DEPARTMENT INFORMATION
Request for
City Council Action
ORGINATING DEPARTMENT:
REQUESTOR:
MEETING DATE:
Utilities
City Utilities Manager
November 9, 2015
Neidermeier
PRESENTER(s):
REVIEWED BY:
ITEM #:
Consent Agenda
Finance Director Flaherty
3.9A
AGENDA ITEM DETAILS
RECOMMENDATION:
Staff recommends approval of payment in the amount of$62,219.00 for the Lift Station #3 Improvement
Project and Well #5 Variable Frequency Drive addition to Total Control Systems Inc.
ARE YOU SEEKING APPROVAL OF A CONTRACT?
IS A PUBLIC HEARING REQUIRED?
No
No
BACKGROUND/JUSTIFICATION:
The 2015 Capital Improvement Plan includes a Utility project to increase pumping capacity at Lift Station
#3 (Project # UTIL-12-075). The Lift Station serves the growing population in the West Sanitary District
conveying all its wastewater to the West Wastewater Treatment Facility and is anticipated to reach
capacity in 2016.
The Sewer Fund allocated $85,000 dollars in 2015 to increase Lift Station #3 capacity. Project progress
includes the installation of an existing 40 horsepower submersible pump, the addition of a control
cabinet and three variable frequency drives, air conditioner and electrical services. The request of
$49,677.00 is in line with construction progress and project price of $74,177.00.
Total Control Systems Inc. is also requesting payment for the installation of Well #5 Variable Frequency
Drive of $12,542; the addition was a change order to replace the failed soft start for the well approved
at the September Public Works Subcommittee meeting. Well #5 is one of two production wells used for
the West Water System Supply. The soft start for the well has met useful life expectations.
Instrumentation, startup, manuals and project completion is on track for the November 201h deadline.
City staff recommends payment.
SUPPORTING DOCUMENTS: (X) ATTACHED
• Invoice 7404
MOTION: (Please word motion as you would like it to appear in the minutes.)
Motion to approve payment to Total Control Systems, Inc. in the amount of $62,219.00 for the Lift
Station No. 3 Project UTIL-12-075 and Well 5 Variable Frequency Drive Installation.
BUDGET INFORMATION
FUNDING: BUDGETED: (X) YES
601— Water Utilities Fund $12,542
602 — Wastewater Utilities $49,677
ACTION TAKEN
SY S �T EI'vTSINC
38841 Nyman Drive NE
P.O. Box 40
Stanchfield, MN 55080-0040
ehl To
City of Otsego
Kurt Neidermeier
13400 90th ST NE
Otsego, MN 55330
Quantity
Description
Date
10/20/2015
Invoice No.
7404
P.O. No. Terms; Projec----------------
Kurt-Project SLS3 Net 30
1 Progress billing for the Otsego LS #3 Modifications Project,
Including the LS Control Panel, Electrical Construction,
1 Well #5 Change Order #1 PO 2769
Rate
49,677.00
12,542.00
Amount
49,677.00
12,542.00
Phone: 320 396-4442