ITEM 3.4E Street Renewal Project 16-04OtsTefffo MINNESOTA V DEPARTMENT INFORMATION Request for City Council Action ORIGINATING DEPARTMENT: REQUESTOR: MEETING DATE: Public Works City Engineer Wagner September 26, 2016 PRESENTER(s): REVIEWED BY: ITEM #: City Engineer Wagner City Administrator Johnson 3.4E AGENDA ITEM DETAILS RECOMMENDATION: Staff recommends approval of final payment in the amount of $115,806.25 for the 2016 Otsego Street Renewal, Improvement Project No. 16-04 (James Addition) to Omann Contracting Companies, Inc. ARE YOU SEEKING APPROVAL OF A CONTRACT? IS A PUBLIC HEARING REQUIRED? No No BACKGROUND/JUSTIFICATION: This the 15t and final payment for the work completed within James Addition. Omann Brothers has completed all contract work for subgrade correction, bituminous patching, placing the 2" bituminous overlay, and shouldering along 87th Street, 88th Street and Packard Avenue within James Addition. All improvements were completed before the final completion date of September 15, 2016. Final construction costs are $115,806.25. The original contract was for $104,937.66. Some additional subgrade correction, aggregate base, and full depth patching was necessary to provide a good final product. The project cost estimate (including Admin, Engineering, and overhead) was $137,844.00. The actual project costs will be $134,000.67. The public hearing for the assessments to the property owners is currently being advertised so that the assessment hearing can be held on October 10, 2016. The amount advertised to for the assessment hearing, $134,000.00, is less than the estimated total of $154,000 advertised for the public hearing held on the March 18th, 2016. SUPPORTING DOCUMENTS: X ATTACHED X NONE • Final Pay Estimate (PE#1) POSSIBLE MOTION Please word motion as you would like it to appear in the minutes. Motion to approve final payment to Omann Contracting Companies, Inc. in the amount of $115,806.25 for the 2016 Otsego Street Renewal, Improvement Project No. 16-04 (James Addition). BUDGET INFORMATION FUNDING: Assessments City Street Fund BUDGETED: X YES Zug FINAL PAYMENT CITY OF OTSEGO 2016 Otsego Street Renewal, Project (James Addition) City Project # 16-04 September 21, 2016 Honorable Mayor & City Counci City of Otsego 13400 90th Street Otsego, MN 55330 RE: 2016 Otsego Street Renewal, Project No. 16-04 (James Addition; Contractor: Omann Contracting Companies, Inc. Contract Amount: $104,937.66 Award Date: May 18, 2016 Completion Date: September 15, 2016 Dear Honorable Mayor and Council Members The following work has been completed on the above -referenced project by Omann Contracting Companies In( ITEM NO. ITEM DESCRIPTION ESTIMATED QUANTITY UNIT CONTRACT UNITPRICE CONTRACT AMOUNT USED TO DATE EXTENSION 1 MOBILIZATION 1 LS $4,000.00 $ 4,000.00 1 $ 4,000.00 2 REMOVE BITUMINOUS PAVEMENT 918 SY $4.22 $ 3,873.96 1092 $ 4,608.24 3 SAWING BIT PAVEMENT (FULL DEPTH) 314 LF $2.00 $ 628.00 321 $ 642.00 4 SUBGRADE EXCAVATION 171 CY $16.50 $ 2,821.50 311 $ 5,131.50 5 ICL 5 AGGREGATE BASE 335 TON $15.25 $ 5,108.75 617 $ 9,409.25 6 SHOULDERING -TOPSOIL 84 CY $74.00 $ 6,216.00 100 $ 7,400.00 7 TYPE LV3 NON -WEARING COURSE MIXTURE (B) (PATCH) 103 TON $68.25 $ 7,029.75 132 $ 9,009.00 8 MILL BITUMINOUS SURFACE (2.0") 748 SY $3.25 $ 2,431.00 650 $ 2,112.50 9 BITUMINOUS MATERIAL FOR TACK COAT 550 GAL $2.50 $ 1,375.00 680 $ 4,700.00 10 TYPE LV4 WEARING COURSE MIXTURE (B) 1270 TON $54.15 $ 68,770.50 1276.28 $ 69,110.56 11 TRAFFIC CONTROL 1 LS $825.60 $ 825.60 1 $ 825.60 12 ITURF ESTABLISHMENT 1 LS $1,857.601 $ 1,857.601 1 $ 1,857.60 Total Bid Schedule "A" $ 104,931.66 Bid Schedule "A" TOTAL ALL BID SCHEDULES TOTAL WORK COMPLETED TO DATE WE RECOMMEND FINAL PAYMENT OF: Please verify the amount of previous payments, and the receipt of the following items prior to making payment. 1. Certificate of claims payment (lien waiver), 2. Affidavit of payment of States taxes (MN State TAX Form IC 134), 3. Letter of consent from surety firm. APPROVALS: CONTRACTOR: OMANN CONTRACTING COMPANIES, INC. Certification by Contractor: I certify that all items and amounts are correct for the work completed to date. Date ENGINEER: HAKANSON ANDERSON ASSOCIATES, INC. Certification by Engineer: We recommend payment for work and quantities as shown. Title: OWNER: CITY OF OTSEGO $ 104,937.66 $ 104,937.66 $ 115,806.25 $ 115,806.26 $ 115,806.26 $ 116,806.26 OT392-2016 PE.xisx PE - 1