
Hwys, Streets, & Roads
Hays, Streets, & Roads
Sanitary Sewer Construction
Sanitary Sewer Construction
Sanitary Sewer Construction
Sanitary Sewer Construction
Sanitary Sewer Construction
Engineer
Engineer
Engineer
Sanitary Sewer Construction
Sanitary Sewer Construction
Administration
Hwys, Streets, & Roads
Administration
Sanitary Sewer Construction
Hwys, Streets, & Roads
Administration
Culture and Rec (GENERAL)
Administration
Hwys, Streets, & Roads
Hwys, Streets, & Roads
Comments
Repair Glass Windshield
Rental toilet unit
Rental
1 Yr monitoring
Office Supplies
Reinbursement Medical
Miscell supplies
2 Yr renewal
Winter Fest supplies
Repair water heater
Miscell supplies
Monthly rental
Legal notice
Legal ordinace 99-1
City Summary Budget
Display Ad - facility
Bldg Permits printed
ROW
Supplies
Supplies
Uniforms
Miscell supplies
Testing serines
January Services
Gas & Oil
Well Y1
MSA Adm
Culvert Mason Ave
Well No 2 Design
Well No 2 Extra Services
Water Tower Construction
Water Tower Const Extra
Trunk Sanitary Sew Extra
Miscell Engineering
City Map
Staff Meeting
Pump House &Controls
Pump House/Controls Extra
Heritage Hills a
Odean Ave Extra Service
PPE 2-6-99
PPE 2-6-99
Water Tank & Tower Const
Health Ins
Health Ins
Supplies
Life Ins
Life Ins
Miscell supplies
Transaction Batch
Amount Name
216.25 022299
114.50 022299
12.66 022299
272.64 022299
52.42 022299
66.00 022299
21.99 022299
38.00 022299
169.40 022299
89.00 022299
10.97 022299
237.92 022299
35.36 022299
172.10 022299
205.10 022299
18.70 022299
81.47 022299
6,411.00 022299
100.56 022299
100.57 022299
171.92 022299
43.50 022299
882.50 022299
870.00 022299
1,707.40 022299
105.00 022299
632.50 022299
196.18 022299
1,147.50 022299
349.35 022299
595.00 022299
1,544.13 022299
1,934.75 022299
1,120.00 022299
43.88 022299
455.00 022299
4,682.29 022299
274.88 022299
37.50 022299
4,326.72 022299
422.39 022299
192.31 022299
66,600.00 022299
796.37 022299
1,742.42 022299
69.86 022299
26.85 022299
29.60 022299
29.78 022299
18 Feb 1999 C11111 Lilt Page 2
Th( 6:51 AM CITY OF OTSEGO
Dept
Transaction
Batch
No
Description
Comments
Amount
Name
Batch Name 022299
NORTHERN
Hwys, Streets, 3 Roads
Miscell supplies
26.61
022299
NORTHERN
Hwys, Streets, & Roads
Miscell supplies
58.56
022299
NORTHWEST ASSOC CONSULTANTS
Sanitary Sewer Construction
Water Tower CUP
130.03
022299
NORTHWEST ASSOC CONSULTANTS
Planner
Miss Wild & Scenic Plan
608.35
022299
NORTHWEST ASSOC CONSULTANTS
Planner
General Planning Issues
300.89
022299
NORTHWEST ASSOC CONSULTANTS
Planner
Wild & Scenic Ord Task
8.50
022299
NORTHWEST ASSOC CONSULTANTS
Planner
Sanitary Sew System Plan
21.25
022299
NORTHWEST ASSOC CONSULTANTS
Planner
Zoning Ord Update
1,332.91
022299
NORTHWEST ASSOC CONSULTANTS
Planner
Meetings
600.00
022299
PRINCIPAL FINANCIAL GROUP
Hwys, Streets, & Roads
Insurance
82.23
022299
PRINCIPAL FINANCIAL GROUP
Administration
Insurance
183.85
022299
PUBLIC EMPLOYEES RETIREMENT FD
PPE 2-6-99
320.25
022299
PUBLIC EMPLOYEES RETIREMENT FD
Hwys, Streets, b Roads
PPE 2-6-99
188.23
022299
PUBLIC EMPLOYEES RETIREMENT FO
Administration
PPE 2-6-99
161.03
022299
STATE CAPITAL CREDIT UNION
PPE 2-6-99 Olson 141923
50.00
022299
SUPERIOR SERVICES
Recycling
Recylcing services
460.00
022299
TRAUT WELLS
Sanitary Sewer Construction
Pay estimate #1
24,599.06
022299
UNLIMITED ELECTRIC INC
Hwys, Streets, & Roads
Wired garage doors
313.50
022299
WEST SHERBURNE TRIBUNE
Administration
Display Ad Fac
13.40
022299
WRIGHT COUNTY AUDITOR -TREASURE
Police -Contracted
Patrol for Jan & Feb
21,253.15
022299
WRTr"' COUNTY HIGHWAY DEPT
Hwys, Streets, & Roads
Salt and Sand
4,361.44
022299
Grand Total
154,530.03