Loading...
ITEM 4.1 _attachment 2CITY OF AM Ote 0 MINNESOTA 2018 CIP - PROPOSED TRAIL PROJECT Boulder Creek to 75th Street Mobilization 1 LS $ 5,000.00 $ 5,000.00 Remove Pavement 10 SY $ 15.00 $ 150.00 Mill 11/2" Deep 5 SY $ 10.00 $ 50.00 Curb Removal 15 LF $ 25.00 $ 375.00 Common Excavation 305 CY $ 8.00 $ 2,440.00 Soil Corrections/Muck Excavation 375 CY $ 10.00 $ 3,750.00 Common Borrow 580 CY $ 10.00 $ 5,800.00 Topsoil Borrow 100 CY $ 25.00 $ 2,500.00 9" Thick Class 5 Agg Base 365 Tons $ 18.00 $ 6,570.00 3" Thick Bit Path 115 Tons $ 100.00 $ 11,500.00 Curb and Gutter 15 LF $ 45.00 $ 675.00 Concrete Pedestrian Ramp 1 LS $ 2,500.00 $ 2,500.00 Storm Sewer 1 LS $ 2,500.00 $ 2,500.00 Erosion Control 1 LS $ 5,000.00 $ 5,000.00 Signage 2 EA $ 250.00 $ 500.00 Striping j 126 SF $ 1.75 $ 220.50 Restoration • • • 0.2 Acre $ 7,500.00 $ 1,500.00 1 Wetland Deliniation 1 LS $ 2,000.00 $ 2,000.00 Overhead Project Total (2016 Cost) Project Total (2018 Cost) 1 15% I I 3%/YR 1 $ 7,654.58 $ 60,685.08 $ 64,380.80 Only City Portion of Trail ( North -575 LF) -Hakanson 1111Anderson