ITEM 2.2_attachmentReview No. 1 ENGINEERING REVIEW_ Hakanson Commercial Lot for the City of Otsego Anderson by -a Hakanson Anderson Submitted to: Honorable Mayor and City Council cc: Lori Johnson, Administrator Tami'Loff, City Clerk Dan Licht, City Planner Andy MacArthur, City Attorney Steve Fischer, Arrow Companies Todd W. McLouth, P.E., Loucks Associates Reviewed by: Ronald J. Wagner, P.E. Brent M. Larson, P.E. Date: January 5, 2015 Proposed Development: Otsego Waterfront East 5th Addition — Waterfront Commons III Street Location A portion of the SW 1/4 of the SW 1/4 of Section 14, T121N, of Property: R23W, East of Quantrelle Ave and South of 901h Street Applicant: Steve Fischer Arrow Companies 7365 Kirkwood Court N. #335 Maple Grove, MN 55369 Developer: WFC III, LLC Owners of Record: WFC III, LLC Purpose: Otsego Waterfiont East 5th Addition — Waterfiont Commons III is a proposed 32,224 gross square foot 2 story office building located on 2.29 acres of Outlot K of Otsego Waterfront East and Lot 1, Block 1 Otsego Waterfront East 4th Addition in the City of Otsego, Wright County, Minnesota. The proposed development will be served with municipal water, sanitary sewer, storm sewer, and public streets typical of an urban commercial setting. Jurisdictional Agencies: City of Otsego, Wright County, Minnesota Department of (but not limited to) Health, Minnesota Department of Natural Resources, Minnesota Pollution Control Agency, Wright Soil and Water Conservation District. Permits Required: NPDES, Minnesota Department of Health (water), and (but not limited to) Minnesota Pollution Control Agency (sanitary sewer) TABLE OF CONTENTS INFORMATION AVAILIBLE FINAL PLAT SCHEMATIC DESIGN SET EXISTING CONDITIONS (C1.1) DEMOLITION PLAN (C1.2) SITE PLAN (C2.1) GRADING AND DRAINAGE PLAN (C3.1) STORM WATER POLLUTION PREVENTION PLAN (SWPPP) (C3.2 - C3.3) UTILITY PLAN (C4.1) DETAIL SHEET (C8.1- C8.2) ARCHITECTUAL PLANS (A1.1 - Al 1) LANSCAPE PLAN (L1.1 - L1.2) HYDROLOGY/STORMWATER SUMMARY AND/OR RECOMMENDATION PAGE 2 S:\Municipal\Aotsego22xx\2500\2015\WFE 5th Add\ot2500-2015 WFE5 RVW1.doc INFORMATION AVAILABLE Final Plat for Otsego Waterfront East 5th Addition, by Loucks Associates Preliminary Plans for Otsego Waterfront East 5th Addition — Waterfront Commons III, 12/8/14, by Loucks Associates Original Otsego Waterfront East Information Final Plat for Otsego Waterfront East Final Plats for Otsego Waterfront East 1 st thiu 4th Additions Hydrology Report/Storm Sewer Design for Buildings D, E, & F, 2/12/07 revision, by Metro Land Surveying Engineering Hydrology Report/Storm Sewer Design for Building C, 2/13/07 revision, by Metro Land Surveying Engineering Additional Information Minnesota Rules, Chapter 4410 — EAW Requirement Trunk Stormwater Facilities Study for Portions of the Otsego Creek Watershed City of Otsego Engineering Manual City of Otsego Zoning and Subdivision Ordinances National Wetland Inventory Map PAGE 3 S:\Municipal\Aotsego22xx\2500\2015\WFE 5th Add\ot2500-2015 WFE5 RVW1.doc PRELIMINARY PLAT 1) The preliminary plat was reviewed with the existing conditions as much of the information required is shown on one or the other or both. Please note, no preliminary plat submittal was received prior to final plat submittal. FINAL PLAT 1) A 10' wide drainage and utility easement is required along the rear lot line of Lot 2, Block 1. 2) A 10' wide drainage and utility easement (5' each side of property line) is required along the shared lot line between Lot 1 and 2. 3) A 20' wide utility easement centered over the all watermain, hydrant and hydrant leads is required. 4) The shared parking area/drive lane is not shown within any easements. Separate documentation will be required. SCHEMATIC DESIGN SET Existinsi Conditions Plan (Sheet C1.1) 1) List the benchmark(s) to be used. All elevations shall use 1929 datum. 2) (All Sheets) the benchmarks listed are using 1988 datum. All Otsego projects (i.e. Quantrelle Avenue and 90th Street) use the 1929 NGVD datum. Please provide an equation between the separate datum's. Verify that any existing utilities that are proposed to be connected to are labeled with the same datum. 3) Label existing easement. 4) The following required information is missing from the existing conditions plan: a. Label widths of existing streets not just right-of-way. b. Identify by name and ownership, all the adjacent properties within 150' of the boundary. C. Provide the normal and 100 year flood elevations for the regional storm pond to the east of the property. (NWL = 852.60 and HWL = 857.56) Demolition Plan (Sheet C1.2) 1) See Existing Conditions Plan comment #2. 2) (All Sheets) Provide a contact name and phone number for the developer. 3) The existing hydrant proposed to be removed may be able to be salvaged and reused. A hydrant will be needed in the NE corner of the building. PAGE 4 S:\Municipal\Aotsego22xx\2500\2015\WFE 5th Add\ot2500-2015 WFE5 RVW1.doc 4) The bituminous shall be saw cut in all areas where removals are required. The existing pavement next to the new concrete shall be milled 18" wide x 1.5" deep to provide a staggered joint for the wear course. 5) Remove the existing 12" storm sewer pipe from the existing storm manhole in the middle of the proposed parking area. A new cored hole will be required at this manhole for the new proposed pipe connection. 6) A portion of the curb must be removed at the south entrances in order to place pedestrian ramps and the sidewalk. Site Plan (Sheet C2.1) 1) Per the PUD, there is a 0' setback allowed along Quantrelle Avenue and 90th Street. For the rest of the lot lines throughout the development the minimum parking lot setback shall be 5'. 2) It is unclear why the walk between Quantrell Avenue and the parking lot at the north entrance is not a Handicap Accessible route. 3) Call out the concrete aprons at both entrances. 4) Pedestrian Ramps are needed at the south entrance. 5) The parking stalls not adjacent to curb and gutter shall have a minimum depth of 20'. 6) (All Sheets) Provide the normal and 100 year flood elevations for the regional storm pond to the east of the property. (NWL = 852.60 and HWL = 857.56) Grading Plan (Sheet C3.1) 1) See Existing Conditions Plan comment #2. 2) Label the required rim elevation adjustment at each existing storm manhole. 3) It appears that tip out curb is needed in many areas to get the runoff to designated storm sewer. We suggest labeling these on the plans. SWPP Plan (Sheet C3.2 — C3.3) 1) The MPCA NPDES requires volume control for all new construction prior to discharging off-site. It is unclear how this site intends to provide storage or runoff of the 1" rainfall. 2) Inlet protection is missing from the storm manhole along the western curb line. 3) Erosion control (fiber blanket?) is required on the slope east of the bike trail at both trail utility crossings. PAGE 5 S:\MunicipaMotsego22xx\2500\2015\WFE 5th Add\ot2500-2015 WFE5 RVW1.doc Utility Plan (Sheet C4.1) 1) Show the existing hydrants along Quantrelle Ave. 2) Hydrant coverage is insufficient. Another hydrant is needed in the NE corner of the building. We suggest connecting to the existing watermain at the tee near the NW corner of the building and extending the waterline to the east to provide this hydrant. 3) 900 bends are not permitted. A combination of (2) 45° bends is required. 4) How is the "Warping" the curb around the existing sanitary sewer manhole to be achieved? We suggest a larger radius on the curb. 5) The sanitary sewer has been stubbed to the east of the existing manhole. This line shall be extended to the east and the service from the building shall flow to this new manhole. Details (Sheet C8.1— 8.2) 1) Provide Otsego Standard Plates. The latest version of the Otsego Engineering manual is available at http://www.ei.otsego.mn.us/vertical/sites/%7B5E9EA6DA-857D-4088-B3 96- lEBOF2DBA26D%7D/uploads/Otsego_Engineering_Manual NEW 2013(1).pdf 2) All rip rap shall be articulated block or approved equal per Otsego Standard Plates. 3) The pavement section shall be per a geotechnical engineers recommendation. Architectural Plans (Sheet A1.1 -AM) 1) No comments Landscape Plan (Sheet L2.1 - L2.2) 1) No comments HYDROLOGY/STORMWATER 1) The storm sewer for the Waterfront Commons III drains to the Regional Pond to the East. It is anticipated that there is sufficient vertical fall from through the site and to the Pond for the storm water runoff to be properly conveyed. Storm sewer and inlet spread calculations shall be provide prior to final plan approval SUMMARY AND/OR RECOMMENDATION We recommend approval contingent upon the above comments being addressed. PAGE 6 S:\Municipal\Aotsego22xx\2500\2015\WFE 5th Add\ot2500-2015 WFE5 RVW1.doc