Loading...
09-12-95 PRMEMO TO: Otsego Parks Commission FROM: Merland Otto DATE: September 12, 1995 STATUS OF ISTEA GRANTS FY 96 On September 5th, we received Mn/DOT review comments on the Project Memorandum (submitted 2/16/95). The comments are not extensive but do require a revised schedule, a description of design elements, and change to metric units. After revising, ten copies of the Project Memorandum need to be re -submitted. I also spoke with Mike Tardy, District State Aid Engineer with MnDot, to get a better idea of cash flow for budget purposes: Salient points are: Sometime around June 1, 1996 Mn/DOT would request the City's share for the project ($61,525.). • Mn/DOT administers project funds. • Mn/DOT wants the project bid as one, not two projects. • Land would need to be secured prior to award of contract. • They anticipate a policy change in next 2-3 months that allows for costs within MSA ROW's for Bike Trail Construction. Engineering fees for the ISTEA project that can be attributed to MSA improvement could then be funded with MSA funds. Roughly speaking this would be about half of the engineering costs (est. @ $37,800 in application). Quandary The FY '96 project of $246,100 includes a Federal share of $184,575 plus: 61,525. Local share of construction 23,500. Land Acquisition 49,220. *Engineering (20% of construction) $134,245. Total City Cost * Approximately 1/2 could be funded w/MSA funds. The City does not, at this time, have $134,000 to fund the project. Options 1) No build Alternative - withdraw from grant program - give up $184,000. In all likelihood would probably lose FY '98 ISTEA project since it builds on FY '96. 2) Bond for local share FY 96, FY 98 projects. 3) Defer project for FY 97 letting, assuming money would be available in early 1997. Project would need to be completed by October 1, 1997. FY '98 then immediately follows. 4) Revise project to one of the following options: Existing Total Construction Project: $246,100. ISTEA 184, 575. City Construction Costs 61,525. Engineering Fees (20%) 49,220. Land 23,500. Total City Costs: $134,245. A) Reduce construction by cost of Engineering in original Application. $246,100 - 37,800 = $208,300. ISTEA FUNDS 156,225. City Construction Costs 52,075. Engineering Fees (20%) 41,660. Land 23,500. Total City Costs: $117,235. B) Reduce Project by reducing original City cost of $61,525 by $37,800 originally projected engineering costs. City share would then be $23,725. If this is 25% of Project construction, the project would be $94,900. This would be less than the minimum $100,000 project and would NOT be a viable option. C) Use MSA Funds for engineering and meet obligations of total construction (existing project of $246,100). Local share outside of MSA funding would be approximately $134,250 - 25,000 = $109,250. D) Use MSA funds for engineering and meet obligations of reduced project (option A - project of $208,300). City share outside of MSA funding would be approximately $117,235 - 25,000 = $92,235. A copy of the project schedule excepted from the Project Memorandum is attached. Action Required: The City Council needs to make a decision on whether and how to meet the City's share of the project. If appropriate, the project schedule needs to be revised prior to re -submittal of the Project Memorandum. The Project Memorandum needs final approval prior to beginning negotiations for land acquisition. The PRC should make a recommendation to City Council for their consideration. This application was for $317,700 with $238,275 Federal and $79,425 City share plus engineering and land acquisition. File: OT73.MEM V. SCHEDULING AND PROJECT MANAGER Schedules The following project schedule is proposed: ACTIVITY Project Memorandum PS&E Land Acquisition for Offroad Trails (Phase II)** Letting Date Phase I Construction Start Substantial Completion Phase I Phase II Construction Start Substantial Completion Phase II Construction Completion *Dependent on ISTEA funding availability. **This can be accelerated to single phase if necessary. Project Manager DATE February 14, 1995 May 15, 1995 September 15, 1995 June 30, 1995* July 30, 1995* September 15, 1995 July 15, 1996 October 30, 1996 November 15, 1996 Name : Merland Otto Title : Landscape Architect Address : Hakanson Anderson Associates, Inc. 222 Monroe Street Anoka, MN 55303 Phone : (612) 427-5860 3 9/30 CITY OF TSEGO 8899 Nashua Avenue N.E. ON THE GREAT RIVER ROAD (612) 441-4414 Elk River, MN 55330 Fax: (612) 441-8823 September 27, 1995 lr.John Bolduc 9070 Ochoa Circle NE Otsego, ININ 55330 RE: YOUR LETTER OF RESIGNATION FROM THE PARK AND RECREATION COMMISSION Dear .John: This letter is to thank you for your interest in the Park and Recreation Commission and for your time to apply and interview for the position. The City Council considered your letter at the Council Meeting of September 25, 1995 and approved your resignation. The Council would like to thank you personally for being a civic minded citizen and if your schedule permits, please consider applying for a position on one of our Boards or Commissions at a future date. Sincerely, CITY OF OTSEGO Norman F Freske, Mayor eb CC: Mayor and Council Otsego Boards and Commissions Otsego Staff Professional Staff File