Norin Landing Paving CostsEngineer's Estimate Norin's Landing Park City of Otsego, MN ot720norin landing parkengest 7/31/2015 10:35 AM A B C D E F 1 Norin's Landing Boat Ramp Cost Estimate (2015) P& R -NL12-042 Schedule "A" - Site Work 2 3 4 5 6 Item No. Description Unit Estimated Unit Cost Estimated Quantity Total Estimated Cost 7 1 Common Excavation (CV) CY $9.50 560 $5,320.00 8 2 Salvage Topsoil to Stockpile (CV) CY $7.00 1,620 $11,340.00 9 3 Salvage Topsoil from Stockpile (CV) CY $3.50 1,1001 $3,850.00 10 Schedule "B" - Bituminous Driveway/Parking Lot Total Schedule "A": $20,510.00 11 12 13 Item No. Description Unit Estimated Unit Cost Estimated Quantity Total Estimated Cost 14 1 Aggregate Base, Class 5 (Modified) TON $19.50 1,300 $25,350.00 15 2 Type LV4 Wearing Course Mixture (B) TON $97.00 350 $33,950.00 16 3 IType LV3 Non -Wearing Course Mixture (B) TON $91.50 310 $28,365.00 17 4 Bituminous Material for Tack Coat GAL $4.50 140 $630.00 18 5 Concrete Curb and Gutter LF $19.50 565 $11,017.50 19 6 Sawcut Bituminous Pavement (Full Depth) LF $4.50 40 $180.00 20 7 Mill Bituminous Surface SF $11.50 28 $322.00 21 8 4" Solid White Line - Paint I LF $0.40 540 $216.00 22 Schedule "C" - Storm Sewer Total Schedule "B": $100,030.50 23 24 25 26 Item No. Description Unit Estimated Unit Cost Estimated Quantity Total Estimated Cost 27 1 RC Pipe Sewer, Design 3006 CL V LF $43.50 500 $21,750.00 28 2 Construct Drainage Structure EA $2,625.00 5 $13,125.00 29 3 Concrete Apron I EA 1 $855.001 5 $4,275.00 30 Please Note: this estimate does not include costs for installing a boat ramp, dock, any required dredging, or breakwater checks for dock protection. Total Schedule "C": Total All Schedules: 15% Engineering Fee: 5% Contingency: Total: $39,150.00 $159,690.50 $23,953.58 $7,984.53 $191,628.60 31 32 33 34 35 36 ot720norin landing parkengest 7/31/2015 10:35 AM