ITEM 3.6 Purchase of submersible pump4
Otkzo
F
MINNESOTA V
DEPARTMENT INFORMATION
Request for
City Council Action
ORIGINATING DEPARTMENT
REQUESTOR:
MEETING DATE:
Utilities
Utility Manager Neidermeier
May 8, 2017
PRESENTER(s)
REVIEWED BY:
ITEM #:
Consent
City Administrator/Finance Director
Flaherty
3.6
AGENDA ITEM DETAILS
RECOMMENDATION:
Staff recommends the purchase of a new replacement submersible pump with bladeless impeller at the
Main Lift Station for the East Collection System. The purchase was discussed at the April Public Works
Subcommittee with recommendation of pursuing as the existing pump is no longer serviceable. The
purchase request has been submitted under the Emergency Management Act within purchase policy
requirements.
ARE YOU SEEKING APPROVAL OF A CONTRACT?
IS A PUBLIC HEARING REQUIRED?
No
No
BACKGROUND/1 USTI F I CATI O N:
An emergency purchase of a submersible pump was completed for the Main East Collection System Lift
Station located at Quaday Avenue. The purchase was placed due to pump failure resulting from a seal leak
and motor submergence. The pump was installed in 2009 and has met its expected life cycle of age,
repairs and significant use. The equipment was reviewed for new and future force main requirements to
identify the best fit for the application including velocities, capacities, restrictive pressures and ability to
pass material. Two quotes were received ranging from $19,582.00 to $22,942.00. The manufacturer
representative was the low quote for the equipment. The pump is anticipated to arrive early June for
service.
SUPPORTING DOCUMENTS ATTACHED:
• Pump Quote from WW Goetsch Associates
POSSIBLE MOTION
PLEASE WORD MOTION AS YOU WOULD LIKE ITTO APPEAR IN THE MINUTES:
Motion to approve purchase of a new replacement submersible pump for the Main Lift Station for
$19,582.00 through WW Goetsch Associates.
BUDGET INFORMATION
FUNDING:
BUDGETED:
602 -49450-530
Yes
Kurt Neidermeier
From: Bryan Goehring <bgoehring@wwgoetsch.com>
Sent: Tuesday, April 18, 2017 7:26 PM
To: Kurt Neidermeier
Subject: RE: lift station info Otsego
Attachments: Otsego Quaday LS EXISTING PUMPS.pdf, Otsego Quaday LS NEW BLADELESS
IMPELLER PUMP.pdf
Kurt,
Attached pleas find pump curves for the existing pumps and a variable speed curve for the existing pumps, both have
the system head curves plotted for the 8" forcemain and the 12" forcemain,
Also please find performance curves for the proposed new pump with the bladeless impeller, I only plotted the 12"
forcemain on these curves.
The cost for the new model, Fairbanks 4"D5433MVK, 40hp, 1750 rpm, Bladeless impeller sized for the design condition
of (700 gpm @ 106' tdh), $19,582. Lead time for this one would be the same, 4 — 6 weeks.
Thanks for your time today, I always enjoy getting together.
Please let me know if you have any questions,
Bryan Goehring
W.W. Goetsch Associates
5250 West 74th Street
Minneapolis, MN 55439
Direct (952) 374-6472
Mobile (612) 845-9243
From: Kurt Neidermeier[mai Ito: KNeidermeier(a)ci.otsego.mn.usl
Sent: Tuesday, April 18, 2017 5:27 PM
To: Bryan Goehring (Goetch)
Subject: Fwd: lift station info Otsego
Attached
Sent from my Whone
Begin forwarded message:
From: "Kurt Neidermeier" <KNeidermeier a,ci.otsego.mn.us>
To: "Kurt Neidermeier" <KNeidermeier@ci.otsj .mn.us>