ITEM 3.5A Street Improvement Project 14-01 14-020
oull.'= o
MINNESOTA V
DEPARTMENT INFORMATION
Request for
City Council Action
ORIGINATING DEPARTMENT:
REQUESTOR:
MEETING DATE:
Public Works
City Engineer Wagner
January 25, 2016
PRESENTER(s):
REVIEWED BY:
ITEM #:
City Engineer Wagner
City Administrator Johnson
3.5A
Finance Director Flaherty
AGENDA ITEM DETAILS
RECOMMENDATION:
Staff recommends approval of payment in the amount of $275,505.86 for the 70th Street/CSAH 37
Improvement Project, City Project No. 14-01 & 14-02 to Fehn Companies, Inc.
ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED?
No No
BACKGROUND/JUSTIFICATION:
This payment is being made for work completed through December 315t, 2015. Fehn Companies and their
subcontractors have completed all the clearing and grubbing, bituminous removal, temporary traffic
signage, electric lighting system, trail subgrade preparation, all concrete work has been completed and
the first 2 lifts of bituminous have been placed. Temporary striping and permanent signage has been
completed and the entire project was open to traffic by November 7th, 2015 as required by the contract
and Supplemental Agreement #2.
All work has been completed for the year and the project will resume in the Spring of 2016. The only
things that remain to be completed will be paving the final lift for the street, some minor trail base
preparation, paving the trail, and making sure vegetation has been established.
This pay estimate (#5) includes Change Order #2 and Minor Work Order #3. Change Order #2 includes
monetary deductions in the amount of $5,141.91 for the bituminous failing to meet required densities in a
couple areas. Minor Work Order #3 totals $10,618.76 and includes many various extra work items
necessary to complete the project as contemplated and within the allotted time frame. Some of these
items include extra time and time and material to work around existing live utilities within the road bed
that could not be relocated without disturbing service to many residents and businesses. Other items
included adjusting, widening, moving driveways or field accesses, mailboxes, and storm sewer. All these
items were tracked by and being paid for as Force Work (i.e. tracking time and materials). Please refer to
the Minor Work Order #3 for full descriptions and cost breakdowns of individual items.
The City portion of this Pay Estimate is $173,979.58 with the County portion being $101,526.29.
SUPPORTING DOCUMENTS: x ATTACHED Ei NONE
List: Pay Estimate No. 5
Pay Estimate No. 5 Cost Breakdown
Change Order No. 2
Minor Work Order No. 3
POSSIBLE MOTION
Motion to approve payment to Fehn Companies, Inc. in the amount of $275,505.86 for the 70th
Street/CSAH 37 Improvement Project, City Project No. 14-01 & 14-02.
BUDGET INFORMATION
mwmwG: auoesTEo xYEG
K4SASFunds
Region 7VVFederal Funds omo
County Reimbursement |
ACTION TAKEN
oAPPROVED AoREQUESTED oDENIED oTaoLso oOTHER (List changes)
PAY ESTIMATE #5
CITY OF OTSEGO
70th Street/CSAH 37 Improvement Project
S.P. 217-112-002 and S.P. 086-637-033
Date: January 18, 2016
Honorable Mayor & City Council
City of Otsego
13400 90th Street NE
Otsego, MN 55330
RE: 70th Street/CSAH 37 Improvement Project
SP 217-112-002 and SP 086-637-033
Contractor: Fehn Companies, Inc.
Award Date: May 11, 2015
Completion Date: June 15, 2016
Dear Honorable Mayor and Council Members:
The following work has been completed on the above -referenced project by Fehn Companies, Inc.
Bid Schedule "A"
OWNER
ITEM
NO.
Mn/DOT
SPEC. NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
1
2021.501
Mobilization
1.00
LS
$89 234.00
$ 89,234.00
0.75
$ 66.925.50
2
2041.610
Trainees
500
HOURS
$1.00
$ 500.00
400
$ 400,00
3
2101.501
Clearing
3.2
ACRE
$2,5%00
$ 8,160.00
3
$ 8,160.00
4
2101.506
Grubbing
3.2
ACRE
$2 550.00
$ 8,160.00
3
$ 8,160.00
5
2104.501
Remove Curb & Gutter
435
LF
$3.13
$ 1,361.55
157
$ 491.41
6
2104.501
Remove Pipe Culverts
520
LF
$12.24
$ 6,364.80
863
$ 10,563.12
7
2104.505
Remove Bituminous Pavement
14548
SY
$1.54
$ 22,403.92
14343
$ 22,088.22
8
2104.509
Remove Bollards
2
EACH
1 $750.00 -
$ 1,500.00
2
$ 1,500.00
9
2104.509
Remove Sin
10
EACH
$26.00
$ 260.00
10
$ 260.00
10
2104.513
1 Sawing Bit Pavement Full Depth)
689
LF
$1.50
$ 1,033.50
329
$ 493.50
11
2104.521
Salvage Barbed Wire Fence
250
LF
$3.00
$ 750.00
$
12
2104.523
Salvage Casting
2
EACH
$100.00
$ 200.00
1
1 $ 100.00
13
2105.501
Common Excavation P
39992
CY
$4.08
$ 163,167.36
42692
1 $ 174,183.36
14
2105.505
Muck Excavation E
2204
CY
$4.31
$ 9,499.24
2204
$ 9,499.24
15 1
2105.521 1
Granular Borrow LV
180
CY
$10.66
$ 1,918.80
151
$ 1,607.00
16
2105.523
Common Borrow LV
13098
CY
$3.60
$ 47,152.80
13098
$ 47,152.80
17
2105.535
Salvaged Topsoil From Stockpile LV
32622
CY
$1.98
$ 64,591.56
24467
$ 48,444.66
18
2105.535
Salvaged Topsoil in Stockpile EV
48809
CY
$1.41
$ 68,820.69
48809
$ 68,820.69
19
2211.501
Aggreqate Base Class 3 or 4
40992
TON
$6.39
$ 261,938.88
37688
$ 240,826.32
20
2211.501
Aggregate Base Class 5 Mod
33142
TON
$11.34
$ 375,830.28
34949
$ 396,321.66
21
2221.501
Shoulder Base Aggregate Class 2
1254
TON
$28.44
$ 35,663.76
455
$ 12,951.58
22
2232.501 1
Mill Bituminous Surface 1.5"
145
SY
$5.17
$ 749.65
$
23
2357.502
Bituminous Material For Tack Coat
3431
GAL
$2.18
$ 7.479.58
2800
$ 6,104.00
24
2360.501
Type SP 9.5 Wearing Course Mixture 3,C
4801
TON
$64.97
$ 311.920.97
589
$ 38,267.33
25
2360.501
Type SP 12.5 Wearing Course Mixture 2,8
2116
TON
$58.56
$ 123,912.96
118
$ 6.910.08
26
2360.502
Type SP 12.5 Non Wear Course Mixture 3,C
12745
TON
$57.96
$ 738,700.20
11568
$ 670,481.28
27
2411.507
Concrete Flume
11
EACH
$332.00
$ 3,652.00
9
$ 2,988.00
S:Wun1cipaltA0TSEG0l388\(3) ConstructiontPay Estimates and CO's\OT388 PE#5.xlsx
PAY ESTIMATE #5
CITY OF OTSEGO
70th Street/CSAH 37 Improvement Project
S.P. 217-112-002 and S.P. 086-637-033
Bid Schedule "A"
OWNER
ITEM
NO.
Mn/DOT
SPEC. NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
I UNIT PRICE
CONTRACT
I AMOUNT
USED TO
DATE
EXTENSION
28
2501.515
12" RC Pipe Apron
5
EACH
$510.00
$ 2,550.00
6
$ 3,060.00
29
2501.515
15" RC Pie Apron
6
EACH
$510.00
$ 3,060.00
5
$ 2,550.00
30
2501.515
18" RC Pipe Apron
5
EACH
$510.00
$ 2,550.00
5
$ 2,550.00
31
2501.515
21" RC Pi e A ron
3
EACH
$510.00
$ 1,530.00
3
$ 1,530.00
32
1 2501.515
24" RC Pipe Apron
6
EACH
$510.00
$ 3,060.00
6
$ 3,060.00
33
2501.515
27" RC Pipe Apron
1
EACH
$510.00
$ 510.00
1
$ 510.00
34
2501.515
30" RC Pipe Apron
1
EACH
$612.00
$ 612.00
1
$ 612.00
35
2501,515
48" RC Pipe Apron
2
EACH
$1,224.00
$ 2,448.00
2
$ 2,448.00
36
2501.525
28" Span RC Pipe -Arch Apron
2
EACH
$510.00
$ 1,020.00
2
$ 1.020.00
37
2501.561
18" RC Pie Culvert Design 3006 CL V all depths)
754
LF
$30.60
$ 23 07240
648
$ 19,828.80
38
2501.561
24" RC Pie Culvert Design 3008 CL III all depths)
136
LF
$37.00
$ 5,032.00
136
$ 5,032.00
39
2501.561
48" RC Pie Culvert Design 3006 CL III all depths)
148
LF
1 $133.00
$ 19 684.00
128
$ 17,024.00
40
1 2501.569
15" RC Safety Apron
2
EACH
$612.00
$ 1,224.00
2
$ 1,224.00
41
2501.569
18" RC Safety Apron
34
EACH
$612.00
$ 20 808.00
30
$ 18 360.00
42
2501.569
24" RC Safety Apron
3
EACH
$612.00
$ 1,836.00
1 3
$ 1,836.00
43
2501.569
30" RC Safety Apron
1
EACH
$918.00
$ 918,00
1
$ 918.00
44
2501.573
Install Culvert Marker
31
EACH
1 $60.00
$ 1,860.00
38
$ 2,280.00
45
2501.602
Outlet Structure
5
EACH
$2,550.00
$ 12,750.00
5
$ 12 750.00
46
2501,602
Safety Grate for 24" RCApron
3
EACH
$1.224.00
$ 3,672.00
$
47
2501.602
Safety Grate for 30" RCApron
1
EACH
$918.00
$ 918.00
1
$ 918.00
48
2501.602
Trash Guard for 24" Pipe Apron
6
EACH
$612.00
$ 3,672.00
2
$ 1,224.00
49
2501.602
Trash Guard for 27"Pi eA ron
1
EACH
$612.00
$ 612.00
1
$ 612.00
50
2601.602
Trash Guard for 30" Pipe Apron
1
EACH
$612.00
$ 612.00
1 1
$ 612.00
51
2501.602
Trash Guard for 48" Pipe Apron
2
EACH
$1,224.00
$ 2,448.00
2
$ 2,448.00
52
2501.602
Trash Guard for 28" Span Apron
2
EACH
$612.00
$ 1,224.00
$
53
2502.501
4" Precast Concrete Headwall
64
EACH
$204.00
$ 13,056.00
46
$ 9,384.00
54
2502.541
4" Perf PVC Pipe Drain
2305
LF
$6.12
$ 14,106.60
2035
$ 12 454.20
55
2502.541
8" Perf PVC Pipe Drain
450
LF
$14.28
$ 6.426.00
543
$ 7,754.04
56
2503.541
28" Span RC Pipe -Arch Sewer CL III-
106
LF
$71.40
$ 7,568.40
106
$ 7,568.40
57
2503.541
12" RC Pipe Sewer Design 3006 CL V all depths)
101
LF
$32.64
$ 3,296.64
137
$ 4,471.68
58
2503.541
15" RC Pipe Sewer Design 3006 CL V all depths)
1917
LF
$34.68
$ 66,481.56
1935
$ 67.105.80
59
2503.541
18" RC Pipe Sewer Design 3006 CL V all depths)
620
LF
$34.68
$ 21.501.60
131
$ 4,543.08
60 1
2503.541
21" RC Pipe Sewer Design 3006 CL III all depths)
283
LF
$36.72
$ 10,391.76
791
$ 29,045.52
61 1
2503.541
24" RC Pipe Sewer Design 3006 CL III all depths)
202
LF
$38.76
$ 7,829.52
199
$ 7,713.24
62
2503.541
27" RC Pipe Sewer Design 3006 CL III all depths)
77
LF
$45.90
$ 3,534.30
81
$ 3,717.90
63
2503.541
30" RC Pipe Sewer Design 3006 CL III all depths)
419
LF
$51.00
$ 21,369.00
414
$ 21.114.00
64
2506.501
Construct Drainage Structure Design 484020
38.5
LF
$612.00
$ 23,562.00 1
62.4
$ 38,188.80
65
2506.501
Construct Drainage Structure Design 544020
13.6
LF
$918.00
$ 12,484.80 1
13.6
$ 12,484.80
SAMun1cipaNA0TSEG0\388\(3) ConstmctionTay Estimates and CO's\OT388 PE#5.xlsx
PAY ESTIMATE #5
CITY OF OTSEGO
70th Street/CSAH 37 Improvement Project
S.P. 217-112-002 and S.P. 086-637-033
Bid Schedule "A"
OWNER
ITEM
NO.
Mn/DOT
SPEC. NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
I UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
66
2506.501
Construct Drainage Structure Design 6OA020
12.2
LF
$714.00
$.. 8,710.80
1 t9
$ 8,496.60
67
2506.501
Construct Drainage Structure Design 66AO20
4.6
LF
$816.00
$ 3,753.60
4.6
$ 3,753.60
68
2506.501
Construct Draina a Structure Design H
16.6
LF
$408.00
$ 6,772.80
,0
$
69
2506.501
Construct Drainage Structure Design N
41.9
LF
$408.00
$ 17,095.20
34.9
$ 14,239.20
70
2515.503
Articulated Interlocking Block Open Cell Type A
319
SY
$110.00
$ 35 090.00
293
$ 32,230.00
71
2521.501
4" Concrete Walk
9602
SF
$3.11
$ 29,862.22
8012
$ 24,916.08
72
2531.501
Concrete Curb & Gutter Design B424
4601
LF
$13.00
$ 59,813.00
4661
$ 60,593.00
73
2531.501
Concrete Curb & Gutter Design B418
3698
LF
$11.30
$ 41.787.40
3698
$ 41,787.40
74
2531.501
Concrete Curb & Gutter Design S518
444
LF
$15.38
$ 6,828.72
444
$ 6,828.72
75
2531.507
6" Concrete Driveway Pavement
535
SY
$39.72
$ 21,250.20
543
$ 21,567.96
76
2531.618
Truncated Domes
48
SF
$36.72
$ 1,762,56
$
77
2540.602
Install Mail Box Support
12
EACH
1 $143.00
$ 1,716.00
12
$ 1,716.00
78
2545:501
Electric Light System
1
LS
$73 909.00
$ 73,909.00
1.00
$ 73,909.00
79
2563.601
Traffic Control
1
LS
$7,548.00
$ 7,548.00
.8
$ 5,736.48
80
2564.531
1 Sign Panels, Type C
334
SF
$33A5
$ 11,072.10
376
$ 12,463.74
81
2573.502
Silt Fence, Type MS
22650
LF
$2.34
$ 53.001.00
21058
$ 49,275.72
82
2573.530
Storm Drain Inlet Protection
53
EACH
$153.00
$ 8,109.00
33
$ 5.049.00
83
2573.533
Sediment Control Log Type Straw
640
LF
$2.04
$ 1,305.60
1300
$ 2,652.00
84
2573.535
Stabilized Construction Exit
1
LS 1
$1,500.00
$ 1,500.00
.66
$ 990.00
85
2574,508
Fertilizer Type 1
8150
LBS
$0.77
$ 6,275.50
8000
$ 6,160.00
86
2575.501
Seeding
16.3
ACRE
$102.00
2.60
16
$ 1632.00
87
2575.502
SeedingMixture - 25-141
786
LBS
$4.08
6.88
800
$ 3,264.00
88
2575.502
SeedingMixture - 25-151
330
LBS
$3.26
5.80
r$5,049.00
300
$ 978.00
89
2575.511
Mulch Material Type 1
33
TON
$153.00
28
$ 4,238.10
90
2575.523
Erosion Control Blanket - Category 2
10249
SY
$1.22
$ 12 503.78
13972
$ 17,045.84
91 1
2580.601 1
Interim Pavement Markin - Paint
1
LS
$8,740.00
$ 8740.00
1
$ 8,740,00
92
2582.501
Pavement Message Left Arrow - Paint
10
EACH
$71.40
$ 714.00
$
93
2582.501
Pavement Message (Right Arrow - Paint
6
EACH 1
$71.40
$ 428.40
$
94
2582.501
Pavement Message Thru Arrow - Paint
9
EACH
$71.40
$ 642.60
$
95
2582.501
Pavement Message Yield - Paint
3
EACH
$112.20
$ 336.60
$
96 1
2582.502
4" Solid Line White - Paint
24500
LF
$0.09
$ 2,205.00
$
97
2582.502
8" Solid Line White - Paint
236
LF
$0.09
$ 21.24
$
98
2582.502
8" Dotted Line White - Paint
171
LF
$1.53
$ 261,63
$
99
2582.502
12" St02 Line White - Paint
56
LF 1
$2.55
$ 142.80
$
100
2582,502
4" Solid Line Yellow -Paint
1501
LF
$0.09
$ 135.09
$
101 1
2582.502 124P
Solid Line Yellow - Paint
547
LF
$2.45
$ 1,340.15
$
102 1
2582.502
4" Double Solid Line Yellow - Paint
13370
LF
$0.17
$ 2,272.90
$
S:1Municipa1tA0T8EG0\3881(3) ConstmctiomPay Estimates and CUMOT388 PEtll5.xlsx
PAY ESTIMATE #5
CITY OF OTSEGO
70th Street/CSAH 37 Improvement Project
S.P. 217-112-002 and S.P. 086-637-033
Bid Schedule "A"
OWNER
ITEM
NO.
Mn/DOT
SPEC. NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
103
2582.603
Pavement Marking Special - Paint
61
LF
1 $4.59
$ 279.99
$
Total Bid Schedule "A" $ 3,122,398.24 $ 2,579,914.43
Change Order No. 1
ITEM
NO.
SPEC NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
1
2104.505
Additional Bituminous Pavement Removed
791
CY
$10.08
$ 7,973.28
791
$ 7,973.28
2
2021.501
Mobilization
3
EACH
$412.50
$ 1,237.50
3
$ 1237,50
3
Relocate Special Sin
2
EACH
$605.00
$ 1.210.00
1
$ 505.00
Signs Installed on 6123115
4
2563.601
48" Road Closed Ahead
85
PER
DAY
$0.75
$ 63.75
122
$ 91.50
5
2563.601
48" Detour Ahead
85
PER
DAY
$0.75
$ 63.75
122
$ 91.50
6
2563.601
(8) Detour Guidance Assemblies + Portable Supports (10.2
SF/Each @ $0.16 SF/Da + $0.47 support/day)
85
PER
DAY
$16.82
$ 1.429.70
122
$ 2,052.04
7
2563.601
(3) Type III Barricades 0 $1.53//Each/Day)
85
PER
DAY
$4.59
$ 390.15
122
$ 559.98
8
2563.601
(6) Type A Flasher (o? $0.25//Each/Da
85
PER
DAY
$1.50
$ 127.50
122
$ 183.00
9
2563.601
(4) 60" x 30" Road Closed Miles Ahead Sign (12.5 SF/Each
0 $0.16 SF/Day)
85
PER
DAY
$8.00
$ 680.00
122
$ 976.00
10
2563.601
(2) 48" x 18" Detour Sign (6 SF/Each @ $0.16 SF/Day)
85
PER
DAY
$1.92
$ 163.20
122
$ 234.24
Signs Installed on 6130115 - -
11 1
2563.601
(9) Detour Guidance Assemblies +Portable Supports (10.2
SF/Each a $0.16 SF/Day+ $0.47 support/day)
78
PER
DAY
$18.92
$ 1,475.76 1
115
$ 2,175.80
Signs Installed on 7/2/15
12 1
2563.601
(2) 48" Road Closed Sign ( $0.75 per sign/day)
75
PER
DAY
$1.50
$ 112.50
113
$ 169.50
13
2563.601
(3) 48" Detour Ahead Sin ( $0.75 persign/day)
75
PER
DAY
$2.25
$ 168.75
113 .
$ 254.25
14
2563.601
(19) Detour Guidance Assemblies + Portable Supports
00.2 SF/Each (a) $0.16 SF/Da +$0.47 support/day)
75
PER
DAY
$39.94
$ 2,995.50
113
$ 4,513.22
15
2563.601
(2) Special 84" x 48" Signs (28 SF/Each @ $38.59 SF)
56
SF
$38.59
$ 2,161.04
56
$ 2,161.04
Total Change Order No. 1 $ 20,262.38 $ 23,277.85
Minor Work Order No. 1 - LED Hahtinn
ITEM
NO.
SPEC NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
1
2545.501
Electric Light System
-1
LS
$73,909.00
$ (73,909.00)
-1
$ (73.909.00)
2
2545.501
1 Electric Light System
1
LS
$75,830.38
$ 75,830.38
1.00
$ 75,830.38
Total Minor Work Order No.1 $ 1,921.38 $ 1,921.38
SuoDlemental Agreement No. 1
SPEC NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
M13
2105.505
MuckExcavtion EV
26636
CY
$4.31
$ 114,801A6
36689
$ 158,129.59
2105.522
Select Granular Borrow LV
9500
CY
$10.44
$ 99,180.00
8329
$ 86,954.76
2105.523
Common Borrow LV
14894
1 CY
$3.60
$ 53,618.40
24328
$ 87,580.80
4
2105.604
Geotextile Fabric, Type 5
1600
SY
1 $4.50
$ 7,200.00
$
Total Supplemental Agreement No. 1 $ 274,799.56 $ 332, 665.15
S:WtuniciparA0TSEG0\388\(3) Construction\Pay Estimates and CO's\OT388 PE#5.xlsx
PAY ESTIMATE #5
CITY OF OTSEGO
70th Street/CSAH 37 Improvement Project
S.P. 217-112-002 and S.P. 086-637-033
OWNER
ITEM
NO.
I SPEC NO.
I ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
1
2211.501
JAggregate Base Class 5 Mod
1500
1 TON
1 $11.34
$ 17,010.00
1508
$ 17,100.72
2
2451.609
1 Crushed Rock 3" RE de
3 )o
I TON
1 $38.93
$ 11,679.00
1 323
$ 12,569.33
Total Work Order No. 2 $ 28,689.00 $ 29,670.05
ITEM
NO.
I SPEC NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
I UNIT
CONTRACT
UNIT PRICE
CONTRACT
AMOUNT
USED TO
DATE
EXTENSION
1
2360.501 IType
SP 9.5 Wear Course Mixture 3,C
1
LS
1 -$4,376.56
$ (4,376.56)
1
$ (4,376.56)
2
2360.502 IType
SP 12.5 Non Wear Course Mixture 3,C
1
LS
1 -$765.34
$ (765.34)
1
$ (765.34
Total Change Order No. 2 $ (5,141.90) $ (5,141.90)
R.A:TRT,, Tlr-1l.\y1TS.T Rr.VM
ITEM
NO.
SPEC NO.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT
CONTRACT
UNIT PRICE
CONTRACT
I AMOUNT
USED TO
DATE
EXTENSION
1
Lowering small utilities: Sta 216+75 to 220+00
1
LS
$1 980.62
$ 1,980.62
1
$ 1,980.62
2
Lower small utility crossings: Sta 216+50, 181+90,
& 192+90
1
LS
$1,320.51
$ 1,320.61
1
$ 1,320.51
3
Excavate and Backfill for conduit Crossing under
48" culvert
1
LS
$621.86
$ 621.86
1
$ 621.86
4
Add field access: Sta 231+50
1
LS
$504.90
$ 504.90
1
1 $ 504.90
5
Raise field access and widen: Sta 159+00
1
LS
$1,852.42
$_ 1,852.42
1
$ 1,852.42
6
Raise trailgrade: Sta 232+90 to 234+40
1
LS
$B96.97
$ 896.97
1
$ 896.97
7
Change Ditch and relocate field access; Sta 162+00
1
LS
$352.33
$ 352.33
1
$ 352.33
6
Relocate field access: Sta 225+00
1
LS
$504.90
$ 504.90
1
1 $ 504.90
9
Add berm:Sta 22+75
1
LS 1
$159.20
$ 159.20
1
$ 159.20
10
Revise driveway: Sta 191+50
1
LS
$405.05
$ 405.05
1
$ 405.05
11
Relocate Mailbox: Sta 223+00
1
LS
$220.00
$ 220.00
1
$ 220.00
12
Revise storm sewer: Ste 214+00
1
LS
$1,800.00 1
$ 1,800.00 1
1 1
$ 1,800.00
Total Work Order No. 2
$ 10,618.76
$
10,618.76
Bid Schedule "A"
$ 3,122,398.24
$
2,579,914.43
Change Order No. 1
$ 20,262.38
$
23,277.86
Minor Work Order No. 1
$ 1,921.38
$
1,921.38
Supplemental Agreement No. 1
$ 274,799.56
$
332,666.15
Minor Work Order No. 2
$ 28,689.00
$
29,670.05
Change Order No. 2
$ (5,141.90)
$
(5,141.90)
Minor Work Order No. 3
$ 10,618.76
$
10,618,76
TOTAL
$ 3,453,537.42
TOTAL WORK COMPLETED TO DATE
$
2,972,925.72
LESS 5% RETAINAGE:
$
148,646.29
ERODIBLE ACREAGE WITHHOLDING ($3,000/ DISTRUBED ACRE)
$
48,900.00
LESS PAY ESTIMATE NO.1
$
457,681.93
LESS PAY ESTIMATE NO.2
$
445,805.94
LESS PAY ESTIMATE NO.3
$
878,304.56
LESS PAY ESTIMATE NOA
$
718,081.15
WE RECOMMEND PAYMENT OF: $ 275,505.86
S:\Mun1c1paM0TSEG0\3881(3) Constmcflon\Pay Estimates and WsW388 PE#5.x1sx
PAY ESTIMATE #5
CITY OF OTSEGO
70th Street/CSAH 37 Improvement Project
S.P. 217-112-002 and S.P. 086-637-033
APPROVALS:
CONTRACTOR: FEHN COMPANIES, INC.
Certification by Contractor: I certify that all items and amounts are correct for the work completed to date.
Title: Date
ENGINEER: HAKA ON ANDERSON ASSOCIATES, INC.
Certification Mriginee We ommend payme and quantities as shown.
Signed: �L
Title: Date
OWNER: CITY OF OTSEGO
OWNER
S:V,Aunicipa1\A0TSEG0\388\(3) Construction\Pay Estimates and CUMOT388 PE#5.xlsx
STATE AID FOR LOCAL TRANSPORTATION
CHANGE ORDER
Rev.July 2010
Page 1 of 1
SP 217-112-002 & 086-637-033 Minn. Proj. No. STPM 8615 (153) CO No. 2
Project Location: CSAH 37/70th Street, Otsego, MN
Local Agency: City of Otsego
Local Project No. 14-01 & 14-02
Contractor: Fehn Companies
Contract No.
Address/City/State/Zip: 5050 Barthel Industrial Dr, Albertville, MN 55301
Total Change Order Amount $-$5,141.91
Table 2360-22 of Special Provisions 2360 and Table 2360-23 of MnDOT Standard
Specifications 2360, Plant Mixed Asphalt Pavement provides for reduced payment for
bituminous pavement not meeting minimum densities. Bituminous lot densities were tested per
MnDOT 2360.D. and the bituminous coring testing results are located in the Engineer's Project
File. The above mentioned tables indicate that the Contractor shall receive reduced payments in
the amount of $5,141.91 for pavement placed during the 2015 construction season.
Make disincentive payment as a backsheet item as follows:
Estimate Of Cost: (Include any increases or decreases in contract items, any negotiated or force account items.)
•}Group/Funding
+ or—
+ or —
Category
Item No.
Description
Unit
Unit Price
Quantity
Amount $
1
2360.502
Type SP 12.5 Non Wear
Course Mixture (3,C)
LS
-$3,941.63
1
-$3,941.63
3
2360.502
Type SP 12.5 Non Wear
Course Mixture (3,C)
LS
-$434.93
1
-$434.93
1
2360.501
Type SP 9.5 Wear
Course Mixture (3,C)
LS
-$252.56
1
-$252.56
3
2360.501
Type SP 9.5 Wear
Course Mixture (3,C)
LS
-$512.78
1
-$512.78
Net
Change for Change Order #21
-$5,141.90
Approved by Project Engineer: Date:
Print Name: / eFiv r- a.ro 1/ Phone:
Approved by Contractor:
Print Name:
Phone:
Date:
Distribution: Project Engineer (Original), Contractor (copy), DSAE (copy for funding review)
DSAE Portion: The State of Minnesota is not a participant in this contract. Signature by the
District State Aid Engineer is for FUNDING PURPOSES ONLY and for compliance with State
and Federal Aid Rules/Policy. Eligibility does not guarantee funds will be available.
This work is eligible for: _ Federal Funding _ State Aid Funding _ Local funds
District State Aid Engineer:
Date:
� n
3
o Z
0
Z
r � o
m m �
c c
d c
o -
U U E Q
E
envoi m E
W a
Z 2i0t
Mama
U U) rn
m
0
T=
'O
O O
O O
m O
O O
O O
O O
O O
O
O O
O O
O
O O O
O O
o
0 0 0
0 0
0 0
0
O m 0
0 o
o o
o
o o o
o
o 0 o
o 1-0
Or
j N
O ❑
m O
O O
0 o
o 0
0 0
0
0 0
o 0
0 0
o 0
0 o
o 0
0 0
0 0
0
o
0 0
0 0
0 0
0 0
0
O
0 0 0
o 0 0
0 0
0 0
o
o
O O O
0 o 0
O O
0 0
O O
o 0
O
o
O O m
0 o 0
o 0
o 0
0 0
0 0
0 ...
O m o
0
o
0
0 0 0
0 0 0
0
0
O
oo
O
W
- M--
- to
--m
-
--
--
-
--
--
-
- --
--
-
fig---f9
U3 E.9
Y
E.969 M
E+9 E9
E9 69
ER
69 -0 EA
f9
---
- _
M
O
T
O o
0 0
N 0
0
0
0 0
0 0
0
0 0
0
0
(\I
O
OOO
OOO
0 0 0
m000
0 0
0
o00
0 0 0
000o
0 0
0 0
O
0
O
0 0 7
OO10
0 �j
00
00
0 0
0
00
000Eli
0 N
N
EH
la
U3 EA
EA EA------E9
H3
m:A mm
to-
mm----s3
U3
FA f.9 nj
s?�
m fA
H3
to m mU3
- m-fA
a
co
0
r
o 0
0 0
0 0
0 0
0
0 0
0 0
0
0 0 0
0 0
0
0 0 0
0 0
0 0
0
0 0 0
0 0
0 0
0
0 0 0
0
0 0
0
0
0
U
m m
m m
m m
o 0
0 0
0 0
0 0
0
0 0
0 0
0
0 0 0
0 0
0
0 0 0
0 0
0 0
0
0 0 0
0 0
.T.
0 0 0
0
0
0 0 0
0 0
0
0
0 0
0 0
0 0
0
0 0 0
V
0 0
0 0
0 0
0 0
0
0 0
0 0
0
0 0 0
0 0
0
0 0 o
O o
o 0
0
0 0 0
0 0
0 0
0
0 0 0
0
0 0 0
o M
0
m m
m m
m m
o 0
0 0
0 0
0 0
0
0 0
0 0
0
0 0 0
0 0
0
0 0 0
0 0
0 0
0
0 0 0
0 0
0 0
0
0 0 0
0
0 0 0
o m
m
C
m m
0
N
m
V EO
itl
Or+
m
mmV
NmffJ
mmN
m
rmrO+
+
+ +
+ +
+
+
+ +
+ +
+
m
+ +m+
+ +
mOrmmmm0m+
+
+ + +
+
c.
OmJ
rN
mc2
Voo
N
j
Un ISL
P1Z
u!1 IS L
u!� PUZ
ll!l7sL
u!� is L
31!l PUZ
P! IS
u!l PUZ
P! Pi£
m
t° m
9Z/L/OL
LO
9LOZ/8/0L
9LOZ/6/OL
9LOZ/OL/OL
9LOZ/ZL/OL
9LOZ/£L/OL
9LOZ/bL/OL
❑ a
u
❑
tR
O
O
0
H3
O
O
o
H3
u�
a
-
�
O
O
0
ff3
O
O
0
E9
O
O
0
tH
O
O
0
M
O
O
0
(+9
O
O
0
fF3
O
O
0
69 N3
O
O
0
O
O
0
EA
O
O
0
fA H3
O
O
0
O
O
0
H3
O
o
0
E»
O
O
0
m
O
O
o
m
r
�
ni
N
m
y
o
O
o
EA U3
0
O
0
0
O
0
to
iv
r
Q
7
0
O
o
U3
n
m
��
x
o
u>
�n
o
r
r
r En
�n
En
o
0
o
O
rn
rn
rn
rn
r
r
m
m
rn
C
O
F
U
7
y
o
O
O
0
N
0
m
0
N
N
N
❑
0
C
O
T
•y
d'
O�
t0
d'
r
m
OI
V V
u'l
m 4)
N
m
N
N m
m
m
m
m
7
N
to
N
m
m
W
m
m
m
m
m
O
m
Is
m
O
W
W
W
m
m
m
m
W
Obi
O
Obi
W
E
❑
0
U
u�i
O
w
Y
N
VLL>
LLJ
LO 0m
N
l0 m
LL�
0
mm❑O
l
N
Cj
N
N
N
N
N
N (V
(V
N r
N
N
F
W
O �
•C
J y
>
d'
°�
m
rn
N
rn
V
rn
M
w
M
rn
N
rn
M
rn
rn
V m
m rn
m
rn
N V
rn rn
V
rn
m
rn
V �
rn rn
rn
N
rn
m V
rn rn
�[l N
rn rn
d'
rn
rn
Q
O
w
•y
rN
Ohm
mm
mtOMvmm�m
�O�rmrm'7
V'm��m
rmrnvrmmm
m
V'mm7N�N
mNmm
mO)ry
u1
i
C
y
m m
rn rn
m m
rn rn
m 0
rn rn
m En
rn rn
m m
rn
N m
rn rn
rn
rn rn
rn rn
rn rn rn
rn
rn rn
rn rn rn
m
rn rn
rn rn
rn rn rn
rn
rn rn
rn rn
rn m
rn
rn rn rn
rn
rn rn
rn
rn
c
0
❑
U
N
V
En
m
m
En
m
m
to En
m
En t0
EO EO
in m �n
EO
in
EO m
m
in
m N
V if] `o
m
Etl m
Y
O
N
N N
N
N (V
�-
N
N �,j
N N
N
N
N N
N N
N
r r N
N
N
N
N
r
N N
N
r m
Ill
N cV
cV N �-
m
m
`- N
N
N N
L
r
0
a
x
x
x
x
x
x
x
x
x
x
x
x
x x
x
x
x x
x
x
x
x
x x
x
x
E
0
U
N
�-EN
�- N
.- N
.- N
rN �
N
� N
� N �
N
� N
� N
� N �
N
� N
� N
rN �
N
7 NNmmO2-NmNmOoNNNN
N N
N
N N
N
N
m
V
EO
m
o0££BMNdS
O4£V3MdS
mm rn
m �
Obi N �
Lo
Ln m rn
n m v
STATE AID FOR LOCAL TRANSPORTATION Rev .July2010
WORK ORDER FOR MINOR EXTRA WORK Page 1 of
SP 217-112-002 & 086-637-033 Minn. Proj. No. STPM 8615 (153) WO No. 3
Project Location: CSAH 37/70th Street, Otsego, MN
Local Agency: City of Otsego Local Project No. 14-01 & 14-02
Contractor: Fehn Companies Contract No.
Address/City/State/Zip: 5050 Barthel Industrial Dr, Albertville, MN 55301
- - - ----------------_._----
Total Work Order Amount $ $ 10,618.76
At the direction of the Engineer, the Contractor performed the extra work as described
below necessary to fully complete the Project as contemplated and within the allotted
time frame.
Additional time and different equipment was necessary to dig around and lower the
existing live utilities within the road bed from Station 216+75 to 220+00 and crossings at
Stations 191+90, 192+90 and 216+75. These utility lines were live at the time and
could not be relocated without disturbing service to many residents and businesses.
To aid in the coordination and timing of the installation of the 48" culvert at Sta 156+50
and the small utility joint trench which will pass under this culvert the Contractor
excavated and back filled the joint trench for the small utilities to place their conduits so
the utilities could be placed at a later date without disturbing the structural fill below the
culvert.
Many field entrances and/or driveways were moved, revised, widened, or otherwise
altered at the request of various farmers and residents. Typically these changes were
made to accommodate larger farm equipment than anticipated or provide a different
access point than the original existing location. Changes required include.- re -grading of
the driveways that were already constructed, re -spreading class 5, extending already
placed culverts to and placing additional fill to widen driveways, re -grade driveways to
lessen the slope.
Trail grades were revised in the field to better match the existing residential yard and
not disturb existing landscaping trees. This required regrading a portion of already
prepared subgrade from station 232+90 to 234+40.
Regrade area in front of resident's yard to provide a berm so the water stays contained
within the ditch at station 222+75.
Mailbox at station 223+00 was placed along the south side of CSAH 37 after confirming
with the Postmaster that this would be the proper side. The Postmaster later stated that
they will require the mailbox be placed on the north side at this location.
The storm sewer near 214+00 was revised to eliminate the culvert crossing under the
trail at this location and instead drain the ditch into the storm sewer structure #127 and
towards the south side of the roundabout. This was done to divert as much water from
flowing to the north which has no direct outlet.
The contractor shall provide all equipment, material and labor to perform the necessary
work as determined by the Project Engineer and shown in the Estimate of Cost. All
work was completed in accordance with all the applicable specifications.
STATE AID FOR LOCAL TRANSPORTATION Rev.July2010
WORK ORDER FOR MINOR EXTRA WORK Page 2of3
Payment for this work will be made on a Force Account basis as provided in MnDOT
Specification 1904.4; except
Payment for this Relocation of the Mailbox at Sta 223+00 and revision to the storm
sewer at Sta 214+00 will be made at the negotiated unit prices shown in the Estimate of
Cost in accordance with MnDOT Specification 1904.3.
Exhibit A, attached, is a Force Account Summary showing the labor and equipment
hourly rate breakdowns for the various types of work performed. Exhibit B, also
attached, calculates a Lump Sum costs based on these labor and equipment rates and
is shown in the Estimate of Cost below.
This Work Order does not change Contract Time.
Estimate Of Cost: (Include any increases or decreases in contract items, any negotiated or force account items.)
—Grouffundi
+
ng Category Item No.
Description
Unit
Unit Price Quantity
Amount $
Lowering small
3
utilities from Sta
LS
$1,980.62 j 1
$1,980.62
216+75 to 220+00
1 Lower small utility
1
crossings: Sta
LS
$884.74
1
$884.74
216+50, 181 +90 &
192+90
Lower small utility
3
crossings: Sta
LS
$435.77
1
$435.77
216+50, 181 +90, &
192+90
Excavate and Backfill
1
for conduit Crossing
LS
$621.86
1
$621.86
under 48" culvert
Add field access: Sta
3
LS
$504.90
1
$504.90
� 231+50
Raise field access
1
and widen: Sta
LS
$1,852.42
1
$1,852.42
159+00
Raise trail grade: Sta
1
LS
$896.97
1
$896.97
232+90 to 234+40
Change Ditch and
1
relocate field access;
LS
$352.33
1
$352.33
Sta 162+00
3
Relocate field
LS
$504.90
1
$504.90
access: Sta 225+00
—Add-be rm: Sta 22+75
3
LS
$159.20
1
$159.20
STATE AID FOR LOCAL TRANSPORTATION
WORK ORDER FOR MINOR EXTRA WORK
Rev .July 2010
Page 3 of 3
1
Revise driveway: Sta
LS
$405.05
1
$405.05
191+50
3
Relocate Mailbox:
LS
$220.00
1
$220.00
Sta 223+00
2
Revise storm sewer:
LS
$1,800.00
1
$1,800.00
Sta 214+00
Net Change this Work Order
$10,618.76
"Group/Funding category is required for Federal Aid projects
Due to this change, the contract time: (check one)
(x) Is NOT changed I ( ) May be revised as provided in Mn/DOT Specification 1806
( ) Is Increased by Working Days ( ) Is Increased by Calendar Days
( ) Is Decreased by Working Days ( ) Is Decreased by Calendar Days
Approved by Project Engineer:
Print Name: &rI✓—.1- /-
Approved by Contractor:
Print Name:
Date: AxIlK
Phone: (7n-� yZ7 _ .fAo
Phone:
Date:
Distribution: Project Engineer (Original), Contractor (copy), DSAE (copy for funding review)
DSAE Portion: The State of Minnesota is not a participant in this contract. Signature by the
District State Aid Engineer is for FUNDING PURPOSES ONLY and for compliance with State
and Federal Aid Rules/Policy. Eligibility does not guarantee funds will be available.
This work is eligible for: _ Federal Funding _ State Aid Funding _ Local funds
District State Aid Engineer:
Date:
�
C
U
E
h
N
m
u
W
X0
co
af
a0i
IJ.F
U N
co
CD
�O
(D
O
(D
O
iE
O
Z
w
CO
U
C
O
U
LL
C�
G
U)
I—
Z
O
U
U
Q
w
U
0
LL
(o
N
O
O
4
O
Z
T
U
C
N
Q
(6
0
O
J
Sy
Z co
W a
� U
O
Y
ry
O
i
C
O
U)
N
O o
Z N
� o
Z i N
w r N
w a
w CD
J O
Z O
Z
w m a
:E 0 0
w 0.. �
d a> a
a O
�
Cn U-
U)
N
m
m
o
N
V
O
(O 6
6
N
W
W
N
M
V
(D
m
(o
69 fA
FR
69
69
64
69
ffl
69
O
j o '7
(O
N
1m
(Op
7
m
O
4. r N of
fA 69
N
V3
O
69
6,
EA
611
6m4
V,
I'll
M n
O
M
O
(D
O
fD
O
,F41,
l6
69
69 64
ffi
�
�
9
69,
Ef36-,69-69
6-,
69
C
N
� �
�
O p
c
E
a
Y
Q
w
O_
T
U
<0
Y
O U
c aJ
n-
N
N
:P > 3
N
O
o
a
N
F-
U
U X
O
O
O_
N
cL
a
o
_l
O
J
N
N W U
m
m
C7
u)
m
LL
F-
,
N
am,a
p
m
M
7
(o (
Z
c
O
E
¢
(Q
J
w
m
Q
�
O
Y
0
Z
C m
r
h
O
N
m
N
La
t�
m
n
cm7
E
69 f»
69
ffi 1-1-1-
v}
N c
Si
m
W
cq
m
c
m 6F3 6%
fH
6%
69
69
fA
6%
ffl
d
N d N o
(OD
(OD
m
VN,'
N
'NU
c�
O X N N
N
N
M
N
N
d
d 0 69 ffl
fPr
fH
fli
fA
69
fA
6%
E
U PM V'
N m
M
N
M
N
O
M
M
m
O
m
M
m
I�
(`'i V'
m
M
N
N
I-
N
<I'
N
a
N 69 69
d
69
69
69
69
69
69
0
7
G
�
C
�
O
2
O
Q
o
m a
—
m
a
m
o
o
m
m
o
m
CL
0
E
j= E
d �
pa
O
Q
pa
Q
Y
o
o 0
0`
O
0
2
LL
.o
O
U
p
F
J fL
a
>
F
r.
a
N
u)
a
(.�
m
c
O
a
a
cl)
u,J
a
a
O Y
�
a
0
N
0
>.
m
Z
O
R
0 0
U
MINOR WORK ORDER #3
ESTIMATE OF COST SUMMARY
CSAH 37/70TH STREET
SP 217-112-002 SP 086-637-033
Description of Work
Unit
Labor Unit
Price
Equipment
Unit Price
* Unit
Price
w/operator
GPS Foreman
HR
$72.89
$0.00
$72.89
Laborer
HR
$56.10
$0.00
$56.10
336 Excavator
HR
$71.75
$176.35
$248.10
Quad Tractorw/Scraper
HR
$71.75
$149.21
$220.96
D6 Dozer
HR
1 $71.27
$165.61
1 $236.88
D6K GPS Dozer
HR
$71.27
$118.02
$189.29
563 Sheepsfoot Packer
HR
$54.05
$82.83
$136.88
247Skidsteer
HR
$62.96
$35.27
$98.23
257 Skidsteer
HR
$62.96
$35.27
$98.23
938 Loader
HR
$71.27
$64.43
$135.70
950 Loader
HR
$71.27
$64.43
$135.70
966F Loader JHR
1
$71.27 1
$91.77 1
$163.04
Quad -Axel Truck JHR
1
$39.16 1
$69.00 1
$108.16
** no 950 Loader Equipment rate
submitted so using 938 loader rate as
su bstiti ute
FUNDING CATEGORY
* = See Force Account Summary for Work Order #3 for breakdown of unit prices SP 217-112-002 SP 086-637-033
Date Description of Work I QuantiiyTUnitT Unit Price * Amount 1 1 2 3 1 4
Working around and lowering small utilities from Sta 216+75 to 220+00
336 Excavator
4
HR
$248.10
$ 992.40
1 Laborer
4
HR
$56.10
$ 224.40
7/29/2015
Quad Tractorw/Scraper
2
HR
$220.96
$ 441.92
GPS Foreman
1
HR
$72.89
$ 72.89
Quad Tractor w/Scra per
1
HR
$220.96
$ 220.96
7/30/2015
Laborer
0.5
HR
$56.10
$ 28.05
$ 1,980.62
$ 1,980.62
Lower small utility crossings; at Sta 216+75 (Fiber), 191+90 (Power), 192+90 (Charter)
336 Excavator
4
HR
$248.10
$ 992.40
8/13/2015
Laborer
3.25
HR
$56.10
$ 182.33
GPS Foreman
1 2
1 HR
1 $72.89
$ 145.78
-
$ 1,320.51
$ 884.74
$ 435.77
Excavate and Backfill for conduit crossing under future 48" culvert
336 Excavator
1
HR
$248.10
$ 248.10
8/31/2015
ID6 Dozer
1
HR
$236.88
$ 236.88
563 Sheepsfoot Packer
1
HR
$136.88
$ 136.88
$ 621.86
$ 621.86
Add field access at Sta 231+50
D6K GPS Dozer
1.5
HR
$189.29
$ 283.94
10/6/2015
Quad Tractorw/Scraper
1
HR
$220.96
$ 220.96
$ 504,90
$ 504.90
Raise Field Driveway at 159+00 LT, change field access widths from 12' to 16' to 20'
247 Skid Steer
7.5
HR
$98.23
$ 736.73
10/13/2015
938 Loader
Laborer
6
2
HR
HR
$135.70
$56.10
$ 814.20
$ 112.20
D6K GPS Dozer
1
HR
$189.29
$ 189.29
$ 1,852.42
$ 1,852.42
Raise trail grades from Sta 234+40 to 232+90 to match existing yard
247 Skid Steer
1 4.5
HR
$136.88
$ 615.96
10/16/2015
1966F Loader
1.5
HR
$163.04
$ 244.56
GPS Foreman
0.5
1 HR
1 $72.89
$ 36.45
$ 896.97
$ 896.97
Ditch/Slope Change at Sta 162+00 to 163+00 for field access relocation
D6K GPS Dozer
1
HR
$189.29
$ 189.29
10/19/2015
966FLoader
1
HR
$163.04
$ 163.04
$ 352.33
$ 352.33
Relocate field access at Sta 225+00 to 226+25
10/20/2015
D6K GPS Dozer
1.5
HR
$189.29
$ 283.94
Quad Tractorw/Scraper
1
HR
$220.96
$ 220.96
$ 504.90
1
1
1 $ 504.90
Berm in front of Dale Kolles at Sta 222+75
257 Skid Steer 1 1 1 HR 1 $98.23 1 $ 98.23
EXHIBIT B
MINOR WORK ORDER #3
ESTIMATE OF COST SUMMARY
CSAH 37/70TH STREET
SP 217-112-002 SP 086-637-033
* = See Force Account Summary for Work Order #3 for breakdown of unit prices
FUNDING CATEGORY
SP 217-112-002
SP 086-637-033
Date
IDescription of Work
I Quantity
Unit
Unit Price *
Amount
1
2
3
4
11/4/2015
1950 Loader
1 0.25
HR
$135.70
$ 33.93
Quad -Axle Truck
0.25
1 HR
1 $108.16
$ 27.04
$ 159.20
$ 159.20
Revise drivewav at Sta 191+50
257 Skid Steer
1 2
1 HR
1 $98.23
$ 196.46
11/5/2015
950 Loader
1
HR
$135.70
135.70
GPS Foreman
1
HR
$72.89
72 889
fE405.05
$ 405.05
Relocate mailbox at Sta 223+00
Relocate Mailbox 1 EA $ 220.00 $ 220.00
$ 220.00 $ 220.00
Revise storm sewer at Sta 214+00
8/21/2015
ICut Hole in CBMH #127
1
LS
$ 900.00
$ 900.00
8/24/2015
Remove FES #27, install 4' of
15" RCP & Reinstall FES #27
1
LS
$ 900.00
$ 900.00
$ 1,800.00
$ 1,800.00
Total $ 10,618.76 $ 5,013.37 $ 1,800.00 $ 3,805.39 $
EXHIBIT B
PAY ESTIMATE #5- COST BREAKDOWN
S.P. 217-112-002 & S.P. 086-637-033
70TH STREET NEICSAH 37 IMPROVEMENT PROJECT
CITY OF OTSEGO AND WRIGHT COUNTY
Bid Schedule
"A"
S.P. 217-112-002
S.P. 086-6 33
Roatlway
Storm
Sewer
TOTAL
Roadway
Storm
Sewer
TOTAL
"Used to
"Used to
Estimated
Used to
Estimated
Cost
Used to
Cost
Estimated
Date"
Estimated
Used to
Cost
Estimated
Cost
Used to
Cost
Estimated
Date"
Total Estiamted
Total Estimated
Total Usad to
Total "Used to
Item
Quantity
Cost Extension
Date
Cost Extension
Quantity
Extension
Date
Extension
Quantity
Cost Extenslon
Extension
Cost Extension
Quantity
Cost Extension
Date
Extension
Ouantlty
Extension
Date
Extension
Quantity
Cost Extension
Extension
Cost Extension
Quantity
Extension
Date
Date"EXtenslen
No.
S .Ref
Descrltion
Unit
Unit Price
0.61
S 54.43274
0.46
S 41047.64
0.05
$ 4461.70
0.03
$ 2677.02
0.66
$ 58,894.44
OA9
$ 43.724.66
0.32
S 26.554.86
0.25
$ 22.308,50
0.02
$ 1784.6a
0.01
$ 892.34
0.34
$ 30339.56
0.26
$ 23200.84
1.00
$89,234.00
0.75
$66925.50
1
20210501
Mobilization
LS
$89234.00
330
$ 330.00
400
$ 400.00
160
$ 160.00
$ -
10
$ 10.00
$ -
170
$ 170.00
0
$ -
500
$500.00
400
$400.00
2
3
2041.610
2101501
Trainees
CanningACRE
HR
$1.00
$2,550.00
305
2
$ 305.00
$ 5,100.00
400
2e
$ 400.00
$ 5,100.00
25
$ 25.00
$ -
$
$ -
2
$ 6.100.00
20
$ 5,100.00
1.2
$ 3,060.00
1.2
$ 3,060.00
$
$ -
1.2
$ 3.060.00
12
$ 306000
3.2
$8,160.00
3.2
$8,160.00
4
2101.506
Gmbbm
ACRE
$Z550.00
2
$ 5100.00
2.1
$ 5100.00
$ -
$ -
2
$ 5,100.00
2,0
$ 5,100.00
1.2
$ 3060.00
1.2
$ 3060.00
$ -
$ -
1.2
$ 3.060.00
1.2
$ 3060.00
3.2
$8160.00
3.2
$8160.00
5
2104.501
Remove Curb & Gutter
LF
$3.13
137
$ 428.81
157
$ 491.41
$ -
$ -
137
$ 428.81
157
$ 491A1
298
$ 93274
$ -
$
$ -
298
$ 932.74
0
$ -
435
$1,36155
157
$491.41
6
2104.501
Remove Pi aCulvarts
LF
$12.24
151
$ 1848.24
218
$ 2668.32
$ -
$ -
151
$ 1848.24
218
$ 2668.32
369
S 4516.56
645
$ 7.894.80
$ -
$
369
$ 4516.56
645
$ 7.894.80
520
$6,364.80
863
$10563.12
7
2104.505
Remove Bituminous Pavement
SY
$1.54
673
$ 1036.42
795
$ 1,224.30
$
$ -
673
$ 1036.42
795
$ 1,224.30
13875
S 21367.50
13648
$ 20863.92
3 -
$ -
13875
$ 21367.50
13548
$ 20863.92
14548
$22403.92
14343
$22, 088.22
EACH
$750.00
$
$ -
$ -
$
0
$ -
0
$ -
2
$ 1,500.00
2
$ 1.500.00
$ -
$ -
2
S 1,500.00
2
$ 1,500.00
2
$1,500A0
2
$1,500.00
8
2104.509
Remove Bollards
EACH
2
$ 52.00
2
$ 52.00
$ -
$
2
$ 5200
2
$ 52-00
8
$ 20B.00
8
$ 208.00
S -
$
8
$ 208.00
8
$ 208.00
10
$260.00
10
$260.00
9
2104.509
Remove Sin
$28.00
370.50
$ -
$ -
SB5
$ 877.50
247
$ 370.50
1D4
$ 156.00
82
S 123.00
$
$ -
104
$ 156.00
82
$ 123.00
689
$1 033.50
329
$483.50
10
2104.513
Sawing Bit Pavement Full Depth)
LF
$1.50
585
$ 877.50
247
$
250
$ 750.00
0
$ -
$ -
$ -
$ -
$ -
0
$ -
0
$ -
250
$750.00
0
$0.00
11
2104.521
Salvage Barbed Wre Fence
LF
$3.00
250
$ 750.00
$
$
$ -
100400
$ -
$ -
$
$
0
$ -
0
$ -
2
$200.00
1
$10000
12
2104.523
Salvage Castin
EACH
$100.00
2
$ 200.00
1
$ 100.00
$ -
$ -
5
2
24406
$ 200.00
$ 99,576.48
1
27,106
$
$ 110,592A8
15586
$ 63,590.88
15.586
$ 63,590488
$
$
15586
$ 63,590.88
15.586
$ 63,590.88
39.992
$163,167.36
42,692
$774,183.36
13
2105.501
Common Excavation P
CV
S4.08
24406
$ 99,576-48
27,106
$ 110,592.48
$ -
-
$
491
$ 2116.21
491
$ 2116.21
1713
S 7,383.03
1713
$ 7383.03
$ -
$ -
1713
$ 7.383.03
1713
$ 7383.03
2204
$9499.24
2,204
$9499.24
14
2105.505
Muck Excava5on E
CY
$4.31
491
$ 2.11fi21
491
$ 2.116.21
$ -
-
t 607.00
$ -
$ -
$ -
$ -
0
$ -
0
$ -
180
$1.918.80
151
$1 607.00
15
16.
2105,521
2105.523
Granular Bonow LV
Common Bartow LV
CV
CV
$10.68
$3.60
180
11055
$ 1 918.80
$ 39,798.00
151
11055
$ 1 607.00
$ 39,798.00
$ -
$ -
$ -
$ -
180
11055
$ 1 918.80
$ 39798.00
151
11,055
$
$ 39,798.00
2043
$ 7,35480
2.043
$ 7,354.80
$ -
$ -
2043
$ 7354.80
2,043
$ 7,354.80
13,098
$47,152BO
13098
$47152.80
17
2105.535
Salve ed Tc Soil From Stockpile L
CY
$1.98
19593
S 38,794.14
14.695
S 29 096.10
$ -
$ -
19593
$ 38 794.14
14.695
$ 29 096.10
13029
$ 25.797-42
9.772
$ 19 348.56
$ -
$ -
13029
$ 25 797.42
9,772
$ 19 348.55
32 622
$64.591.56
24,467
$4B 444.66
2105.535
561Va To St.. Ile EV
CY
$1.41
35591
S 50,183.31
35,591
$ 50,183.31
S -
$ -
35591
$ 50,183.31
35.591
$ 50,183.31
1321E
$ 18.637-38
13.218
$ 18.537.38
8 -
$ -
13218
$ 18,637.3E
13,218
$ 18,637.38
48.809
$68.820.69
48,809
$68,820.69
18
ed aollin
TON
$6.39
29512
$ 188 581.68
27,133
$ 173 379.87
S -
$ -
29512
$ 188 581.68
27.133
$ 173.379.87
11480
8 73,35720
10.555
$ 67 446.45
$ -
$ -
11480
S 73 35720
10.555
$ 67 446.45
40.992
$261 938.88
37,688
$240 826.32
19
22116501
A re ate Base Class 3 or 4
303492.42
$ -
$
25379
$ 287797.86
26763
$ 303492.42
7763
S 88032642
8186
$ 92,829.24
5 -
$ -
7763
$ 8803242
8186
$ 92829.24
33,142
$375830.28
34949
$396321.66
20
2211.501
A e ate Base. Classy Mod
TON
$11.34
25379
$ 287,797-86
26763
$
1254
$ 35,663476
455
$ 12.951.58
$ -
$ -
$ -
$ -
0
$ -
0
$ -
1254
$35.663.76
455
$12,951.58
21
2221.501
Shoulder Base re ate Classy
TON
$28.44
1254
S 35,663.76
455
$ 12951656
$
$ -
$ 620.40
$ -
$ -
$ -
120
$ 620.40
0
$ -
145
$749.65
0
$0.00
22
23
2232501
2357502
MITI Bituminous Sulfa-(1.5"
Bituminous Material For Tack Coat
SY
GAL
$5417
$2.18
25
1611
$ 129.25
$ 3,511.99
1,500
$ -
$ 3,270.00
S -
$ -
$ -
$ -
25
1611
$ 129.25
$ 3.511.98
0
1.500
$ -
$ 3,270400
120
1820
$ 3.967.60
1.300
$ 2,834.00
$ -
$ -
1820
$ 3.967.60
1.300
$ 2 834.00
3,431
$7 479.5B
2800
$fi 104.00
24
2360.501
T eSP9.5 Weadn Course Mixture
TON
$64697
3329
$ 216285.13
196
$ 12,734.12
5 -
$ -
3329
$ 216,285.13
196
$ 12734.12
1472
$ 95.635.84
393
$ 25,533.21
$
$ -
1472
$ 95635.84
393
$ 25533.21
4801
$311920.97
589
6382,&33
25
2360.501
T e SP 12.5 Weadn Course M-xWre 213
TON
$58.56
2116
$ 123,912.96
118
$ 6 910.08
$ -
$ -
2116
$ 123,912.96
118
$ 6 91098
$ -
$ -
$ -
$ -
0
3926
$ -
$ 227 550.96
0
3,fi13
$ -
$ 209 409.48
2 116
12 745
$123,912.96
$738 700.20
718
11 568
$6 970.08
$670 4B1.2B
26
2360.502
T a SP 12.5 Nan Wear Ccurse Mixture 3,C.
TON
$57.96
8819
$ 511.149.24
7.955
$ 461.071.80
$ -
$ -
8819
$ 511 149.24
7 955
$ 461 071.80
3926
$ 227.550.96
3,613
$ 209 409.48
$ -
$
9
$2988.00
27
24110507
Concrete Flume
EACH
$332.00
6
$ 1992.00
6
$ 1992.00
$
$
6
$ 1,892.00
6
$ 1992-00
5
$ 1660.00
3
$ 996.00
$ -
$ -
5
$ 1660.00
3
$ 996.00
11
$3,652.00
28
2501 515
12" RC Pie
EACH
$510.00
$
$ -
5
$ 2,550.00
6
$ 3.060.00
5
$ 550.00
6
$ 3.06a 00
$ -
$ -
$ -
$ -
0
$ -
0
$ -
510.00
5
6
$2550.00
$3,O60.00
6
5
$3 060.00
$2 550.00
29
2501.515
15" RC Pi e A ron
EACH
$510.00
$
$ -
5
$ 2 550.00
4
$ 2 040.00
5
$ 2 550.00
4
$ 2,040.00
$ -
$ -
7
S 510.00
1
$ 510.00
1
$ 510.00
1
$
$2,550.00
30
2501.515
18" RC Pi A ran
EACH
$510.00
$
$ -
1
$ 510.00
1
$ 510.00
1
$ 510.00
1
$ 510.00
$ -
$ -
4
$ 2.040.00
4
$ 040.00
4
$ 2040.00
4
$ 2040A0
5
$2550.00
5
31
2501.515
21 "RC Pipe Aron
EACH
$510.00
$
$
2
$ 1,020.00
2
$ 1,020600
2
$ 1,020.00
2
$ 1,020.00
$ -
$ -
1
S 510.00
1
$ 510.00
1
$ 510.00
1
$ 510.00
3
$1530.00
3
$1.530.00
32
2501.515
24"RC Pip, Aron
EACH
$510.00
$ -
$ -
4
$ 2040.00
4
$ 2040,00
4
$ 2040.00
4
$ 2. 40.00
$ -
$ -
2
$ 1,020.00
2
$ 1020.00
2
$ 1020.00
2
$ 1.020.00
6
$3.ubue0
6
$3060.00
33
2501.515
2T' RC Pi a ran
EACH
$510,00
$
$ -
1
$ 510.00
1
S 510.00
1
S 510,00
1
$ 510.00
$ -
$ -
$ -
$ -
61200
0
7
$ -
$ 61200
a
1
$ -
$ 61200
1
1
$510400
$612 00
1
1
$510.00
$612.00
34
2501.515
30" RC Pipe A ran
EACH
$612.00
$
$ -
$ -
$
0
$
0
$ -
$ -
$ -
1
$ 612.00
$
1
$
$ -
0
S
0
$ -
2
$2.446.00
2
$2448.00
35
2501.515
48"RC Pie ron
EACH
$1224.00
$
$ -
2
$ 448.00
2
S 2448-00
2
$ 2448.00
2
$ 2448.00
$ -
$
$ -
$
$ -
$ -
0
$ -
0
$ -
2
81,020.00
2
$1,020.00
36
2501.525
28"S an RC PI a -Arch ron
EACH
$510.00
$
$ -
2
$ 1.020.00
2
$ 1.020.00
2
$ 1.020.00
2
376
$ 1.020.00
11 505.60
176
-
$ 5,385.60
160
-
$ 4,896.00
112
$ 3,427.20
112
$ 3.427.20
288
$ 8.812.80
272
$ B 323.20
754
$23 072.40
648
$19 828,00
37
25014561
18" RC Pi a Culvert Desi n 3006 CLV all depths)
LF
$30.60
466
$ 14 259.60
376
$ 11.505.60
$ -
$ -
466
$ 14 259.60
$
2,072.00
$
$ -
80
$ 2.960.00
80
$ 2.960.00
80
$ 2,960400
80
$ 2,950.001
136
$5,032.00
136
$5 032.00
38
2501.561
24" RC Mine Culvert Design 30D6 CL III all de the
LF
$37400
$
$
56
$ 072.00
56
$ 2 072-00
56
$ 072.00
56
$
$
$
$
$ -
0
$ -
0
$ -
148
$19.684.00
128
$17 024.00
39
2501.561
48" RC Pipe Culvert Design 30DS CL III all de the
LF
$133.00
$
$
148
$ 19 684.00
128
$ 17 024.00
14B
$ 19 684.00
128
$ 17 024.00
612.00
-
$
-
$ -
$ -
1
$ 612.00
0
$ -
1
$ 612.00
2
$1 224.00
2
$1 224.00
40
2501.569
15" RC S Aron
-- EACH
$612DD
$ -
$ -
2
$ 1.224.00
1
$ 612.00
2
$ 1,224.00
1
$
-
$ 7.344.00
10
$ 6,120.00
$ -
$ -
12
$ 7.344.00
10
$ 6120.00
34
$20,808.00
30
$78,360.00
41
42
2501456918"RC
2501.56924"RCSaf
Safety Aran
Aron-
FACH
EACH
$612.00
$61200
20
$ 12,240.00
$ -
18
$ 11,016.00
$ -
2
3
$ 1.224.00
$ 1836.00
2
3
$ 1224.00
$ 1,836.00
22
3
$ 13.464.00
$ 1836.00
20
3
$ 12,240.00
$ 1,836.00
12
$
$ -
$ -
$ -
0
S -
0
$ -
3
$1.836.00
3
$1836.00
43
2501+569
30" RC Sa A
EACH
$918.00
$
$ -
$ -
$ -
0
$ -
0
$ -
$ -
$ -
1
$ 918.00
1
$ 918,00
1
$ 918.00
1
$ 918.00
1
$918.00
1
$918ea
ran
In Culvert Marker
EACH
$60A0
$
$ -
21
$ 1260.00
27
$ 1,620.00
21
$ 1 60.00
27
$ 1620.00
$ -
$ -
10
$ 600.00
11
$ 660.00
10
$ 600.00
11
$ 860.00
31
$1860.00
3B
$2280.00
44
2501.573
stall
$
5
$ 12750.00
5
$ 12750.00
5
$ 12750,00
5
$ 12,75D.00
$ -
$ -
$
$ -
0
$
0
$ -
5
$12.750.00
5
$12,750.00
45
2501A02
OuBet Structure
EACH
$2550.00
$ -
-
3
$ 3,672.00
0
$
$ -
$ -
$ -
$ -
0
$ -
0
$ -
3
$3,672.00
0
$0.00
46
2507.602
Safe Grate fal24'"RCA ran
EACH
$1.224400
$ -
$ -
3
$ 3,67200
$
0
$
$ -
$ -
1
$ 918.00
1
$ 918.00
1
$ 918.00
1
$ 918.00
1
$918.00
1
$910.00
47
2501,602
Safe Grate for W":RCA ron
EACH
$918.00
S
$
$ -
$ -
0
$ -
24448.00
0
-
$ -
$ -
$ -
2
$ 1.224.00
2
$ 1224.00
2
$ 1224+00
2
$ 1224.00
6
$3.672.00
2
$1224.00
mO
48
2501.602
Trash Guardfor24"PI eA ron
EACH
$612-00
$
$ -
4
$ 2,448.00
8 -
4
$
612.00
1
S 612.00
$ -
$ -
$ -
$ -
0
$ -
0
$ -
1
$612+00
1
$612.00
49
25D1,602
Trash Guard for2T' Pi eA ran
EACH
$61ZOU
$
$ -
1
$ 612.00
1
$ 612.00
1
0
$
$
0
$ -
$ -
$ -
1
$ 612.00
1
$ 612.00
1
$ 61200
1
$ 612.00
1
$612A0
1
$612.00
50
2501.602
Trash Guardfor 30"Pi eA ran
EACH
$61200
$
$
$
$ -
-
$
2
$ 2,448.00
$ -
$ -
$
$ -
0
$ -
0
$ -
2
$2,44H.00
2
$2448.00
51
2501.602
Trash Guard for 48" Pie ran -
_EACH
$1,224.00
$
$ - -
2
$ 2,448.00
2
$ 2.448.00
2
2448.00
$ -
-
$ -
$ -
-
$
0
$ -
0
$ -
2
$1,224.00
0
$0.00
52
2501.602
Trash Guard for 28"S anA ron
EACH
$612.00
$
$ -
2
$ 1224.00
$ -
2
44
$ 1224.00
$ 8976.00
0
28
S -
$ 5712.00
20
$ 4,080.00
18
$ 3672.00
$ -
$ -
20
$ 4080.00
18
$ 3,672.00
64
$13056.00
46
$9384.00
53
2502.501
4"Precast Concrete Headwall
EACH
$204.00
44
$ 8,976.00
28
$ 5712.00
$
$ -
1585
$ 9,700.20
1,307
$ 7.990.84
720
S 44D6.40
728
$ 4,455-36
$ -
S -
720
$ 4466.46
728
$ 4,455.36
2,305
$14,106.60
2,035
$12,45420
54
2502.541
4"Perf PVC Pi. Drain
LF
$6.12
1585
$ 9.70020
1,307
$ 7.998.84
$ -
$
6426.00
442
$ 6311.76
$ -
101
$ 1442.28
$ -
$ -
0
$
101
$ 1442.28
450
$6.426.00
543
$7754.04
55
25D2.541
."Pert PVC Pipe Grain
LF
$14.28
450
S 6.426-02
442
$ 6.311.76
3
$ -
450
$
7,568140
$
$ -
$ -
$ -
0
$ -
0
$ -
106
$7 56BAO
106
$7 568.40
56
2503.541
28 S an RC Pi e-Amh Sewer LillI
LF
$71,40
$
106
$ 7,568+40
106
$ 7,568.40
106
$ 7,568.40
106
$
-
$
$ -
$ -
0
$ -
0
$ -
101
$3 296.64
137
$4 471.68
57
2503.541
12" RC Pi a $ewe! Desi n 3006 CL V all depths)
LF
63264
-
$ -
101
$ 3,296.64
137
$ 4,471.68
101
$ 3 96,64
137
t 67fi
$ 4 471.68
$ 5604288
$
$ -
-
$ -
321
$ 11 13228
319
$ 11 062.92
321
$ 11.132.28
319
$ 11 062.92
1 917
$66481.56
1 935
$67105.80
58
2503.541
15" RC Pipe Sewer Desi n 3006 CLV all d
LF
$34.68
Eli
$
1596
$ 55,349.28
1,61fi
$ 58 042.88
1596
$ 55,349.28
$
$ -
$ -
$ -
0
$ -
0
$ -620
521,501460
131
$4.543.08
59
2503.541
18" RC Pipe Sewer Design 3006 CLV all depths)
LF
$34.68
$ -
fi20
$ 21,501.60
137
$ 4 543.08
620
$ 21 501.60
131
$ 4,543.08
26 144.64
-
S -
$
83
$ 3 047.76
79
$ 900.BB
B3
$ 3047.76
79
$ 2 900.88
2B3
$10 391.76
791
$29,0455261
fi0
2503.541
21" RC Pi eSewer Desi n 3008 CL III all de s
LF
$36.72
-
$
2le
$ 7 344.00
712
$ 26 144.fi4
200
$ 7 344.00
712
Joe
$
$
$ -
$ -
$ -
0
$
0
$ -
202
67 829.52
Lee
$7 713.24
2503.541
ZV RC Pi eSewer Desi n 30.B CL I all de
LF
$3876
$ -
202
$ 7,829.52
199
$ 7 713.24
202
S 7 029.52
$ 7 713.24
3 777.90
-
$
$ -
$ -
$ -
0
$ -
0
$
534.30
81
$3,717.90
fit
2503.541
2T' RC Pi eSewer Desi n 3006.CL III all de s
LF
$45.9D
$
$ -
77
$ 3.534430
81
$ 3 717.90
77
$ 3,514.30
81
$
-
$
419
$ 21 369.00
414
$ 21 114.00
419
$ 21 369.00
414
$ 21 114.00
419
$21 369.00
414
$21 114.00
fi3
2503.541
30" RC Pi a Sewar Desi n 3006 CL III all de 0is
LF
$51.00
$
S -
$ -
$ -
0
$
0
$ -
$ -
-
Bid Schedule
"A"
S.P. 217-712-002
S.P. 086E37-033
Roadway
Storm
Sewer
TOTAL
Roadway
Storm
Sawa!
TOTAL
"Used to
"Used to
Estimated
Used to
Estimated
Cost
Used to
Cost
Estimated
Date"
Estimated
Used to
Cost
Estimated
Cost
Used to
Cost
Estimated
Date"
Total Estlamted
Total Estimated
Total Used to
Total "Used to
Item
Unit Price
Quantity
Cost Extension
Date
Cost Extension
Quantity
Extension
Date
Extension
Quantity
Cost Extension
Extension
Cost Extension
puantity
Cost Extension
Date
Extension
Quantity
Extension
Date
Extension
Quantity
Cost Extension
Extension
Cast Extension
puanti
Extension
Date
Date"Extension
No.
Sec. Ref
Descri tlon
Unit
$612.00
$
$
30.5
$ 18,666.00
48.40
$ 29,620.80
31
$ 1B,fi66A0
48.40
$ 29,620.80
$ -
$ -
8
$ 4,895.00
14.00
$ 8,55&00
8
$ 4,896.00
14.00
$ 8,568.00
38.50
$23,562.00
62.40
$38,188.80
64
2506.501
Constuct Drama, Structure Des l n48-4020
LF
5.5
$ 5049,00
5.50
$ 5.049.00
6
$ 5049.00
5.50
$ 5049.00
$ -
$ -
8.1
$ 7435.80
8.10
$ 7435.80
8
$ 7435.80
8.10
$ 7435.80
13.60
$12484.80
73.fi0
$12484.80
65
2506.501
ConshuctDrainageSlNCNre Desl 54.4020
LF
$918.00
$
$ -
0496.60
12
$ 8710ef)
11.90
$ 8,496.60
$ -
$ -
$ -
$ -
0
$ -
0.00
$ -
1220
$8,770.80
11.90
$8496.60
66
25064501
Construct Draina eStructure Desi n60-4020
LF
$714.00
$
$ -
12.2
$ 8710480
11.90
$
0.00
$ -
$ -
$
446
$ 3753.60
4.60
$ 3753.60
5.
$ 3.753.60
4.60
$ 3753.60
4.60
$3753.60
4.60
$3,753.60
67
2506.501
Construct Drainage Structure Design66-0020
LF
$816.00
S
$
0
$ -
$
0
$ -
0.00
$
$ -
$ -
2.5
$ 7 020.00
$ -
3
$ 1,020.00
0,00
$ -
76.60
$fi T7280
0.00
$0.00
68
2506.501
Construct Draina a Structure Desi n H
LF
$408.00
S
$ -
14.1
$ 5,752.80
$ -
14
$ 5,752.80
-
$ 6160.80
$ -
$ -
225
$ 9180.00
19.80
$ 8078.40
23
S 9180.00
19.80
$ 8,078-40
41.90
$77095.20
34.90
$14239.20
69
2506.501
Construct Draina eStructure DesiginN
LF
$408.00
$
$
19.4
$ 7.91520
15.10
$ 6160.80
19
$ 791520
15.10
22,660.00
$ -
$ -
72
$ 7 920.00
87
$ 9 570.00
72
$ 7.920.00
B7
$ 9,570.OD
319
$35 090.00
293
$32 230.00
70
2515,503
Articulated lntarlocldn Block Open Cell Type A
BY
$110.00
$ -
$ -
247
$ 27170.00
206
$ 22 660.00
247
$ 27170.00
206
$
8620,92
6581
$ 204fi6.91
5240-
$ 16295.16
3 -
--
$ -
6581
$ 20466.91
5240
$ 16295A6
9602
$29,862.22
0012
$24916.08
71
72
2521.501
2531.501
4" Concrete Walk--
Concrete Curb& Gutter Design B424
-SF-
LF
$3.11-
$13.00
3021
4175
$ 9395.31
$ 54,275.00
772
4,235
$ 8620.92
$ 55,055.00
5 -
$
S - -
$ -
3021
4175
$ 9395.31
$ 54,275.00
- 2772
4,235
$ -
$ 55,055.00
426
$ 5,53800
426
$ 5,538,00
$ -
$ -
426
$ 5,538.00
426
$ 5,538.00
4,601
$59,813.00
4,661
$60,593.00
73
2531,501
Concrete Curb& Gutter Design B4i8
LF
$11.30
1613
$ 18226.90
1613
$ 18226.90
$ -
S -
1613
$ 18226.90
1613
$ 18226.90
2085
$ 23,560.50
2085
$ 23560.50
$ -
$ -
2085
$ 23.560.50
2,085
$ 23560.50
3698
$41787.40
3698
$41787.40
74
2531.501
Concrete Curb& Gutter Design 8518
LF
$15.38
148
$ 2276.24
148
$ 2.276.24
$ -
$ -
148
$ 2276.24
140
$ 2276,24
296
$ 4,552.48
296
$ 4552A8
$ -
$ -
296
$ 455248
296
$ 4552.48
444
$6,828.72
444
$6,828.72
75
2531.507
6" Concrete Drivewa Pavement
SY
$39.72
247
$ 9 810.84
255
$ 10 128,60
1
$ -
247
$ 9,810.84
255
$ 10 128.60
288
$ 11 439.36
28B
$ 11 439.36
$ -
$ -
288
$ 11 439.36
288
$ 11 439.36
535
$21250.20
543
$27 567.96
76
2531 P618
Truncated Domes
SF
$36.72
48
$ 1762.56
$ -
$ -
$
48
$ 1,762.56
0
$ -
$ 1,144.00
4
$ -
$ 572.00
4
3 -
$ 572e0
$
$ -
$ -
$ -
0
4
S -
S 572.00
0
4
$ -
$ 572.00
48
12
$1762.56
$1.716.00
0
12
$DAO
$1,716.00
77
2540.602
Install Mail Box Su ort
EACH
$743.00
B
$ 1,144.00
8
$ 1.144.00
$ -
S
8
0
S 1.144.00
$ 24,389.97
8
0.33
$ 24 389.97
0.67
$ 49 519.03
0.67
$ 49 519.03
$ -
$ -
1
$ 49 519.03
0.67
$ 49 519.03
1.00
$73 909.00
1.00
$73 909.00
78
2545.501
Li
Electric ht S
LS
$73 909.00
0.33
$ 24 389.97
0.33
S 24 389.97
$ -
$ -
$
1
$ 4981.68
0.50
$ 3774.00
0.34
S 2,56632
0,26
$ 196248
$ -
$ -
0
$ 566.32
0,26
$ 1.962.48
1.00
$754B.00
0.76
$5736.48
79
2563601
Traffic Control
LS
$7548.00
0.66
$ 4,981.68
0.50
$ 3.774.00
$ -
-
$
151
$ 5.005465
182
$ 8028.33
183
$ 6,066445
19413
$ 6435.41
1
It -
$ -
183
5 6.066.45
194
$ 6,435.41
334
$11072.10
376
$12463.74
80
2564.531
Sig. P ..I.Type C
SF
$33.15
151
$ 5,005.65
181.85
$ 6028.33
$ -
-
37.472.76
14,868
$ 34 837.92
6636
$ 15 528.24
6 170
$ 14 437.80
$ -
$ -
6636
$ 15 528.24
6 170
$ 14.437.80
22.650
$53 001.00
21 058
$49,275.72
81
1 2573.502
ISilt Fence, Type M5
LF
$2.34
$153.00
16014
6
$ 37 472.76
$ 918.00
14.888
5
$ 34,837.92
$ 765.00
23
$ -
$ 3,519.00
14
$ -
$ 2,142.00
16014
29
S
$ 4,437.00
19
$ 2,907.00
13
$ 7,989.00
11
$ 1,683.00
11
$ 1,683.00
3
$ 459,00
24
$ 3,672,00
14
$ 2,142.00
53
$8,109.00
33
$5,049.00
82
2573.530
Storm Drain Inlet Protection
EACH
488
$ 995.52
1188
$ 2423.52
$ -
$ -
488
$ 995.52
1188
$ 2,423.52
152
$ 310.OB
112
$ 228448
$ -
$ -
152
$ 310AB
112
$ 228.48
640
$1,305.60
1300
$2652.00
83
2573,533
Sediment Control LoaT .Straw
LF
$2.04
$
$
1
$ 750,00
0
$ 495.00
0.5
$ 750.00
0.33
$ 495,00
$ -
$ -
1
$ 750.00
0
$ 495.00
1.0
$1,500.00
01
$990.00
84
25734535
Stabilized Constructan Exit
LS
$1 500.00
0.5
$ 750.00
0.33
$ 495.00
-
-
$
5400
$ 4.158400
5,250
$ 4,042.50
2750
$ 2117.50
2750
$ 2.117.50
$ -
$ -
2750
$ 2117.50
2750
$ 2.117.50
8,150
$6275.50
8000
$6160.00
85
2574.508
F.,fte,Type 1
LBS
$0.77
5400
1 $ 4,158.00
5,250
$ 404250
$ -
-
$ 1071.00
5.5
$ 561.00
5.5
$ 561.00
$
$
5e
$ 561,00
5.5
$ 561eO
16.3
$1,662.60
16,0
$7632.00
86
2575.501
Seedin
ACRE
$102.00
10.8
$ 7101.60
10.5
$ 1071,00
$ -
$ -
10.8
$ 1101-60
10e
236
$ 962.88
236
$ 962.88
$ -
$
236
$ 962,88
236
$ 962.88
786
$3206.88
800
$3.264.00
87
2575.502
Seedin Mixture-25-141
LBS
LBS
$4A8
$3.26
550
180
$ 2,244.00
$ 586.80
564
150
$ 2,301.12
$ 489.00
$ -
$ -
$ -
$ -
550
180
$ 2,244.00
$ 586.80
564
150
$ 2,301.12
8 409.00
150
$ 489.00
150
S 489,D0
$ -
$ -
ISO
$ 489.00
150
$ 489.00
330
$1075.8a
300
$978e0
88
2575,502
Seedin Mixture-25-151
TON
$153A0
22
$ 3,366.00
17
$ 2 555.10
$ -
$ -
22
$ 3 365.00
17
$ 2 555,10
11
$ 1 fi83.00
11
$ 1 fi83.00
$ -
$ -
11
$ 1,683,00
11
$ 1 683.00
33
$5,049.00
28
$4,230.10
89
2675.el I
Mulch Material T e 1
SY
$1.22
8057
$ 91829054
10494
$ 12802.68
$ -
S -
8057
$ 9,829.54
10494
$ 12,802.68
2192
$ 2,67424
3,478
$ 4243.16
$ -
$ -
2192
$ 2,674.24
3478
$ 4,243.16
10249
$12503.78
13972
$17,045.84
90
2575.523
Erosion Corral Blanket-G,t9, 2
5768.40
$
$ -
0.66
$ 5768.40
0.66
$ 5768.40
0.34
$ 2971.60
0.34
$ 2971.60
$
$
0.3fl$2
1.fi0
0.34
$ 2971.60
91
2580.601
Interim Pavement Markin -Perot
LS
$8740.00
0.66
$ 5,768.40
0.66
$
-
357.00
0
$ -
5
$ 357.00
$
$ -
$ -
57.00
0
$ -
10
$714.00
0
$0.00
92
2582.501
PavementMassa a LeftArrow -Paint
EACH
$71.40
5
S 357.00
S -
$ -
$ -
5
$
2
$ 142.80
$ -
$ -
$ -
22.80
0
$
6
$428.40
0
594
93
2582.501
Pavement Messy a Ri ht Arrow -Paint
EACH
$71.40
4
S 285.60
$
$ -
$ -
4
$ 285.60
0
$ -
-
$ -
45.60
0
$ -
9
$fi42.60
0
$000
2582501
Pavement Mes NArrow -Palm,
EACH
$71.40
5
$ 357.00
$ -
$ -
$
5
$ 357.00
0
$ -
4
2
$ 285.60
224AO
$$
$
$ -
$ -
2.40
0
$
3
$336.60
0
$0.00
95
2582.501
Pavement Messy e. field -Pair
EACH
$112.20
1
$ 11220
$ -
$ -
$ -
1
$ 11220
0
$
675.00
$
$ -
$ -
750.00
0
$ -24500
$2205.00
0
$0.00
96
2582.502
4"Sclid Line White-Palnt
LF
$0.09
17000
$ 1,530,00
$ -
$ -
$ -
17000
$ 1530.00
0
7500
158
$
14.22
-
$
$ -
$ -
1584.22
0
$
236
$2124
0
$0,00
97
2582502
8" Solid Line White -Paint
LF
$009
78
$702$
-
$
$ -
76
$ 7.02
0
113
$
17289
-
$ -
$
$
1132.89
0
$
171
$261.63
099
98
2582-502
B" Dotted Line White - Paint
LF
$1.53
58
$ 88.74
$ -
$ -
$ -
58
$ 88.74
0
M
S
$
S -
$ -
0-
0
$ -
56
S14280
0
$0.00
2112.112
12"Sto Line White -Paint
LF
$2.55
56
$ 14280
$
$
$ -
56
$ 142-80
0
1051
S -
$ 94.59
-
$ -
$ -
$ -
1054.59
0
$ -
1,501
$135.09
0
$0.00
100
2582.502
4"Solid Line Yellow-PaintLF
$0.09
450
$ 40.50
$$
-
450
$ 40.50
0
133
325.85
$ -
$ -
$
1335.85
0
$ -
547
$1340A5
0
$0.00
101
2582.502
24"Solid Line Yellow -Paint
LF
$2,45
414
S 7014.30
$ -
$ -
$
414
$ 1014.30
0
3870
$
$ 657.90
$ -
$$
-
367.90
0
$ -
13370
$2272.90
0
60.00
102
2582.502
4"Double Solid Lin. Yellow -Paint
LF
$0A7
9500
$ 1615.00
$
$
$ -
9500
$ 1,675.00
0
36
-
-
-
-
81
$279.99
0
$0.00
103
2582.603
aVement ar ng Pecla - runt
LF
-
25
1
_
-
-
-
-
7 ... Ica
IF
S a9 a5B 14
S 944.336.01
S 834.571.87
S 3.122.398.24
$2.579,914.43
S.P. 217-112-002
S.P. 086-037-033
Roadway
Storm Sewer
TOTAL
Roadway
Storm
Sewer
TOTAL
Item
No.
Sec. Ref
Description
Unit
Unit Price
Estimated
Quantity
Cost Extension
Used to
Date
Cost Extension
Estimated
quantity
Cost
Extension
Used to
Date
Cost
Extension
Estimated
Quantity
Cost Extension
"Used to
Date"
Extension
Cost Extension
Estimated
Quantity
Cost Extension
Used ro
Date
Cost
Extension
Estimated
Quantity
Cost
Extension
Used to
Date
Cost
Extension
Estimated
Quantity
Cost Extension
"Used to
Date"
Extenslan
Cost Exmnsion
Total Estlamted
Quantity
Total Estimated
Extension
Total Used to
Date
Total "Used to
Date" Extension
1
2104.505
Addifianal Bituminous Pavement Removed
CY
$10.08
$
$
S
$
0
$ -
0
$ -
791
$ 7,973.28
791
$ 7,973.28
$ -
$
791
$ 7,973.28
791
$ 7,973.28 791
$7,973.28
791
$7,97328
2
2021.501
Mobil¢a8on
EACH
$412.50
$
$
$
$ -
0
$ -
0
$ -
3,00
$ 1,22751
3.11
$ 1.29750
$ -
$ -
3
$ 1.237.50
3.00
$ 1,237650 3.00
$1 237.50
3.00
$1 237.50
3
Relocate Spada] Sin
EACH
$fi05.00
$
$
$
$ -
0
$ -
0
S -
2
$ 1,210.00
1
$ Go5.00
$ -
$
2
$ 1 210.00
1
$ 605.00 2
$1 210.00
1
$605.00
S7 ns
Installed on
623715
4
2563.601
48"Road Closed Ahead PER DAY $0.75
$ $ $ $ 0 $ -
0 $
85
$ 53.75
122
$ 91.50
$ -
$ - 85
$ fi3.75
122.00
$ 91.50 85.00
$63.75
122.00 $91.50
5
2563.601
48"Detour Ahead
PER DAY
$0.75
$
$
$
$ -
0
$
0
$ -
85
$ 93.75
122
$ 91.50
$ -
$ -
85
$ 63.75
122.00
$ 91.50 85.00
$63.75
12200
$91.50
8
2563.601
(e)Oatour Guidance Assemblies+portable Stipp..
70.25E/Each $0.16 SF/Da +$0.47 su oNda)
PER DAY
$16.82
$
$
$
$
0
$
0
$ -
85
S 1,429.70
122
$ 2.052.04
$
$ -
85
$ 1,429.70
122.00
$ 2.052.04 85.00
$1,429.70
122.00
$2,052.04
7
2563.601
3 T e III Barricades $1.53//Each/Da
PER DAY
$4.59
$
$
$ -
$ -
0
S -
0
$
85
$ 390.15
122
$ 559.98
$ -
S -
85
$ 390.15
12200
$ 559.98 05.00
$390115
12200
$55998
8
2563.601
6 T g e A Flasher $0.25//Each/Da
PER DAY
$1.50
$
$
$
$ -
0
$ -
0
$ -
85
$ 127.50
122
$ 183.00
$ -
$ -
85
$ 127.50
122.00
$ 163.00 85.00
$127.50
122.00
$183.00
9
2563.601
(4) 60" x 30" Road Closed Miles Ahead Sign (12.5
SF/Each $0-le SF/Da
PER DAY
$8.00
$
$ -
$ -
$ -
0
$ -
0
$ -
85
$ 680.00
122
$ 976.00
$
$
85
$ 680.00
122.00
$ 976.D0 85A0
$680.00
122.00
$976.00
10
2563.601
(2) 45" x 18" Detour Sign (6 SF/Each @ $0.16
SF/Day)
PER DAY
$1.92
$
$ -
$ -
$ -
0
$ -
0
$ -
85
$ 163-201
122
$ 234.24
$
$
85
$ 163.20
12200
$ 234.24 85.00
$163.20
122.00
$234.24
S.P. 217-112-002
S.P. 086-637-033
Roadway
Storm Sewer
TOTAL
Roadway
Storm Sewer
TOTAL
Item
No.
S .Rot
Description
Unit
Unit Price
Estimated
Quantlry
Cost Extension
Used to
Date
Cost Extension
Estimated
Quantity
Cost
Extenston
Used to
Date
Cost
Extension
Estimated
Quantity
Cos[Extension
"Used
•ua to
Date"
Extension
Cast Extension
Estimated
Quantity
Used to
Cast Extension Date
Cost
Extension
Estimated
Quantity
Cost Usedto
Extension Date
Cost
Extension
Estimated
Quantlry
•sea m
Date"
Cost Extension Extension
Cost Exmnslon
Total Estlamted
Quanti
Total Estimated
Extension
Total Used to
Date
Total "Used to
Date" Extension
Sl s
lnstalletl on 6/JO/15
11
2563.601 (9) Detour Guidance Assemblies+portable Supports
10.2 SF/Each $0.16 SF/Da +$0.47 su oMda PER DAY $18.92
S $ $ $ - 0 $ 0 $ -
78 $ 1475.76 715 $ 2175.80 $ - $ 79 $ 1,475,76 115 $ 2175.80
78 $7,475.76 175 $2175.80
Signslnstalled
on 7R45
12
2563.1 1
2 48"Road Closed St $0.75 er si Nda. PER DAY $1.50
$ $ $ - $ 0 $ - 0 $ -
75 $ 11250 113 $ 169.50 $ - $ - 75 $ 11250 113.00 $ 169.50
75.00 $112.50 713.00 $169:50
13
2563.601
3.48"Detour Ahead Sin $0.75 er si /da
PER DAY
$2.25
$
$
$
$ -
0
$ -
0
$ -
75
$ 168.75
113
$�25$
-
$ -
75
$ 168.75
113.00
$ 254.25
75.00
$168.75
113.00
$254.25
14
2563.601
(19) Detour Guidance Assemblies Portable Supports
10.2SF/Each $0.16SF/Da +$0.47su ort/da
PER DAY
$39.94
$
$
$ -
$ -
0
$
0
$ -
75
$ 2,995.50
113
$
$75$
2,995.50
113.00
$ 1.a13..
75.00
$2,995.50
11100
$4,513.2215
2563:601
(2) Special84x 46 Signs (2B SF/Each (9 $38.59SF)
SF
$38.59
$
$
$ -
$ -
0
$
0
$ -
56
S 2.161.04
56
$$
$
56
$ 2,161.04
56,00
$ 2;161.04
56.00
$2,161.04
56.00
$2,181.04
tome
-mange
S.P. 217-112-002
S.P. 086-037-033
Roadway
Storm Sewer
TOTAL
Roadway
Storm Sewer
TOTAL
Item
No.
Spec. Rai
Description
Unit
Unit Pdee
Estimated
Quantity
Cost Extension
Used to
Oam
Cost Extension
Estimated
Quantlry
Cost
Extension
Used to
Date
Cost
Extension
Estimamd
Quantity
Cost Extension
"Used
a to
Date"
Extension
Cost Extension
Estimated
Quantity
Gast Exmnsion
Used ro
Date
Cost
Extension
Estimated
Quantity
Cost Usetl to
Ezmnsfan Date
Cos[
Extension
Estimated
Quantlry
Cost Extension
"Used to
Date"
Extension
Cost Exmnsion
Total Estlamted
puanti
Total Estimated
Extension
Total Used to
Date
Total "Used to
Date" Extension
1
2545.501
ElectricU htS stem
LS
$73909.00
-0.33
$(24,636.09)-0.33
$ 24 W09
$ -
$
24636.09
0,33
$ 2463&(m
-0.67
$ 49272.91
-0.67
$ 49,272.91
$
$ -
-0.67
$ 49272.91
0.67
$ 4927291
-1.00
573909.D0
-1
-$73909.00
2
2545.170
ecmcLightSystem
LS
$7 ,830.38
0.33
$ 2 ,276.54
0.33
$ 6.5
$ -
-
0.33
$ 25,2 6.
0.33
25,276.54
0.67
0, 3.
0.67
50,553.84
$ -
-
O.fi7
$ 50,553.84
0.67
$ 50,553.84
7,00
$75,830.38
1
$76.830.38
S.P. 217-112-002
S.P. 088-037-033
Roadway
Storm Sewer
TOTAL
Roadway
Storm
Sewer
TOTAL
It..
No.
S ,Ref
Desed ion
Unit
Unit Price
Estimated
Quantity
Cost Extension
Used to
Date
Cost Extension
Estimated
Quantity
Cost
Extension
Used to
Date
Cost
Extension
Estimated
Quantlty
Cost Extension
" se to
Date"
Extenslan
Cost Extension
Estimated
Quandty
Cost Extension
Used to
Date
Cost
Extension
Estimated
Quantity
Cost
Extension
Used to
Date
Cost
Extension
Estimated
QuantlTy
Gas[Pxtenslon
"Used ro
Date"
Extension
Cost Extension
Total Estlamted
Quantity
Total Estimated
Extension
Total Usad to
Date
Total "Used to
Date" Extension
1
21050505
Muck Excavafian EV
CY
74.31
16369
$ 70550.39
22547 j
$ 97177,57
$
1 $ -
16369
$ 70550.39
22547
$ 97177.57
10267
$ 44,250.77
14,142
1 60,952.0210267
$ 44,250.77
14142.00
$ 60952.02
26.636.00
$114.801.16
36689.00
$158129.59
2
21054522
Select Granular Bo r L
CY
$10.44
2000
$ 20 880.00
S
$ -
$ -
2000
$ 20 880.00
0
$ -
7500
$ 78.300.00
8,329
$ 86 954.76
$ -
$ -
7500
$ 78 300.00
8 329A0
$ 86 954.76
9,500.00
$99 180.00
8.329.00
$86 954.76
3
2105.523
Common Bomow L
CY
$3.60
8863
$ 31.906.80
14.674
$ 52,826.40
$ -
$ -
8863
$ 31906.80
74674
$ 52826.40
6031
5 21711.60
9fi54
$ 34754.40
$
$ -
6031
$ 21,711.60
9654.00
$ 34754.40
14894.00
$53 fi78.40
24328.00
$87580.80
-4
2105.604
Geotexble Fabric, Type 5 _
BY -
_ $4.50.
1600
$ 7,200.00
$ _
$ -
$ - -
7600
$ 7,200.00
0
$ _ _
_ _
S -
$ _ _ - -.
$ -
$ -
0
$ -
0.00_
$ -
1,600.00
$7,200.00
0.00
$0.00
Total - Supplemental Agreement No. 1
S.P. 217-112-002
S.P. 086-037-033
Roatlway
Storm hewer
_
TOTAL
Roadway
Storm Sewer
TOTAL
Item
No.
See. Ref
Des<d tion
U.
Unit Pricet
rE-ma-d
Extension
Used to
Date
Cost Extension
Estimate�.Inst
Quantityon
Used to
Date
Cost
Extenston
Estimated
Quantlry
Cost Extension
"Used to
Date"
Extension
Cost Extension
Estimated
Quantity
Cost Extension
Estimated
Quantlry
Cost
Extension
Used to
Date
Cost
Extension
Estimated
Quantity
Cost Extension
"Used to
Date"
Extension
Cost Extension
Total Estlamted
puanti
Total Estimated
Extension
Total Used to
Date
Total "Used to
Date" Extension
1
T211.501
A re at. Base Class 5 Mod
TON
$11.34
1053
$ 77,941.02
1.059
$ 12,009.06
$
1053
S 11941.02
1,059
$ 12009.Ofi
447
$ 5,068.9ILAExten.s1cm
1.66
$447
$ 5,068.98
449
$ 5,091.66
7,500
$17,010.00
1,508
$17,100.72
2
2451.609
Crashed Rack (3" Recycle)
TON
$38.93
211
$ 8,214.23
234
$ 9,104.56
-
$ -
211
$ 8,214.23
234
$ 9,104.56
89
$ 3,464.779,4.77
$ -
$ -
89
$ 3,464.77
89
$ 3,4fi4.77
300
$11,679.00
323
$12,569.33
S.P. 217-112-002
I S.P.
088-037-033
Road Way
Storm Sewer
TOTAL
Road Way
Storm
Sewer
TOTAL
Imm
No.
Sec. Ref
Descd tion
Unit
Unit Price
Estimated
Quantity
Cost Extension
Usetl to
Date
Cost Extension
Estimated
Quantity
Cast
Exmnsion
Used to
Date
Cost
Exmnsion
Estimated
Quantity
Cost Extension
"Used to
Date"
Exmnsion
I
Cost Extenslan
Estimated
Quantlry
Cost Extension
Used to
Date
Cost
Extension
Estimated
Quantity
Cost
Extension
Used to
Date
Cost
Exmnsion
Estimated
Quantity
Cost Extension
"used to
Date"
Extension
Cost Exmnslon
Total Estiammd
Quantity
Total Estimated
Extension
Total Used to
Date
Total "Used to
Date" Exmnsion
1
2360.501
T e SP 9.5 Wgnnn Coulse Mixture 3 C
L5
.$4,37656
0.90
$ (3,938.90
0.90
$ 3,938.90
5
$ -
0,90
$ 3,938.90
D90
$ 3,938.90
0.10
$ -
0.10
$ 437.fi6
0.10
$ 437.66
1
$4,376.56
1
$4,376.56
2
2360.502
Ype SP 25 on ear Course %lure
LS
3
0.33
$ ( 2 6)
0.33
252.56)
-
-
0.33
u-
$ (2 2. 6)
.6
2 8)
D.67
8)
0.6
j
1
$765.34
7
-$765.34
S.P. 217-112-002
S.P. 096-037-033
Roadway
Storm Sewer
TOTAL
Roadway
Storm
Sewer
TOTAL
Item
No.
Sec, Ref
Desert Bon
Unit
Unit Price
Estimated
Quantity
Cost Extension
Used to
Date
Cost Extension
Estimated
Quantity
Cost
Extension
Used to
Date
Cost
Extension
Estimated
Quantity
Cost Extension
"Used to
Date"
Extension
Cost Extension
Estimated
Quantity
Cost Extension
Used to
Date
Cost
Extension
Estimated
Quantity
Cost
Exmnsion
Used to
Data
Cost
Extension
Estimated
Quantity
Cost Extension
"used to
Oat."
Extension
Cost Extension
Total Estlamted
Quanti
Total Estimated
Extension
Total Used to
Oate
Total "Used to
Date" Extension
1
LoWering small UkliBes:Sta21fi+75 to 220+00
LS
$1980.62
$
$
S -
$ -
0
$ -
0
$ -
1
$ 1980.62
1
$ 1980.62
$
$ -
1
$ 1.980.62
1
$ 1980-62
7
$1,9Sot
1
$1980.fi2
2
Lower small utility crossings: Sta 216+50, 181-90, &
192+90
LS
$1,320.51
0.67
$ 884.74
1
3 884.74
$
$
0.67
$ 884.74
1
$ 884.74
0.33
$ 435.77
0.33
$ 435.77
$
$
0.33
$ 435.77
0
$ 435.77
1
$1.320.51
1
$1,320.51
3
Excavate and Backfill for conduit Crossing under
48' culvert
LS
$621.86
1
$ 621.86
1
$ 621.86
$
$ -
7
S 621.86
1
$ 621.86
$
$
$
$
0
$
0
$
1
$621.86
1
$621.86
4
Add field access: Sta 231+50
LS
$504.90
$
$
$
$ -
0
$ -
0
$
1
$ 504.90
1
$ 504.90
$ -
$ -
i
$ 504.90
1
$ 504.90
1
$50C90
1
$504.90
5
Raise field access and widen: She 159+00
LS
$1 852.42
1
s 1.852.42
1
$ 1,852.42
S
$
1
$ 1.8
1
$ 1 852.42
$ -
$ -
5 -
$
0
$ -
6
Raise trailgrade: She 232+90to 234+40
LS
$896.97
1
$ 896.97
1
$. 896.97
$
$
1
IF B96.97
1
$ 896.97
$ -
$ -
$ -
$ -
0
$ -
0
$ -
1
$9695.97
1
$896.97
7
Chan a DBch and relocate field access' She 1624-00
LS
$352.33
7
$ 352.33
1
$ 352.33
$ -
$ -
i
$ 352.33
1
$ 352.33
$ -
$ -
$ -
$ -
0
$ -
0
$ -
1
$352.33
1
$352.33
8
Relawtefield access: Sta 225+00
LS
$504.90
$
$
$ -
$ -
0
$ -
0
$ -
1
$ 504.90
1
$ 504.90
$
$ -
1
$ 504.90
1
$ 504.90
1
$504.90
1
$504.90
9
Add herm:St. 22+75
LS
$159.20
$
$
$
$
0
$ -
0
$ -
1
$ 159.20
1
$ 159.20
$ -
$ -
1
$ 159.20
1
$ 159.20
1
$15920
1
$159.20
10
Revise drtvewa : Sta 191+50
LS
$405.05
1
$ 405.05
1
$ 405.05
$ -
$
1
$ 405.05
1
$ 405.05
$
S -
$
$ -
0
$ -
0
$ -
1
$405+05
1
$405.05
11
Relocate Mailbox: Sta 223+O0
LS
$220.00
$
$
$ -
$ -
0
$ -
0
$ -
1
$ 220.00
1
$ 220.00
$ -
$ -
1
$ 220.00
1
$ 220.00
1
$220.00
1
$220.00
12
Revise storm sewer. Ste 214+00
LS
$1,600.00
$
7
1.600.00
1
$ 1,800.00
1
$ 1,800.00
1
1,800.00
$
$ -
$ -
0
1 $ -1
0
4 -
1
$1,BOD.00
1
$1,800.00
WORK
COMPLETED
$ 2,079,421.79 $ 1,678,088.48 $ 252,59524 $ 241,664.04 $ 2.332,017.03 TO DATE= $
1,919,722.52 $ 1,032,937.07 $ 963,345.07
$ 88,583.32 $ 89,858.14 $ 1,121,520.39 $
1,053.203.21
$ 3.463,637.42 $
2,972,925.72
LESS S%RETAINAGE= $
95,986.13
$
52,660.16
It
148,646.29
ERODIBLE ACREAGE WITHHOLDING ($3,0001 DISTRUBED ACRE) $
32,400.00
$
16,500.00
$
48,900.00
LESS PAY ESTIMATE #1 = $
271,845.90
$
185,836.03
$
467,681.93
LESS PAY ESTIMATE#2= $
1891869*05
$
22936.88
$
445,805.94
LESS PAY ESTIMATE ❑3 = $
6941706.02
$
183,698.54
$
878,304.56
LESS PAY ES nMATE#4= $
460,935.84
$
257,145.31
$
718,081.15
CURRENTPAYMENT= $
173,879.58
$
101,526.29
$
275,505.86
CURRENT TOTAL PAYMENTS TO DATE= $ 1,791,336.39 CURRENT TOTAL PAYMENTS TO DATE= $ 984,043.05 6 Z775,379.44